Mobile Housing Environments v. Barton and Barton

432 F. Supp. 1343, 1977 U.S. Dist. LEXIS 15267
CourtDistrict Court, D. Colorado
DecidedJune 24, 1977
DocketCiv. A. C-3844
StatusPublished
Cited by9 cases

This text of 432 F. Supp. 1343 (Mobile Housing Environments v. Barton and Barton) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mobile Housing Environments v. Barton and Barton, 432 F. Supp. 1343, 1977 U.S. Dist. LEXIS 15267 (D. Colo. 1977).

Opinion

FINDINGS OF FACT AND CONCLUSIONS RE: “TURNKEY”

CHILSON, Senior District Judge.

Plaintiff seeks to recover damages for alleged improper construction of a mobile home park under a construction contract. There' are a number of issues raised by the parties which must be determined before the complete disposition of this controversy. Counsel for plaintiff and defendants requested that certain of the issues be sepa *1344 rately determined and to that end entered into the following stipulation.

“Undersigned counsel have met and have reviewed the case in accordance with the Court’s instructions that they determine whether it is necessary to amend the existing pretrial order and whether it would in their view be productive to have the Court resolve specified issues affecting liability prior to a complete trial of all remaining issues.
“As a result of their meeting counsel suggest the following:
a. That the Court first issue findings of fact and conclusions of law with respect to the meaning of the term ‘turnkey construction job’ as that term is embodied in the contract documents.
(1) It is the position of plaintiff that the parol evidence rule would operate so as to bar extrinsic and parol evidence as to the meaning of that term.
(2) It is the position of Barton that the intended meaning of the term as used in the contract documents is not determinable from the documents themselves and the parol evidence rule therefore should not be applied to bar extrinsic and parol evidence as to the meaning thereof.
(3) It is suggested that the foregoing issue concerning the application of the parol evidence rule be submitted to the Court upon written briefs. Plaintiff’s opening brief to be filed within fifteen (15) days from the entry of an order approving the within stipulation; answer briefs of the defendant and third party defendants to be filed on or before fifteen (15) days from the date of receipt thereof; plaintiff’s reply brief to be filed on or before five (5) days from the date of receipt of the answer briefs.
(4) In the event the Court determines that the parol evidence rule applies so as to bar extrinsic evidence as to the meaning of the term ‘turnkey construction job’ the Court shall enter its ruling as to the meaning thereof. Depending upon the Court’s ruling, a disposition of the case by the parties may result at that juncture.
(5) In the event the Court determines that the parol evidence rule does not apply so as to bar extrinsic and parol evidence as to the meaning of said term, the parties shall submit a pretrial order for a trial restricted to a determination of the meaning of the term ‘turnkey construction job’ as used in the contract documents. The pretrial order shall be submitted to the Court within twenty (20) days after the issuance of the Court’s determination that evidence will be heard and counsel shall be ready for trial within thirty (30) days from the date of the entry of the pretrial order.
b. Depending upon the ruling of the Court as to the definition of ‘turnkey construction job’ a disposition of the case by the parties may result at that juncture.
c. In the event that no disposition by the parties is reached, the next issues to be tried would be those issues raised by plaintiff’s contentions as to the meaning and application of the contract provisions relating to the ‘unconditional guarantee’ which is set forth in the contract documents. The issues relative to the unconditional guarantee would relate to the effect of any notices given to defendants, to the period of the guarantee (i.e., its commencement and termination) and to a determination of the type of defects to which the guarantee would extend.
d. It is suggested that third party defendants be required to participate in all proceedings described above, inasmuch as the rights, duties and obligations which exist between Barton and the third party defendants are identical to those which will be determined in the findings and rulings to be made by the Court.
e. If resolution of the foregoing issues does not result in a disposition of the case, an amended proposed pretrial order would be required to be submitted by counsel and the matter set for *1345 prompt trial on all remaining issues of liability and damages.”

The Court approved the stipulation and the procedures therein were adopted by the Court.

There is now before the Court as the first issue, the meaning of the term “turnkey construction job” as that term is embodied in the contract documents. Counsel have submitted their briefs which the Court has read and considered and the Court is now prepared to rule on this issue.

FINDINGS OF FACT

In the spring of 1970, Maceo Corporation and Leadership Housing Systems undertook to develop a mobile home park in the City of Federal Heights, Colorado. For this purpose, Leadership and Codeca on April 28, 1970, entered into a written agreement and an amendment thereto whereby Codeca agreed to construct the mobile home park. The construction contract executed by Leadership and Codeca provided that Code-ca, as contractor, would:

“furnish all labor, material, equipment, tools, machinery, facilities and everything else required for the prompt turn-key construction of a mobile home park containing not more than 320 mobile home spaces, all of which shall be constructed in accordance with the general plans and the approved plans and specifications,

and that Codeca would

“cause plans and specifications for the improvements to be prepared at its cost and expense in accordance with the general plans and the quality provisions of paragraph 11 hereof by a licensed architect and shall submit said plans and specifications to owner for its approval within ten days after the execution of this contract. ... In the event owner approves said plans and specifications, contractor shall retain at its sole cost and expense, an independent qualified engineering firm to supervise and inspect the development and construction of the mobile home park.”

The amendment to this agreement provides:

“That the engineering costs are to be considered a part of the development costs and will not be an expense of contractor.”

The plans which Codeca caused to be prepared and which were approved by Leadership provided for 250 mobile home spaces.

In August of 1970, after substantial work had been done by Codeca, the plaintiff purchased the property contingent upon entering into a contract with Codeca for the completion of the mobile home park in accordance with the plans which had been prepared by Codeca in connection with its contract with Leadership.

The contract for completion was executed by Barton and Barton instead of Codeca, but Codeca guaranteed Barton and Barton’s performance. Richard A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
432 F. Supp. 1343, 1977 U.S. Dist. LEXIS 15267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mobile-housing-environments-v-barton-and-barton-cod-1977.