Moberly Asphalt Maintance, Inc. v. Royal Associates, Ltd.

618 P.2d 1347, 1980 Wyo. LEXIS 318
CourtWyoming Supreme Court
DecidedOctober 31, 1980
DocketNo. 5306
StatusPublished
Cited by2 cases

This text of 618 P.2d 1347 (Moberly Asphalt Maintance, Inc. v. Royal Associates, Ltd.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moberly Asphalt Maintance, Inc. v. Royal Associates, Ltd., 618 P.2d 1347, 1980 Wyo. LEXIS 318 (Wyo. 1980).

Opinion

ROSE, Justice.

This is a multi-issue appeal from the judgment of the trial court which found that a residential developer was justified in refusing to pay most of the balance due a subcontractor on two contracts for the reason that the subcontractor’s work was deficient. We will affirm on the ground that the record supports the trial court’s various factual findings. This resolution makes unnecessary a consideration of many of the challenges to the court’s legal conclusions.

Moberly Asphalt Maintenance, Inc., plaintiff-appellant, is a paving contractor. The defendant-appellee, Royal Associates, Ltd., is a partnership composed of three corporations operating as a residential subdivision developer. In July of 1976, the parties entered into a contract under which Moberly agreed to pave most of the streets of Pratt Addition No. 1 to the City of Casper, which Royal was developing. A second contract entered into the same month called for Moberly to also install curbs, gutters and sidewalks. Both agreements provided for the work to be done according to city specifications. The contract price contemplated by these two agreements, as later modified, was $172,298.20. Prior to this litigation, Royal had paid $65,000.00 to Moberly and [1349]*1349offered an additional $9,585.61 in lieu of the balance. It was Royal’s position that it had been required to pay $97,712.59 to other contractors to bring Moberly’s work up to city specifications and to satisfy liens incurred by Moberly, and, thus, Royal was not obligated to pay Moberly the full balance contemplated by the contracts.

The trial court allowed Royal its claimed deduction of $97,712.59 and ordered an additional $9,585.61 payment to Moberly, a sum which Royal acknowledged was due and owing.

Most of the offset claimed by Royal involved money it spent repairing and upgrading Moberly’s paving work. In this regard, it is undisputed that Moberly encountered various problems with the city engineer, who eventually ordered Moberly off the paving job. The major issue in this case is whether Moberly or Royal is responsible for the failure of the paving. Parenthetically, it should be noted that $5,464.47 of the offset claimed by Royal involved money it paid subsequent contractors to bring the curb, gutter and sidewalk up to city specifications. There is a factual dispute as to whether problems with this concrete work were caused by the manner in which the work was performed or whether they developed after completion and were caused by Royal’s trucks driving over the finished concrete work.

At trial, Moberly sought not only the balance due under the contract but almost $400,000.00 in addition, alleging that it was entitled to punitive damages, recovery in quantum meruit, damages for impairment to its business and damages for Royal’s refusal to enter into a second paving contract with Moberly.

Moberly has framed ten issues, three of which we will consider together. These are:

“I. WHETHER THE TRIAL COURT ERRED AS A MATTER OF LAW IN FINDING MOBERLY RESPONSIBLE FOR THE SUB-GRADE PREPARATION
“II. WHETHER THE TRIAL COURT’S FINDING IN REGARD TO ADEQUATE SUBGRADE PREPARATION IS CLEARLY ERRONEOUS AND CONTRARY TO THE GREAT WEIGHT OF THE EVIDENCE
“HI. WHETHER THE TRIAL COURT’S FINDING WITH REGARD TO THE PROXIMATE CAUSE OF THE STREET FAILURE IS CLEARLY ERRONEOUS AND CONTRARY TO THE GREAT WEIGHT OF EVIDENCE”

The street contract incorporates by reference a letter from the Casper city engineer, setting out various paving requirements for city streets. This communication contains cross-section diagrams of a paved street, which show that a street consists of asphalt layers and coatings, gravel and a subgrade. The subgrade is the underlying dirt, or “native inplace material;” the gravel consists of a layer referred to as a “gravel base course;” and there may also be a lower gravel layer called a “gravel subbase course.” Two asphalt layers, each with its own coating, finish the street. To facilitate water drainage, the street is crowned so that it is highest in the center. From the diagram, it appears that the asphalt and gravel layers have a uniform thickness, so it is the contour of the subgrade that determines the contour of the street.

At trial, it was Moberly’s position that subgrade preparation was the responsibility of Royal or its other subcontractors and the street failures were the result of the subgrade being inadequately compacted prior to paving. The court found, however, that the subgrade, contrary to Moberly’s contentions was not the cause of pavement failure. The evidence is sufficient to support this finding.

The water, sanitary sewer and storm sewer lines were laid in the center of the streets, and Moberly urges that when these trenches were backfilled, the dirt was not properly compacted. Moberly further argues that the deficient methods used to compact the dirt in these trenches made the [1350]*1350defective compaction latent rather than patent in nature.

In support of these contentions, Moberly’s expert testified that insufficient compaction of the soil creates a space where water accumulates, freezes in cold weather and, upon expansion, uplifts, breaks up, and causes surface distortion. The witness went on to say that proper compaction of the soil requires a certain optimum moisture content. He explained that too much moisture produces mud which defies compression, while too little moisture deprives the soil of lubrication needed for compaction. The expert witness expressed the opinion that the compaction methods used on the subgrade — and in particular the utility trenches — were inadequate.

Moberly sought additional damages for expenses incurred in removing excess dirt from the subgrade on the theory that the dirt removal was not contemplated by the parties in their contract.

Royal’s first witness was David Korenke, assistant Casper city engineer. Korenke testified that the city required compaction tests of the subgrade and that paving would not be accepted where compaction-test results were not satisfactory. The witness also testified that the city complained to Moberly about the streets lacking a crown when Moberly was preparing to pave. According to Korenke, Moberly first indicated that the crown would be established before the first layer of asphalt. When the first layer of asphalt was in place and there was no crown, Moberly, according to Korenke, promised to structure the crown when applying the second layer of asphalt. The witness further testified that Moberly did not incorporate such a crown in the finished street, as was called for by the city specifications. Korenke further testified that the city refused to allow Moberly to use some materials because they were of poor quality-

It was shown, through photographic exhibits, that portions of the paving were deficient and substandard. These exhibits portray a “lay down machine” applying the second layer of asphalt, and it appears that the first layer of asphalt on which the machine rests is seriously deficient by virtue of its being cracked or containing holes. Yet another exhibit portrays a large gouge mark in the first layer of asphalt, which appears to have been caused by a paving machine becoming stuck. Korenke testified that he complained of these and other inadequacies to Moberly but finally came to disbelieve assurances that various defects would be corrected before Moberly applied the final layer of asphalt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alpine Climate Control, Inc. v. DJ's, Inc.
2003 WY 138 (Wyoming Supreme Court, 2003)
Palmeno v. Cashen
627 P.2d 163 (Wyoming Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
618 P.2d 1347, 1980 Wyo. LEXIS 318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moberly-asphalt-maintance-inc-v-royal-associates-ltd-wyo-1980.