Mohn v. CBS Corp.

2018 WI App 62, 921 N.W.2d 16, 384 Wis. 2d 271
CourtCourt of Appeals of Wisconsin
DecidedAugust 7, 2018
DocketAppeal No. 2017AP861
StatusPublished

This text of 2018 WI App 62 (Mohn v. CBS Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mohn v. CBS Corp., 2018 WI App 62, 921 N.W.2d 16, 384 Wis. 2d 271 (Wis. Ct. App. 2018).

Opinion

PER CURIAM.

¶ 1 Mary Ellen Mohn, both individually and as the personal representative for the Estate of Thomas L. Mohn, her husband (collectively, "Mohn"), appeals an order granting summary judgment in favor of Sprinkmann Sons Corporation. The trial court granted summary judgment on the grounds that Mohn's claims against Sprinkmann were barred pursuant to the construction statute of repose set forth at WIS. STAT. § 893.89 (2015-16).1

¶ 2 Mohn argues that the protections of the statute of repose do not extend to Sprinkmann. Additionally, Mohn raises constitutional challenges to the statute of repose, asserting that it violates the right to remedy clause of the Wisconsin Constitution as well as equal protection rights. We affirm.

BACKGROUND

¶ 3 This lawsuit stems from Mohn's claim that Mr. Mohn was exposed to asbestos while working at construction sites between 1960 and 1980. He was diagnosed with malignant lung cancer in February 2009 and died in April 2009.2 Mohn then filed this action in February 2012 against numerous manufacturers and suppliers of asbestos products that were involved in construction projects where Mr. Mohn worked.

¶ 4 With regard to the claims against Sprinkmann, discovery in the case revealed the following link between Sprinkmann and Mr. Mohn's work history:

• Mr. Mohn was employed by Power Service Corporation during the 1960s;
• Power Service Corporation, along with Allis Chalmers, was involved in the construction of a nuclear power plant in Genoa, Wisconsin;
• Allis Chalmers ordered insulated turbine blankets from Sprinkmann that contained asbestos for use in the construction of a turbine-generator unit at the Genoa power plant project; and
• Mr. Mohn worked as a heavy equipment operator during the construction of the Genoa power plant in the mid-1960s.

Construction of the power plant was substantially completed by the late 1960s.

¶ 5 Sprinkmann filed a motion for summary judgment, heard in November 2015, asserting that Mohn's claims against it were barred by the construction statute of repose. The statute provides that after ten years3 following the substantial completion of improvements to real property, no cause of action may accrue against "any person involved" in those improvements for injuries arising out of any defect related to the construction of those improvements. WIS. STAT. § 893.89(2). However, this bar does not include actions against "manufacturer[s] or producer[s]" of defective materials. Id.

¶ 6 In its motion, Sprinkmann asserted that it is covered by the protections afforded by the statute because its involvement in the construction of the power plant was limited to furnishing defective materials-the asbestos-containing turbine blankets-not manufacturing the materials. Furthermore, Sprinkmann asserted that Mohn's claim was made outside of the ten year exposure period established by the statute, in that the power plant had been completed by the late 1960s. The trial court initially denied Sprinkmann's motion; Sprinkmann filed a motion for reconsideration.4

¶ 7 Prior to the trial court issuing its ruling on the motion for reconsideration, the parties entered into a stipulation of certain facts related to the motion. Included in that stipulation were the following facts:

• The original construction of the nuclear power plant in Genoa, as well as the construction of the turbine-generator unit, were improvements to real property;
• This construction occurred during the mid-to-late-1960s;
• Sprinkmann furnished materials, including the insulated turbine blankets that allegedly contained asbestos, during the original construction of the power plant;
• There is no evidence that Sprinkmann performed any work on the improvements during the original construction of the power plant, nor any subsequent repair work on that project; and
• There is no evidence that Sprinkmann supplied any insulation products to the power plant after 1969.

¶ 8 Upon reconsideration, the trial court identified that it had made an error of law in denying Sprinkmann's summary judgment motion. Ultimately, relying on Kohn v. Darlington Community Schools , 2005 WI 99, 283 Wis. 2d 1, 698 N.W.2d 794, as well as the stipulation of the parties, the trial court found that the statute did apply to protect Sprinkmann from liability: the turbines constructed at the power plant were improvements to real property; Sprinkmann had been involved only in furnishing the defective materials-turbine blankets containing asbestos-with regard to the improvements; and that Mohn's claim had been filed after the ten year period following the completion of the improvements. Therefore, the trial court found that Sprinkmann met the requirements of WIS. STAT. § 893.89(2). As a result, the court granted summary judgment in Sprinkmann's favor.

¶ 9 Additionally, Mohn argued during the summary judgment proceedings against the constitutionality of WIS. STAT. § 893.89, asserting that it violates the right to remedy clause of the Wisconsin Constitution. However, the trial court, relying on precedent that upheld the constitutionality of the statute, rejected Mohn's constitutional challenge. This appeal follows.

DISCUSSION

1. The trial court did not err in granting summary judgment in favor of Sprinkmann on the grounds that the statute of repose bars Mohn's claims against Sprinkmann.

¶ 10 Mohn argues that the circumstances surrounding Sprinkmann's involvement in the construction of the power plant do not meet all of the requirements for protection under the statute of repose, and thus the trial court erred in granting Sprinkmann's motion for summary judgment.

¶ 11 A trial court may grant a motion for summary judgment only if "the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." WIS. STAT. § 802.08(2). Once a moving party "has made a prima facie case for summary judgment," the trial court must then review the parties' submissions to determine whether there are "disputed material facts, or undisputed material facts from which reasonable alternative inferences may be drawn, sufficient to entitle the opposing party to a trial." Clark v. Erdmann , 161 Wis. 2d 428, 441-42, 468 N.W.2d 18 (1991). We review the trial court's decision to grant summary judgment independently, applying that same methodology. Kohn

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Pettit
492 N.W.2d 633 (Court of Appeals of Wisconsin, 1992)
Gasper Ex Rel. Martin v. Parbs
2001 WI App 259 (Court of Appeals of Wisconsin, 2001)
Kohn v. Darlington Community Schools
2005 WI 99 (Wisconsin Supreme Court, 2005)
Clark v. Erdmann
468 N.W.2d 18 (Wisconsin Supreme Court, 1991)
Fond Du Lac County v. Town of Rosendale
440 N.W.2d 818 (Court of Appeals of Wisconsin, 1989)
Swanson Furniture Co. of Marshfield, Inc. v. Advance Transformer Co.
313 N.W.2d 840 (Wisconsin Supreme Court, 1982)
Kohn v. Darlington Community Schools
2005 WI 99 (Wisconsin Supreme Court, 2005)
Peter v. Sprinkmann Sons Corp.
2015 WI App 17 (Court of Appeals of Wisconsin, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2018 WI App 62, 921 N.W.2d 16, 384 Wis. 2d 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mohn-v-cbs-corp-wisctapp-2018.