PER CURIAM:
This appeal arises from the Asset Purchase and Sale Agreement (APSA) entered into between Mirant Corporation (Mirant) and Potomac Electric Power Company (PEPCO). This appeal is not the first time these parties have been before us,
see In re Mirant Corp.,
378 F.3d 511 (5th Cir.2004), and we recognize that it may not be the last. After argument and review of the lengthy briefing and extensive record in this case it is evident that a single theme lies behind the thousands of pages generated in this litigation: Mirant’s unrelenting and unjustified effort to avoid a legitimate contractual obligation it now views as a bad deal.
In order to secure PEPCO’s acceptance of Mirant’s bid to purchase certain electric generating facilities, Mirant agreed to receive assignment of PEPCO’s Purchase Power Agreements (PPAs).
At the time of negotiations both Mirant and PEPCO acknowledged that the purchase price for electricity under the PPAs was above market price, resulting in an agreed “negative value” of approximately $500 million. Consequently, the parties reduced the agreed sale price by $500 million, representing the loss on the PPAs. Instead of $3.2 billion, Mirant paid Pepeo $2.65 billion. The parties memorialized their agreement in the APSA, which included 1) the transfer of certain power generation facilities to Mirant; 2) the assignment of PEPCO’s PPAs to Mirant, including the Back-to-Back arrangement agreed to as a contingency plan in the event that the PPAs were not assignable to Mirant; 3) lease agreements and easements allowing Mirant access to the generating facilities; and 6) inter-connection agreements allowing Mirant to transfer power along PEP-CO’s inter-connection network.
PEPCO notified Mirant at the December 19, 2000 closing on the APSA that certain PPAs were unassignable,
and the
parties began performing under the APSA’s contingency plan known to the parties as the Back-to-Back Agreement (BTB). The cost to Mirant under the BTB is approximately $10-15 million per month.
In July 2003, Mirant filed for bankruptcy and immediately filed a motion to reject the BTB (first motion to reject), but did not attempt to reject the remaining executory portions of the APSA. PEPCO, because of the automatic stay, was required to continue performance. On December 9, 2004, the district court denied Mirant’s first motion to reject, finding that the BTB was not severable from the APSA and thus was not eligible for rejection under 11 U.S.C. § 365. Mirant appeals that order (appeal no. 05-10038). In appeal number 05-10038, Mirant raises two points of error: 1) the finding of the district court that the BTB was not severable from the APSA; and 2) the standard for rejection articulated in dicta by the district court.
On the very date the district court denied Mirant’s first motion to reject, Mirant unilaterally declared that it would no longer perform its obligations under the BTB and ultimately filed a second motion to reject with the bankruptcy court.
This second motion and related pleadings were withdrawn from the bankruptcy court by the district court. On March 1 and March 16, 2005, the district court ordered Mirant to perform under the BTB until either 1) rejection was approved, or 2) Mirant demonstrated that discontinuing performance pending rejection was within the public interest. (The second motion to reject is still pending before the district court.) Mirant appeals these March orders (appeal no. 05-10419) and seeks a stay of the order to perform under the BTB pending ruling on the merits of its second motion to reject. In appeal number 05-10419, Mirant raises an additional two points of error: 1) the district court’s withdrawal from the bankruptcy court of Mirant’s second motion to reject and related pleadings; and 2) the district court’s order that Mirant perform under the BTB until rejection of the BTB or APSA is approved on the merits.
In section I we address the issues presented in appeal number 05-10038. Section II addresses the issues involved in appeal number 05-10419. For the reasons set forth below we AFFIRM all orders of the district court.
I
Appeal no. 05-10038 challenges the district court’s December 9, 2004 order denying Mirant’s first motion to reject the BTB portion of the APSA. Section 365(a) of the Bankruptcy Code provides that “the trustee, subject to the court’s approval, may assume or reject any executory contract or unexpired lease of the debtor.”
11 U.S.C. § 365(a). Under § 365, “[i]t is well established that as a general proposition an executory contract must be assumed or rejected in its entirety.”
Stewart Title Guaranty Co. v. Old Republic Nat’l Title Ins. Co.,
83 F.3d 735, 741 (5th Cir.1996) (citation omitted). This “often-repeated
statement ... means only that the debtor cannot choose to accept the benefits of the contract and reject its burdens to the detriment of the other party to the agreement.”
