Modern Systems Construction & Supply Co. v. State

5 Ill. Ct. Cl. 215, 1926 Ill. Ct. Cl. LEXIS 4
Court of Claims of Illinois·Decided September 14, 1926·No. No. 823·Published

Opinion

Mr. Justice Thomas

delivered the opinion of the court:

On June 15, 1921, the Modern Systems Construction and Supply Company, claimant herein, entered into a contract with the State of Illinois whereby it agreed to provide all the materials and to perform all work for the general work of buildings for the Alton State Hospital at Alton, Illinois, for $326,583.00. The work was to be done according to the drawings, plans and specifications therefor prepared by the Division of Architecture of the Department of Public Works and Buildings, and was to be substantially completed by March 1, 1922. The contract fixed the prices of labor and materials upon which the total contract price was based and bound the contractor in no event to pay more than 65 cents per hour for hod carriers and mortar mixers, 62% cents for other common labor and $1 per hour for brick masons, stone masons, iron workers, lathers, sheetmetal workers, carpenters, painters and plasterers, and provided that the net savings effected should be deducted from the contract price. Under the terms of the contract the time of completion of the work might be extended by the supervising architect, and it was extended by him 60 days.

Two other contracts were entered into between claimant -and the State, the first on October 25, 1921, for the installation of bell traps and drain pipes for which claimant was to receive $2000.00, and the second on November 5, 1921, for certain substituted materials for which claimant was to receive $1400.00.

On December 9,1921, the State let the contract for the general plumbing work of the entire building to E. Baggott & Co. In the latter part of March, 1922, the plumbers went on a strike. In October of that year E. Baggott & Co. gave up their contract and the State took over the plumbing work and later finished it.

Claimant contends that the failure to have the plumbing done in proper time compelled claimant to delay its work and that during such delay the prices of materials and labor increased, its machinery and fixtures were idle, its organization disrupted and its money tied up, etc., for which it has filed This suit. Attached to its declaration are 22 separate claims or “invoices” aggregating the sum of $40,144.53 which claimant contends the State owes it. This amount includes certain items mentioned in the invoices for extra work and material furnished by claimant and for which it had no written contract with the State.

The Attorney General filed a general demurrer to the declaration. After this demurrer was filed it was stipulated by the parties that invoices 1, 4, 5, 6, 7, 8, 9, 10 and 15 and also an item of $379.46, which was not paid on final certificate because of lack of funds, are correct and should be allowed. The total amount of this item and invoices, which the Attorney General agrees is a just claim against the State, is $4,371.26. This stipulation of the Attorney General is án admission that there is some equity in claimant’s case, and the demurrer will be overruled and the cause heard as if the general issue had been filed by the State.

In its declaration claimant alleges there was certain other work in and about the buildings of the State at Alton and also extra work done by it for which no written contracts' were entered into between it and the State.

Both claimant and the State have taken evidence, including a large number of exhibits, on the question of these verbal agreements. After a careful consideration of all the evidence and exhibits introduced in this case,* both on the part of the claimant and of the State, we find that claimant has failed to prove, by a preponderance of the evidence, the verbal agreements to do such extra work, and the claims for it are refused.

The invoices not included in the stipulation are 2, 3, 11, 12, 13, 14, 16, 17, 18, 19, 20, 21 and 22 and they will be decided in that order.

Invoice No. 2 is a claim for clearing out tunnels and openings left for the plumbers and for bricking up these openings. The specifications require the contractor to leave openings for other trades to do their work and then to close up such openings so that the several parts will properly fit together. The specifications also require the contractor to keep clean all parts of the buildings, and the tunnels are a part of the buildings. While the evidence shows there was an oral understanding between the claimant and a representative of the State that larger openings were to be left than the plans and specifications called for, yet the evidence does not show this made any difference in the cost. And, as the materials listed and claimed for in this invoice were all necessary to the final completion of the walls, leaving larger openings than were specified would not necessarily add anything to their cost. It was the duty of claimant to clean out the tunnels before its contract was completed, and there is no evidence showing the cost of cleaning out the tunnels was greater than it would have been had the openings been left the size designated in the specifications. If there was a difference in the cost, there is no evidence from which this court can determine the amount. The claim for invoice No. 2 is refused.

Invoice No. 3, is a claim for levelling basement floor after the water line was laid. The evidence shows that the basement floor was in the same condition when the water line was laid that it was when the claimant finished excavating, except the rubbish that had fallen while the building was going up. The specifications required the contractor to do the work mentioned in this invoice if the architect so directed, which he did. This work being required of claimant under its contract, its claim therefor is refused.

Invoice No. 11 is a claim for $10,483.14 for increased cost of plastering. Under its contract with the State all plastering was to be done by claimant. Claimant’s contention is, as we understand it, that in February, 1922, it contracted with one Thomas Hawkins to do this plastering for 37 cents per square yard; that Hawkins was ready to begin the job when the plumbers ’ strike stopped all work and nothing more was done till the following October when claimant again contracted with Hawkins to do the plastering as a day labor proposition ; that claimant kept an accurate account of the work done under this contract with Hawkins and that the plastering cost 96% cents per square yard under it instead of 37 cents, the price for which Hawkins first agreed to do it. The difference between these two prices is the basis of Invoice No. 11. Article 4 of claimant’s contract with the State fixes the prices of labor and material upon which the total contract price is based and provides the State shall have the benefit of any savings effected by claimant in securing labor or materials at less than those prices. There is no evidence showing how claimant paid Hawkins, whether by the hour or by the day. If claimant paid him no more per hour for labor than its contract with the'State fixes as the basis of the amount to be paid by the State for the entire work, under no theory would the State be liable for any loss sustained by claimant. We are of the opinion that claimant has failed to make any proof upon which the claim for Invoice No. 11 can be allowed and it is therefore refused.

Invoice No. 12 is for storage and extra cost of mill work due to delay on account of the plumbers’ strike.

Free access — add to your briefcase to read the full text and ask questions with AI