Modern Exploration, Inc. v. Maddison

708 S.W.2d 872
CourtCourt of Appeals of Texas
DecidedApril 24, 1986
Docket13-85-092-CV
StatusPublished
Cited by14 cases

This text of 708 S.W.2d 872 (Modern Exploration, Inc. v. Maddison) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Modern Exploration, Inc. v. Maddison, 708 S.W.2d 872 (Tex. Ct. App. 1986).

Opinion

OPINION

BENAVIDES, Justice.

Modern Exploration, Inc. and Modern Drilling, Inc., (“Modern”) appeal the ruling below terminating part of their oil and gas lease from Paul and Melba Maddison. Modern raises issues involving the sufficiency of the evidence, the construction of the lease, the submission of special issues on damages, and the admissibility of testimony about attorney’s fees from an expert witness not listed in response to a discovery question. We reverse and render the judgment in part, modify it in part, and as modified, affirm the remaining portion of the trial court judgment.

Paul Maddison and his wife Melba own a 200-acre tract of land in Gonzales County, Texas. Mr. Maddison contacted Gary Yost to discuss leasing the oil and gas interests to Yost. Yost, who did business as Modern Exploration, Inc., and Modern Drilling, Inc., met with Maddison and Maddison’s attorney in September, 1980. After hours of negotiations, the two men drew up a rough draft of the lease. The parties also signed a two-page memorandum, intended only as a summary of the parties’ actual agreement, to enable Yost to acquire financial backing for exploratory drilling on the land. The actual, final lease was thirteen pages long and was apparently signed several weeks later. 1 It contemplated the drilling of more than one (disputed) well on the 200-acre Maddison tract.

Modern drilled the first well on time, and it proved successful. Under the terms of the lease, Modern had 270 days from “the completion of drilling on the first well” to begin drilling a second well, or the lease would terminate as to the acreage not drilled upon. Modern reported to the Railroad Commission that it completed drilling the first well on 1-24-81. Shortly after the first well began producing oil, Mr. Maddi-son’s attorneys notified Modern that they would calculate the 270-day period from 1-24-81.

Modern had not begun drilling the second well 270 days after 1-24-81. On 10-26-81, Maddison claimed the lease had terminated on all but the acreage surrounding the producing well and ordered Modern off the remaining acres. Modern then sued for a declaratory judgment that the lease remained fully in effect. Modem claimed that it did not actually complete drilling the first well until 2-7-81, explaining that the 1-24-81 date was merely the date when the deepest well depth was reached. Modern had then plugged the hole with cement, and drilled through the cement plug on 2-7-81. Using 2-7-81 as the date when it completed drilling the well, Modem claimed it had until 11-4-81 to begin drilling the second well. Thus, Modern argued at trial, Maddi-son had wrongfully prevented Modem from timely drilling the second well.

The jury returned a verdict generally favorable to the Maddisons, and the trial court entered judgment that the lease had terminated on all but the eighty acres surrounding the first well.

Modern's first two points of error allege that the parties made a mutual mistake (or that Maddison acted fraudulently) by including the term “completion of drilling on the well” in the lease as the 270-day triggering date; Modern contends that the parties actually agreed that the triggering date would be that of the “completion of the well.” Since there was no real dispute that the well was completed on 2-11-81 (the date production actually began), Modern argues that Maddison wrongfully prevented Modern from drilling the second well since 270 days from 2-11-81 had not elapsed as of 10-26-81, the date Maddison ordered Modern off the undeveloped acreage.

*875 Modern’s first point of error alleges that the trial court erred in overruling its motion for judgment n.o.v. because the evidence was legally insufficient to support the jury’s finding that the parties agreed to “completion of drilling” rather than “completion of the well.” Modern’s second point of error alleges that the court erred in overruling its motion for new trial because the evidence was factually insufficient to support the same finding.

Special Issue No. 1 inquired:

Do you find from a preponderance of the evidence that at the time the lease was executed Modern and the defendants acting by and through Paul Maddison, Sr. had agreed that the second well was to be drilled within 270 days following completion of the first well or that the second well was to be commenced within 270 days following completion of drilling of the first well?
Answer: Completion of the first well or completion of drilling of the first well.

The jury answered, “Completion of drilling of the first well.”

In considering a “no evidence” or “insufficient evidence” point of error, we will follow the well-established test set forth in Dyson v. Olin Corp., 692 S.W.2d 456 (Tex.1985); Glover v. Texas General Indemnity Co., 619 S.W.2d 400 (Tex.1981); Garza v. Alviar, 395 S.W.2d 821 (Tex.1965); Allied Finance Co. v. Garza, 626 S.W.2d 120 (Tex.App.—Corpus Christi 1981, writ ref’d n.r.e.); Calvert, No Evidence and Insufficient Evidence Points of Error, 38 Tex.L. Rev. 361 (1960).

The evidence at trial in support of the jury’s finding meets both the factual and legal sufficiency tests. The oil and gas lease contains the term “completion of drilling,” and Maddison testified that the true agreement of the parties was “completion of drilling” all along:

Q. (By opposing counsel) It is your testimony now that the true agreement was that you had completion of drilling in your mind all the time; is that correct?
A. That is a positive fact.

Maddison’s son, who had a one-fourth interest in the total royalty paid under the lease, testified that, when he signed the lease, he understood that Modern was to commence drilling on the second well within 270 days after the completion of drilling on the first well. He stressed that he was aware of the differences between “completion of drilling” and “completion.”

Modern’s evidence directly conflicted with the Maddisons’ testimony that the lease correctly reflected the parties’ intent that “completion of drilling” was to be the triggering language. Yost (same as Modern) testified that the parties intended “completion of the well” all along, and Modern introduced into evidence the notes taken by Maddison’s attorney during the preliminary negotiations and the two-page memorandum the attorney prepared after these negotiations were over.

Yost was to use the memo to acquire funding to commence drilling on the first well. Although the fourth paragraph of the memorandum of September 23, 1980, provides that the second well “shall be spudded within nine months of the completion of the first well” (not “completion of drilling”), the last paragraph provides:

This is not intended to be a complete synopsis of the lease nor is it intended to set out all the terms of the lease.

Free access — add to your briefcase to read the full text and ask questions with AI