Richmond Leasing Co. v. Capital Bank, N.A.,
762 F.2d 1303, 1311 (5th Cir.1985). Consequently, to reject a contract under § 365, a debtor must establish that 1) the contract is executory, and 2) the contract is either an entire agreement, or a severable portion of an agreement. Once a contract is deemed eligible for rejection, court approval is required for rejection.
See
3 Collier on Bankruptcy 11365.03 (15th Ed. Rev.2004) (“The decision to assume or reject a contract or lease is subject to court approval.”).
The parties agree that the relevant portions of the APSA are executory.
Thus, our analysis of the December 9, 2004 order begins with the question of severability. Once severability is resolved, we consider the appropriate standard for approving rejection. Thus we turn to examine, first whether the BTB agreement is severable from the APSA, and second, the appropriate standard for rejection in this context.
A
The issue of severability under § 365 requires that an executory contract be rejected
in toto
to prevent a debtor from picking through an agreement, accepting the benefits while sloughing the burdens.
See In re Cafe Partners/Washington 1983,
90 B.R. 1, 5 (Bankr.D.D.C.1988) (“the Debtor may not pick and choose from among the desirable and undesirable portions of the contract”). However, “[i]f a single contract contains separate, severable agreements the debtor may reject one agreement and not another.”
Stewart Title Guaranty Co.,
83 F.3d at 741.
Free access — add to your briefcase to read the full text and ask questions with AI
PER CURIAM:
This appeal arises from the Asset Purchase and Sale Agreement (APSA) entered into between Mirant Corporation (Mirant) and Potomac Electric Power Company (PEPCO). This appeal is not the first time these parties have been before us,
see In re Mirant Corp.,
378 F.3d 511 (5th Cir.2004), and we recognize that it may not be the last. After argument and review of the lengthy briefing and extensive record in this case it is evident that a single theme lies behind the thousands of pages generated in this litigation: Mirant’s unrelenting and unjustified effort to avoid a legitimate contractual obligation it now views as a bad deal.
In order to secure PEPCO’s acceptance of Mirant’s bid to purchase certain electric generating facilities, Mirant agreed to receive assignment of PEPCO’s Purchase Power Agreements (PPAs).
At the time of negotiations both Mirant and PEPCO acknowledged that the purchase price for electricity under the PPAs was above market price, resulting in an agreed “negative value” of approximately $500 million. Consequently, the parties reduced the agreed sale price by $500 million, representing the loss on the PPAs. Instead of $3.2 billion, Mirant paid Pepeo $2.65 billion. The parties memorialized their agreement in the APSA, which included 1) the transfer of certain power generation facilities to Mirant; 2) the assignment of PEPCO’s PPAs to Mirant, including the Back-to-Back arrangement agreed to as a contingency plan in the event that the PPAs were not assignable to Mirant; 3) lease agreements and easements allowing Mirant access to the generating facilities; and 6) inter-connection agreements allowing Mirant to transfer power along PEP-CO’s inter-connection network.
PEPCO notified Mirant at the December 19, 2000 closing on the APSA that certain PPAs were unassignable,
and the
parties began performing under the APSA’s contingency plan known to the parties as the Back-to-Back Agreement (BTB). The cost to Mirant under the BTB is approximately $10-15 million per month.
In July 2003, Mirant filed for bankruptcy and immediately filed a motion to reject the BTB (first motion to reject), but did not attempt to reject the remaining executory portions of the APSA. PEPCO, because of the automatic stay, was required to continue performance. On December 9, 2004, the district court denied Mirant’s first motion to reject, finding that the BTB was not severable from the APSA and thus was not eligible for rejection under 11 U.S.C. § 365. Mirant appeals that order (appeal no. 05-10038). In appeal number 05-10038, Mirant raises two points of error: 1) the finding of the district court that the BTB was not severable from the APSA; and 2) the standard for rejection articulated in dicta by the district court.
On the very date the district court denied Mirant’s first motion to reject, Mirant unilaterally declared that it would no longer perform its obligations under the BTB and ultimately filed a second motion to reject with the bankruptcy court.
This second motion and related pleadings were withdrawn from the bankruptcy court by the district court. On March 1 and March 16, 2005, the district court ordered Mirant to perform under the BTB until either 1) rejection was approved, or 2) Mirant demonstrated that discontinuing performance pending rejection was within the public interest. (The second motion to reject is still pending before the district court.) Mirant appeals these March orders (appeal no. 05-10419) and seeks a stay of the order to perform under the BTB pending ruling on the merits of its second motion to reject. In appeal number 05-10419, Mirant raises an additional two points of error: 1) the district court’s withdrawal from the bankruptcy court of Mirant’s second motion to reject and related pleadings; and 2) the district court’s order that Mirant perform under the BTB until rejection of the BTB or APSA is approved on the merits.
