Mobile & Birmingham Railroad v. Worthington

95 Ala. 598
CourtSupreme Court of Alabama
DecidedDecember 15, 1891
StatusPublished
Cited by7 cases

This text of 95 Ala. 598 (Mobile & Birmingham Railroad v. Worthington) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mobile & Birmingham Railroad v. Worthington, 95 Ala. 598 (Ala. 1891).

Opinion

STONE, C. J.

The motion to strike the bill of exceptions from the transcript must be overruled. The act of Febru[602]*602ary 22, 1887 — Sess. Acts, 126 — which, provides that the court in term time may fix the time within which bills of exceptions may be signed, contains the further clause, that “the judge in vacation may, for good cause, extend the time fixed in term time but in no case to allow more than six months beyond the adjournment of the term at which the case is tried. The statute is silent as to the manner of showing or authenticating the judge’s order of extension. Whenever, as in this case, the clerk embodies in the transcript what purports to be a copy of the judge’s order of extension, we think it our duty to regard and treat it, at least, as prima facie correct.

The main purpose of this suit by Worthington was to recover damages of the railroad company for the breach of an alleged contract. Worthington claims to have been a bridge-builder, and that he made a contract with Patton, the chief engineer of the road, to construct three trestles at and near certain named streams, to be crossed by the railroad’s track. The complaint contains a special count setting forth the alleged terms of the letting; avers that although plaintiff “has at all times been ready and willing to comply with all the provisions of said contract on his part, and has so complied so far as he has been permitted so to do by the defendant, the defendant has failed to comply with the following provisions thereof.” The complaint then assigns five several breaches, and among them the following : That “it has wholly failed and refused to furnish to the plaintiff the larger portion of said work, . . and refused to permit him to perform the same . . It wholly failed to furnish the said timber and material, at the time it had contracted to so furnish the same, and thereby postponed and delayed the plaintiff, and put him to great expense and trouble in the maintenance of necessary teams, and the maintenance and compensation of laborers. . . It wholly failed and refused to furnish to the plaintiff the necessary timber and material to enable him to perform the large portion of the work specified in the contract.” The plaintiff also claimed that he had been permitted to do, and had done, some of the work contracted to be done, and had done other work outside of the contract which had been received: and the complaint contains common counts for the purpose of recovering for such work done.

The defendant demanded a bill of particulars under the statute, and one was furnished. Testimony was offered to prove that teams were necessary to do the work set forth in the complaint; and it was objected to as not specified in the [603]*603bill of particulars. Tbe objection was overruled, and tbe testimony received; and tbis raises tbe first question we need consider.

It is assigned as part of one of tbe breaches of tbe special contract alleged to baye been made, that defendant bad put plaintiff “to great expense and trouble in tbe maintenance of necessary teams.” There was some proof that teams were a necessary power in raising large timbers in tbe construction of trestles of tbe height here required. True, there was no testimony tending to show that seventeen yokes of oxen were needed, but the record presents no ruling on that question. Tbe bill of particulars gave notice of items of “corn, oats and bran consumed,” for which compensation was claimed. These were suitable food for teams.

Tbe question propounded for and to plaintiff as a witness in bis own behalf was as follows : “Explain whether or not it was necessary or proper to have teams up there to do anything on tbe work ?” Objected to, because not specified in bill of particulars ; objection overruled, answered affirmatively, and exception reserved. We think there was nothing in this exception. Defendant had sufficient notice of this claim to prevent him from being surprised. — Code of 1886, § 2670 ; Robinson v. Allison, 36 Ala. 525 ; Fountain v. Ware, 56 Ala. 558.

Plaintiff offered in evidence a letter written by PutDamto himself, bearing date March 22, 1888. Defendant objected, and the objection was overruled ; the court remarking that it was permitted to be put in evidence, “as it might tend to show whether or not Worthington knew that Putnam was making any settlement with the railroad company.” Defendant then objected to each sentence of the letter separately; this objection was overruled, and separate exceptions reserved. The letter was read in evidence. Reserved as this exception was, it is probably our duty to treat is as a general exception to the whole letter. — Mayberry v. Leach, 58 Ala. 339.

The most important issue of fact in this case, as developed in the pleadings and testimony, was whether Worthington had an independent contract with the railroad company to build the trestles, or whether he did what work he is shown to have done under Putnam’s contract, or by permission of Putnam. Worthington testified that he made and concluded an independent contract with Patton, the chief engineer, to construct the three trestles. The special count in the complaint is framed on that basis, and claims damages for not being permitted to do the work. Patton denied making [604]*604such contract with Worthington, and claimed that the only contract lie concluded was with Putnam. In making settlements with Putnam, he and his successors recognized him as contractor, and refused to recognize Worthington as a contractor, save as an employe under Putnam. On the issue of original contract vel non with Worthington, his testimony and that of the engineer were in direct conflict. It is claimed by the parties to these opposing versions that they were severally more or less corroborated by other testimony. This was purely a question for the jury.

In settling with the railroad officials for work done under his contract, Putnam testified that he was not authorized to agree on a binding settlement of Worthington’s claim, but was authorized to receive any amount the authorities would pay him for work done by the latter. Some moneys on this account were paid to, and received by Putnam; and he testified that he subsequently accounted to Worthington for such collections. The witnesses were not agreed as to the nature of Putnam’s settlement, whether it was entirely on his own account as contractor to build the trestles, or in part as the representative of Worthington under the latter’s independent contract. Extra work, not embraced in any original contract, had been done by Worthington, and there was no dispute about Worthington’s right to be paid for that. The point we are now considering has nothing to do with the claim for such extra work.

Presented before the court and jury as the issue of fact above stated appears to have been by the testimony, it may be that Putnam’s letter to Worthington of March 22, 1888, would have been competent evidence for the defendant, if offered by it. It was not competent evidence for the plaintiff, and should have been, excluded.

What Putnam testified he told the railroad officials while settling with them, in relation to his contract with Worth-ington, and the extent of his authority to represent him, was part of the res gestae; was original testimony, and rightly received, without any special predicate being laid for its introduction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pigg v. Houston & Liggett
8 Tenn. App. 613 (Court of Appeals of Tennessee, 1928)
Berthold & Jennings Lbr. Co. v. Geo. W. Phalin Lumber Co.
71 So. 989 (Supreme Court of Alabama, 1916)
King Land & Improvement Co. v. Bowen
61 So. 22 (Alabama Court of Appeals, 1913)
Mississippi Lumber Co. v. Smith & Co.
44 So. 475 (Supreme Court of Alabama, 1907)
Sellers v. Farmer
151 Ala. 487 (Supreme Court of Alabama, 1907)
Rainer Mercantile Co. v. Deal
44 So. 100 (Supreme Court of Alabama, 1907)
National Bank v. Baker Hill Iron Co.
108 Ala. 635 (Supreme Court of Alabama, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
95 Ala. 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mobile-birmingham-railroad-v-worthington-ala-1891.