Moen Inc. v. Stanadyne Partners
This text of 191 A.D.2d 338 (Moen Inc. v. Stanadyne Partners) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
—Order, Supreme Court, New York County (Beverly S. Cohen, J.), entered October 28, 1992, which denied plaintiffs motion for a stay of arbitration and granted defendants’ cross motion to compel arbitration, unanimously affirmed, with costs.
Arbitration, properly directed pursuant to section 9.02 of the parties’ agreement, provides for the submission of all environmental matters arising after closing to a designated arbitrator to determine "the scope and estimated cost” of any environmental cleanup or remediation needed. The dispute in question here is environmental in nature and falls squarely within that section. "As we have consistently held, the court’s inquiry is limited to whether or not the dispute is encompassed by the governing arbitration provision, while interpretation of the provisions of the contract is for the arbitrator” (Rio Algom v Sammi Steel Co., 168 AD2d 250, 251, lv denied 78 NY2d 853). Plaintiff’s request for a declaratory judgment as to whether certain claimed items of an environmental nature constitute breaches of the contract would, in effect, have this Court substitute its judgment for that of the arbitrator. Concur — Murphy, P. J., Carro, Rosenberger, Ross and Kassal, JJ.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
191 A.D.2d 338, 595 N.Y.S.2d 189, 1993 N.Y. App. Div. LEXIS 2741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moen-inc-v-stanadyne-partners-nyappdiv-1993.