Moduform, Inc. v. Harry H. Verkler Contractor, Inc.

681 N.E.2d 243, 1997 Ind. App. LEXIS 748, 1997 WL 318063
CourtIndiana Court of Appeals
DecidedJune 13, 1997
Docket34A02-9602-CV-98
StatusPublished
Cited by11 cases

This text of 681 N.E.2d 243 (Moduform, Inc. v. Harry H. Verkler Contractor, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moduform, Inc. v. Harry H. Verkler Contractor, Inc., 681 N.E.2d 243, 1997 Ind. App. LEXIS 748, 1997 WL 318063 (Ind. Ct. App. 1997).

Opinion

OPINION

NAJAM, Judge.

STATEMENT OF THE CASE

ModuForm, Inc. (“ModuForm”) appeals from the trial court’s denial of its motion for summary judgment and grant of summary judgment in favor of both Harry H. Verkler Contractor, Inc. (“Verkler”) and American Casualty Company of Reading, Pa. (“American Casualty”). Verkler was hired by the Howard County Jail and Juvenile Detention Building Corporation (“Project Owner”) to serve as the general contractor for construction of the Howard County Jail and Juvenile Detention Center (the “Project”). Pursuant to Indiana Code § 36-1-12-13.1, Verkler obtained a payment bond from American Casualty, the surety. ModuForm, a furniture manufacturer, had filed a complaint against the bond seeking $145,936.36 in payment for furniture it had supplied to First Office Fur-nitures, another subcontractor, for completion of the Project. The court granted Verkler and American Casualty’s motion for summary judgment on the basis that Modu-Form had failed to pursue its claim within 60 days of the final completion and acceptance of the Project as required by Indiana Code § 36-l-12-13.1(e).

We reverse and remand.

ISSUE

The sole issue presented for our review is whether the trial court erred when it granted summary judgment in favor of Verkler and American Casualty. 1

FACTS

The facts most favorable to ModuForm show that in 1992, Verkler entered into an agreement with the Project Owner to serve as a general contractor for construction of the Project. Verkler was responsible for providing the furniture under the contract and subcontracted with First Office Furnishings for that purpose. First Office Furnishings, in turn, entered into an agreement with ModuForm to provide the furniture and materials. First Office Furnishings later substituted Jasper Seating for ModuForm as the supplier of 44 “Item 26” chairs.

ModuForm completed delivery of its furniture to the Project on May 21, 1993. Jasper Seating made its final shipment of furniture *246 to the Project on October 15, 1993. Prior to delivery of the furniture, on May 10, 1993, the Project Owner President, Joseph Davis, the Project Owner Secretary, John Schultz, the architect, Joseph Mrak, and the President of the Board of Commissioners of Howard County, James Shearer, signed an affidavit which declared the Project “complete and ready for occupancy.”

In July of 1993, Verkler paid First Office Furnishings for the materials it had supplied to the Project, including the $145,936.63 for the furniture supplied by ModuForm. First Office Furnishings then declared bankruptcy, ModuForm was not paid, and the Project retained all of the furniture. On August 13, 1993, ModuForm notified the Project Owner and Verkler that it had not been paid. Seven days later, ModuForm notified Verifier’s counsel and American Casualty that it had not been paid for the materials it supplied to the Project. None of the parties responded to these notices.

Then, on October 13, 1993, ModuForm submitted to the Project Owner signed duplicate statements of its Notice of Default and Statement of Amount Due. American Casualty’s and Verkler’s counsel requested additional information on the amount owed. On November 18, 1993, ModuForm filed suit against Verkler and American Casualty. Cross-motions for summary judgment were filed, and the trial court granted summary judgment in favor of Verkler and American Casualty. The court’s order states in part:

3. ModuForm, so as to be able to pursue a valid claim under I.C. 36-1-12, and to avoid waiving its claim and being estopped from pursuing it, had to pursue its court action against American Casualty as the surety and Verkler within sixty (60) days of the date of final completion and acceptance of the Howard County Jail and Juvenile Detention Center Building Corporation, pursuant to I.C. 36-l-12-13.1(e).
4. For the purpose of I.C. 36-1-12-13.1, the date of final completion and acceptance of the Howard County Jail and Juvenile Detention Center Building Corporation was May 10,1993.
5. ModuForm failed to initiate its court action within sixty (60) days of May 10, 1993, as required by I.C. 36-l-12-13.1(e), and consequently, ModuForm has waived its right to pursue its bond claim in this matter, and is estopped, by operation of law from pursuing its claim on the bond against American Casualty and Verkler.
* * * *
7. The Court, being duly advised in the premises, finds that there are no genuine issues of material fact that would preclude the entry of summary judgment. The Court hereby GRANTS summary judgment in favor of the Defendants Verkler and American Casualty and DENIES Plaintiff ModuForm’s summary judgment motion.

Record at 544-45. ModuForm appeals from that decision.

DISCUSSION AND DECISION

Standard of Review

When reviewing the trial court’s ruling on a motion for summary judgment, this court applies the same standard as the trial court. L.E. Serv., Inc. v. State Lottery Comm’n of Indiana, 646 N.E.2d 334, 339 (Ind.Ct.App.1995), trans. denied. Summary judgment is appropriate if the designated evidentiary matter shows that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. Ind. Trial Rule 56(C). When reviewing cross-motions for summary judgment, the inquiry remains the same: whether a genuine issue of material fact exists which requires resolution by the trier of fact. L.E. Serv., Inc., 646 N.E.2d at 339. When the parties do not dispute the facts material to the claim, our task is to determine whether the trial court correctly applied the law to the undisputed facts. Id.

Final Completion and Acceptance

ModuForm contends that it has satisfied all the requirements of Indiana Code § 36-1-12-13.1 for bringing a lawsuit against American Casualty and Verkler. This statute provides in part:

(d) A person to whom money is due for labor performed, material furnished, or *247 services provided shall within sixty (60) days after the completion of the labor or service, or within sixty (60) days after the last item of material has been furnished, file with the board signed duplicate statements of the amount due. The board shall forward to the surety of the payment bond one (1) of the signed duplicate statements. However, failure of the board to forward a signed duplicate statement does not affect the rights of a person to whom money is due. In addition, a failure to forward the statement does not operate as a defense for the surety.
(e) An action may not be brought against the surety until thirty (30) days after the filing of the signed duplicate statements with the board. If the indebtedness is not paid in full at the end of that thirty (30) day period the person may bring an action in court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rockwell v. MSD Southwest Allen County
737 N.E.2d 829 (Indiana Court of Appeals, 2000)
T.W. Thom Construction, Inc. v. City of Jeffersonville
721 N.E.2d 319 (Indiana Court of Appeals, 1999)
Sweet v. Art Pape Transfer, Inc.
721 N.E.2d 311 (Indiana Court of Appeals, 1999)
Noble County Board of Commissioners v. Fahlsing
714 N.E.2d 1134 (Indiana Court of Appeals, 1999)
Schafer v. Sellersburg Town Council
714 N.E.2d 212 (Indiana Court of Appeals, 1999)
Union Township School Corp. v. State Ex Rel. Joyce
706 N.E.2d 183 (Indiana Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
681 N.E.2d 243, 1997 Ind. App. LEXIS 748, 1997 WL 318063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moduform-inc-v-harry-h-verkler-contractor-inc-indctapp-1997.