Mohican Oil & Gas, LLC. v. Scorpion Exploration & Prodction, Inc.

337 S.W.3d 310, 2011 WL 242424
CourtCourt of Appeals of Texas
DecidedMay 4, 2011
Docket13-09-00516-CV
StatusPublished
Cited by11 cases

This text of 337 S.W.3d 310 (Mohican Oil & Gas, LLC. v. Scorpion Exploration & Prodction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mohican Oil & Gas, LLC. v. Scorpion Exploration & Prodction, Inc., 337 S.W.3d 310, 2011 WL 242424 (Tex. Ct. App. 2011).

Opinion

OPINION

Opinion by

Justice RODRIGUEZ.

This is an appeal from a jury trial on disputes over an oil and gas drilling contract. By one issue, appellant Mohican Oil & Gas, LLC, plaintiff and counter-defendant in the trial court, challenges as legally and factually insufficient the evidence supporting the jury’s award of damages and attorneys’ fees to appellee Chapeo, Inc., defendant and counter-plaintiff in the trial court. By one issue, cross-appellant Scorpion Exploration & Production, Inc., defendant and counter-plaintiff in the trial court, argues that the trial court erred in awarding attorneys’ fees to cross-appellee Mohican and not Scorpion because Scorpion, not Mohican, was the prevailing party in the contract litigation. We affirm, in part, reverse and render, in part, and reverse and remand, in part.

I. BACKGROUND

Mohican is an oil and gas exploration and development company. Scorpion is a drilling contracting company, and Chapeo is a well operating company; both are owned and run by Lauro Chapa. In the fall of 2006, Mohican and Scorpion entered into a turnkey contract 1 for the drilling of Olmitos No. 2, a directional oil and gas well 2 in Webb County, Texas. Under the contract, Mohican, as operator, agreed to pay Scorpion, as drilling contractor, a lump sum of $1.158 million to drill the well. The parties agreed that Chapeo, Chapa’s other company, would be the listed with the Texas Railroad Commission (TRC) as the operator of Olmitos No. 2.

Drilling commenced on Olmitos No. 2 on November 21, 2006. Throughout December 2006, Scorpion encountered several difficulties in setting the intermediate casing and proceeding to production depths, 3 including premature flowing and the well-bore falling in on itself. 4 The difficulties *314 were eventually resolved, and the well reached its total depth on January 15, 2007.

Mohican paid Scorpion the first half of the lump sum contract price up front and the second half when the well reached its total depth. In February 2007, Scorpion demanded 'approximately $836,000 from Mohican in addition to the lump sum contract price, claiming that the contract converted to daywork basis when the drilling complications began in early December 2006. 5 Mohican refused to pay the additional sum, and Chapeo refused to turn over operatorship of Olmitos No. 2 until Mohican did so. 6

In March 2007, Mohican filed a petition for declaratory judgment against Scorpion and Chapeo. 7 In its petition, Mohican also alleged breach of contract, 8 fraud, fraud in the inducement, and sought a verified accounting. Scorpion and Chapeo then filed counterclaims to Mohican’s suit. Scorpion alleged breach of contract, 9 fraud, and quantum meruit, in connection with Mohican’s refusal to pay the additional $836,000 and other claimed wrongs under the contract, and requested judicial foreclosure on its mechanic’s lien on Olmitos No. 2 and an assigned claim Scorpion purchased from a Mohican creditor. Chapeo alleged breach of contract and quantum meruit, claiming that Mohican refused to pay Chapeo for its services as the TRC-listed operator.

In May 2009, Mohican’s claims and Scorpion and Chapco’s counterclaims were tried to a jury. At trial, the following facts, relevant to this appeal, were in dispute: (1) whether the contract converted from turnkey to daywork when Scorpion encountered certain problems in the drilling process; (2) whether Mohican was obligated under the contract to provide Scorpion with a mudlogger 10 to assist Scorpion *315 in the drilling of the well 11 ; (3) whether the absence of a mudlogger caused delays that were - attributable to Mohican and caused Scorpion damages; and (4) whether Chapeo performed any compensable functions as TRC-listed operator.

At the close of evidence, the trial court granted Scorpion’s motion for directed verdict on all of Mohican’s claims except its claim for declaratory relief. 12 Mohican stipulated at trial that it had an oral agreement with Chapeo to serve as the TRC-listed operator for Olmitos No. 2. There was, therefore, no liability question submitted to the jury on Chapco’s breach of contract counterclaim; in this regard, the jury was only questioned on the amount of damages Chapeo proved up. The trial court thus submitted to the jury questions on: Mohican’s request for declaratory relief 13 ; Scorpion’s breach of contract 14 and fraud counterclaims; ' and the relevant damages at issue. 15

*316 In its verdict, the jury answered “yes” to Mohican’s declaratory relief questions. The jury also found that Mohican had breached the drilling agreement with Scorpion but that the breach was not material and that Mohican had not committed fraud against Scorpion. In response to the damages questions, the jury awarded $139,120 in damages to Scorpion and $60,000 in damages to Chapeo. After the jury’s verdict, the attorneys for all parties submitted affidavits to the trial court attesting to their fees and expenses in litigating the parties’ claims and counterclaims. 16

In its judgment, the trial court found that: (1) Mohican had established its entitlement to declaratory relief 17 ; (2) Scorpion had established its breach of contract claim against Mohican and should be awarded $139,120 18 ; and (3) Chapeo should be awarded $60,000 for Mohican’s breach of their agreement. 19 The trial court then found that Mohican was the prevailing party in its case against Scorpion and should be awarded attorneys’ fees in the amount of $163,037.87. The trial court also awarded Chapeo attorneys’ fees in the amount of $72,146.89. Chapco’s total award from Mohican, including prejudgment interest, was calculated to be $138,763.32. After offsetting Mohican’s attorneys’ fees award by the damages it owed to Scorpion, the trial court concluded that Mohican should recover $8,481.87 from Scorpion.

After the trial court issued its judgment, Scorpion filed a motion to modify, correct, or reform the judgment, arguing that the trial court erred in finding that Mohican was the prevailing party in the litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
337 S.W.3d 310, 2011 WL 242424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mohican-oil-gas-llc-v-scorpion-exploration-prodction-inc-texapp-2011.