MMB, Inc. v. ProPacific Builders, Corp

CourtSuperior Court of Guam
DecidedAugust 24, 2021
DocketCV0093-21
StatusUnknown

This text of MMB, Inc. v. ProPacific Builders, Corp (MMB, Inc. v. ProPacific Builders, Corp) is published on Counsel Stack Legal Research, covering Superior Court of Guam primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MMB, Inc. v. ProPacific Builders, Corp, (superctguam 2021).

Opinion

IN THE SUPERIOR COURT Of GUAM

MMB, INC., CIVIL CASE NO. CV0093-21

Plaintiff,

vs. DECISION AND ORDER PROPACIFIC BUILDERS CORP., GRANTING DEFENDANT’S MOTION TO COMPEL ARBITRATION AND Defendant. DISMISS COMPLAINT

INTRODUCTION

This matter came before the Honorable Dana A. Gutierrez on May 26, 2021 for a motion

hearing on Defendant PROPACIFIC Builders Corporation’s (“Defendant”) Motion to Compel

Arbitration and Dismiss Complaint. Present via Zoom were Attorney Thomas Fisher

representing Plaintiff MMB Inc. (“Plaintiff’) and Attorney Joyce Tang representing Defendant.

After the hearing, the Court took the matter under advisement. After reviewing the record,

arguments by both parties, and relevant law, the Court finds that the parties are bound to

mandatory arbitration of the dispute. The Motion to Compel Arbitration and Dismiss Complaint

is therefore GRANTED.

BACKGROUND

This matter arises from a dispute over Defendant’s alleged breach of the Subcontractor

Agreement (“Agreement”) between the parties in which Plaintiff was to perform construction

work for the Guam Waterworks Authority (“GWA”). Compl., ¶J 5-8 (Dec. 8, 2020). In response . DECISION AND ORDER GRANTING DEFENDANT’S MOTION TO COMPEL ARBITRATION AND DISMISS COMPLAINT CV0093-21, liMB, Inc. v. PROPACIFIC Builders Corp.

to the Complaint, Defendant filed a Motion to Compel Arbitration and Dismiss Complaint

(“Motion”) on February 24, 2021. Defendant argues that the instant dispute falls within the

Agreement’s arbitration provision and the Court should order the parties to arbitrate. Motion, at

3 (Feb. 24, 2021). In its Opposition to Defendant’s Motion, Plaintiff argues that Defendant

waived its right to arbitration by failing to respond to a letter from August 2020 in which

Plaintiff invoked its right to arbitrate. Opp., at 2 (Mar. 23, 2021).

In its Reply to Plaintiff’s Opposition, Defendant denies receiving the August letter. Decl.

of Floriano Escabillas, at ¶f 3-4 (Apr. 7, 2021); see Reply (Apr. 7, 2021). On May 26, 2021, the

Court heard oral argument on Defendant’s Motion. After taking the matter under advisement,

the Court now issues this Decision and Order.

DISCUSSION

Pursuant to Rule 12(b)(6) of the Guam Rules of Civil Procedure (“GRCP”), a court can

dismiss a complaint if the plaintiff “fail{s] to state a claim upon which relief can be granted.”

GRCP 12(b)(6). The court can decide a motion to compel arbitration under Rule 12(b)(6) if “a

party’s claims are subject to an enforceable arbitration clause.” Sifee v. Automatic Data

Processing, Inc., 696 Fed. Appx. 576, 578 (3rd Cir. 2017).’ If the agreement is enforceable in

that it is not “null and void, inoperative or incapable of being performed,” then Guam law

requires the court to refer the parties to arbitration. 7 G.C.A. § 42A202(a).2 Referring the parties

to arbitration is mandatory. Ass ‘n of Apartment Owners of Guam Yamanoi Condo. v. Guam

The Guam International Arbitration Chapter (“GJAC”) “substantively mirrors the Federal Arbitration Act (“FAA”). .[andJ federal case law interpreting the FAA is especially persuasive where the GIAC applies.” .

Ass ‘n of Apartment Owners of Guam Yamanoi Condo. v. Guam Yamanaoi Inc., 2019 Guam 14 ¶ 14. 2 Title 7 G.C.A. § 42A202(a) provides: “A court before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party so requests not later than when submitting his or her first statement on the substance of the dispute, refer the parties to arbitration unless it fmds that the agreement is null and void, inoperative or incapable of being performed.”

