Mobley Construction Co. v. United States

68 Fed. Cl. 434, 2005 U.S. Claims LEXIS 319, 2005 WL 2853699
CourtUnited States Court of Federal Claims
DecidedOctober 28, 2005
DocketNo. 04-1739L
StatusPublished
Cited by1 cases

This text of 68 Fed. Cl. 434 (Mobley Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mobley Construction Co. v. United States, 68 Fed. Cl. 434, 2005 U.S. Claims LEXIS 319, 2005 WL 2853699 (uscfc 2005).

Opinion

ORDER AND OPINION

HODGES, Judge.

Plaintiff Mobley Construction Company filed this claim against the United States under the takings clause of the Fifth Amendment to the United States Constitution. The Government had issued plaintiff a series of permits since the 1930’s to dredge portions of the White River in Arkansas. The permit the Army Corps of Engineers authorized in November 1995 imposed two new restrictions. Special Condition 2 is the limitation in dispute in this case.

Special Condition 2 prohibited dredging along twenty miles of the White River during March, April, and May of each year. This period coincided with fish spawning in the area. Plaintiff complains that Mobley’s not being able to dredge for three months each year created a temporary or a permanent taking by the Government because the restriction prevented profitable operations in the White River. Mobley ceased operations there in 2000.

Defendant argued in its Motion to Dismiss that we lack jurisdiction because the statute of limitations has run on the alleged taking. We grant the Government’s Motion to Dismiss.

BACKGROUND

Plaintiff Mobley Construction has been engaged in mining sand and gravel for commercial production since the 1930’s. Compl. ¶ 7. Persons who conduct dredging operations must obtain permits from the Army Corps of Engineers pursuant to Section 404 of the Clean Water Act, 33 U.S.C. § 1344, and the Rivers and Harbors Act of 1899, 33 U.S.C. § 403. The Corps leased to Mobley the right to dredge the White River in Arkansas for sand and gravel and to remove it from the riverbed in designated areas.1 Compl. ¶ 7. Plaintiff has had at least three government-issued dredging leases.

Mobley sought routine renewal of its permit with the Corps in 1995. Compl. ¶ 9. The Corps issued the permit but for the first time restricted dredging to protect fish spawning areas. Special Condition 2 provided, “[n]o dredging will be allowed from March 1 until May 31 of each year between River Miles 120 — 125 and 259 — 274.0 to protect fish spawning.” Compl. Ex. A at 1. Mobley accepted the permit. Compl. ¶ 9.

Mobley sought removal of the permit restrictions in December 1998. Mr. Mobley sent a memorandum to the Corps during permit renewal discussions, contending that the limitation on his dredging operations conflicted with the company’s purpose in obtaining the dredging permit. Compl. ¶ 12(a). He declared that the restriction was unnecessary because the Corps lacked scientific proof that Mobley’s business so interfered with spawning as to endanger the fish population. Compl. ¶ 12(b).

Mr. Mobley noted that sufficient river levels were essential for plaintiff to obtain access to the sand and gravel it needed. Opti[436]*436mal yearly levels of river flow coincided with the months restricted by Special Condition 2. Compl. ¶ 11. The White River is accessible only between January and May, so this gave plaintiff two months to conduct its dredging. Mobley Aff., Mar. 28, 2005 ¶ 4. Mobley’s inability to supply sand and gravel for construction and for other commercial endeavors caused it to lose profits. Plaintiff discontinued its White River operations in 2000. Mobley Aff. ¶ 6.

The Corps of Engineers considered Mobley’s concerns but ultimately issued plaintiffs new permit with the same restrictions. Mobley appealed the restrictions through the Corps of Engineers’ process, and the Corps issued a final administrative ruling denying plaintiffs appeal in 2003.2 Compl. ¶ 13. Mobley accepted the renewal permit containing Special Condition 2 in February 2004. Compl. ¶ 15.

DISCUSSION

The Government argues the alleged taking occurred in November 1995, when the appropriate official of the Corps of Engineers issued the permit with the condition that Mobley complains of.3 Special Condition 2 was a partial denial of plaintiffs 1995 permit application for the right to dredge ninety-nine miles of riverbed. This would have given rise to Mobley’s regulatory takings claim, according to defendant. Mobley did not appeal the denial in 1995, but expressed concerns later that the restrictions on dredging were causing economic hardship for the company.

Plaintiff disputes defendant’s argument that its suit is untimely. It suggests later times for accrual of the taking. The best date for the taking is August 2003, Mobley contends, because the Corps denied its appeal then. Plaintiff relies on Dickinson and similar eases to argue that its takings claim did not accrue until a continuing physical process had stabilized. United States v. Dickinson, 331 U.S. 745, 749, 67 S.Ct. 1382, 91 L.Ed. 1789 (1947). Plaintiff contends the events leading to its taking claim did not “stabilize” until August 2003, because that is when the Corps finally denied plaintiffs appeal. Other dates that plaintiff proposes for the taking are October 2000, when the company ceased operations on the White River, or February 1999, when Mr. Mobley sent a memorandum to the Corps expressing concern about the permit’s economic impact on his company.

Plaintiff argues that if the court finds the accrual date coincided with issuance of the 1995 permit, we should equitably toll the statute of limitations. Mobley asserts that it reasonably could not have known the economic consequences of Special Condition 2 until 1999 at the earliest. Defendant disputes Mobley’s argument that this case presents a Dickinson situation, or that plaintiff could not have known of the alleged taking earlier than December 1998.

Claim Accrual

Takings cases brought in this court are subject to a six-year statute of limitations. See 28 U.S.C. § 2501 (“[Ejvery claim of which the United States Court of Federal Claims has jurisdiction shall be barred unless the petition thereon is filed within six years after such claim first accrues.”). Congress’ limited waiver of sovereign immunity for claims against the Government requires that the court adhere strictly to the statute. Soriano v. United States, 352 U.S. 270, 273, 77 S.Ct. 269, 1 L.Ed.2d 306 (1957); Hopland Band of Pomo Indians v. United States, 855 F.2d 1573, 1576-77 (Fed.Cir.1988). The statute of limitations is jurisdictional in this court. Hopland, 855 F.2d at 1577. The party asserting jurisdiction carries the burden of establishing its existence by a preponderance of the evidence. Reynolds v. Army [437]*437& Air Force Exch. Serv., 846 F.2d 746, 747 (Fed.Cir.1988).

A taking action accrues when all events necessary to fix the Government’s alleged liability have occurred and the plaintiff knew or should have been known of their existence. Alliance of Descendants of Tex. Land Grants v. United States, 37 F.3d 1478, 1481 (Fed.Cir.1994); Alaska v. United States, 32 Fed.Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Energy Security of America Corp. v. United States
86 Fed. Cl. 554 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
68 Fed. Cl. 434, 2005 U.S. Claims LEXIS 319, 2005 WL 2853699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mobley-construction-co-v-united-states-uscfc-2005.