2 . . DECISION AND ORDER GRANTING DEFENDANT’S MOTION TO COMPEL ARBITRATION AND DISMISS COMPLAINT CV0093-2]; liMB, Inc. v. PROPACIFIC Builders Corp.

Yamanoi, Inc., 2019 Guam 14 ¶ 14 (stating that if the arbitration agreement is enforceable, then

the requirement that courts refer the parties to arbitration is “mandatory”).

Defendant argues that the Court must refer the parties to arbitration because Plaintiff’s

claim falls within the scope of the Agreement’s arbitration provision. Motion, at 3. Defendant

further asserts that it did not waive its right to arbitrate, but in the alternative, asks that the Court

defer the question of whether Defendant waived its rights to arbitrate to the arbitrator. Opp., at 2.

For the reasons stated below, the Court agrees with Defendant that Plaintiff’s claim falls within

the scope of the Agreement’s arbitration provision and that the parties must arbitrate their

dispute.

I. Whether Plaintiff’s Claim for Damages for Alleged Breach of Contract Falls Within Scope of the Agreement’s Arbitration Provision.

The Court notes that neither party asserts that the Agreement is unenforceable, therefore

the first issue is whether Plaintiff’s claim falls within the scope of the Agreement’s arbitration

provision. See Motion; Opp.; Reply. The “scope of an arbitrat[or ‘sJ. .authority is determined .

by the language of the arbitration clause.” Gov t of Guam v. Pacficare Health Ins. Co. ofMici,

Inc., 2004 Guam 17 ¶ 24 (“Pacificare”) (quoting Lupone v. Lupone, 848 A.2d 539, 541 (Conn.

Ct. App. 2004)).

Article 8.03 of the Agreement states:

Notice of Demand. Any and all claims or demands arising out of or relating to this contract Agreement or the breach thereof, shall be fully and finally resolved by binding arbitration in accordance with the Arbitration Rules and Procedures of Dispute Prevention & Resolution, Inc. then in effect.

Award. The award rendered by the arbitrator(s) shall be final and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

3 DECISION AND ORDER GRANTING DEFENDANT’S MOTION TO COMPEL ARBITRATION AND DISMISS COMPLAINT CV0093-21; liMB, Inc. v. PROPACIFIC Builders Corp.

Compi., Exhibit B.

The Agreement’s arbitration provision provides no limitations on the arbitrable subject

matter. Article 8.03 states that “any and all claims or demands arising out of or relating to” the

Agreement are to be resolved through arbitration. Compi., Exhibit B. Plaintiff’s claim for

damages stems from Defendant’s alleged breach of contract for failing to perform its obligation

under the Agreement. Id. at ¶J 8-15. Furthermore, Plaintiff does not oppose the Motion on the

grounds that this claim falls outside the scope of the arbitration provision in the Agreement.

See Motion. Thus, the Court finds that Plaintiff’s claim for damages falls under the “any and all

claims or demands” provision and is, therefore, subject to arbitration under the Agreement.

II. Whether Defendant Waived Its Right to Arbitration.

Plaintiff argues that if the claim is arbitrable, Defendant waived its right to arbitrate

when it failed to respond to Plaintiff’s August 2020 letter in which Plaintiff invoked its right to

arbitrate the dispute. Opp., at 3. In response, Defendant makes several arguments: (1) that the

question of whether Defendant waived its right to arbitrate is a question for the arbitrators; (2)

Defendant did not waive its right to arbitration; and (3) Guam law and policy disfavor waiver of

contractual rights. Reply, at 2-3.

The question of whether Defendant waived its right to arbitration is to be resolved by the

arbitrator. Once the court determines that the parties must arbitrate the substance of their

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Wiley & Sons, Inc. v. Livingston
376 U.S. 543 (Supreme Court, 1964)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Joshua Silfee v. Automatic Data Processing Inc
696 F. App'x 576 (Third Circuit, 2017)
Lupone v. Lupone
848 A.2d 539 (Connecticut Appellate Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
MMB, Inc. v. ProPacific Builders, Corp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mmb-inc-v-propacific-builders-corp-superctguam-2021.