In section I we address the issues presented in appeal number 05-10038. Section II addresses the issues involved in appeal number 05-10419. For the reasons set forth below we AFFIRM all orders of the district court.
I
Appeal no. 05-10038 challenges the district court’s December 9, 2004 order denying Mirant’s first motion to reject the BTB portion of the APSA. Section 365(a) of the Bankruptcy Code provides that “the trustee, subject to the court’s approval, may assume or reject any executory contract or unexpired lease of the debtor.”
11 U.S.C. § 365(a). Under § 365, “[i]t is well established that as a general proposition an executory contract must be assumed or rejected in its entirety.”
Stewart Title Guaranty Co. v. Old Republic Nat’l Title Ins. Co.,
83 F.3d 735, 741 (5th Cir.1996) (citation omitted). This “often-repeated
statement ... means only that the debtor cannot choose to accept the benefits of the contract and reject its burdens to the detriment of the other party to the agreement.”
Richmond Leasing Co. v. Capital Bank, N.A.,
762 F.2d 1303, 1311 (5th Cir.1985). Consequently, to reject a contract under § 365, a debtor must establish that 1) the contract is executory, and 2) the contract is either an entire agreement, or a severable portion of an agreement. Once a contract is deemed eligible for rejection, court approval is required for rejection.
See
3 Collier on Bankruptcy 11365.03 (15th Ed. Rev.2004) (“The decision to assume or reject a contract or lease is subject to court approval.”).
The parties agree that the relevant portions of the APSA are executory.
Thus, our analysis of the December 9, 2004 order begins with the question of severability. Once severability is resolved, we consider the appropriate standard for approving rejection. Thus we turn to examine, first whether the BTB agreement is severable from the APSA, and second, the appropriate standard for rejection in this context.
A
The issue of severability under § 365 requires that an executory contract be rejected
in toto
to prevent a debtor from picking through an agreement, accepting the benefits while sloughing the burdens.
See In re Cafe Partners/Washington 1983,
90 B.R. 1, 5 (Bankr.D.D.C.1988) (“the Debtor may not pick and choose from among the desirable and undesirable portions of the contract”). However, “[i]f a single contract contains separate, severable agreements the debtor may reject one agreement and not another.”
Stewart Title Guaranty Co.,
83 F.3d at 741.
The district court found, and the parties agree, that severability for purposes of § 365 rejection is determined by applying the non-bankruptcy, general legal rules applicable to the agreement at issue.
See, e.g., In re Cafe Partners,
90 B.R. at 6 (“[Wjhether a contract ... is an entire contract is not a question of the Federal bankruptcy law but of the law, usually State law, that would govern the parties’ rights outside bankruptcy.”).
The APSA itself provides that it is to be “governed by and construed in accordance with the law of the District of Columbia.” APSA, § 12.6. Under D.C. law, the well established test of severability is
whether the parties, at the time the agreement was entered, intended the contract to be severable.
See, e.g., Holiday Homes v. Briley,
122 A.2d 229, 232 (D.C.1956) (“Whether a number of promises constitutes one contract or more than one is primarily a question of intention of the parties.”).
Howard University v. Durham,
408 A.2d 1216, 1219 (D.C.1979), observed that while the intention of the parties controls, “[t]here is no set answer to the question of when a contract is divisible.” However, the court found there were several “factors to be considered” in determining whether the parties intended the contract to be severable.
Id.
Those factors as enumerated are:
1) whether the parties assented to all the promises as a single whole; 2) whether there was a single consideration covering various parts of the agreement or whether consideration was given for each part of the agreement; and 3) whether [the] performance of each party is divided into two or more parts, the number of parts due from each party being the agreed exchange for a corresponding part by the other party.
Id.; see also Cahn v. Antioch Univ.,
482 A.2d 120, 129 (D.C.1994) (affirming the
Howard Univ.
factors). Based on these factors, the district court concluded that the BTB was not severable from the APSA and thus was not eligible for rejection. After considering these factors and the corresponding evidence, we agree.
First, the parties clearly “assented to all the promises”' — the sale of the generation facilities, the lease agreements, the easements, the BTB agreement, and the interconnection agreements — “as a single whole.” The parties did not enter separate contracts or transactions; nor were the various agreements executed or closed at separate times. Instead, each part of this agreement was contained in a five-volume document collectively entitled the Asset Purchase and Sale Agreement. This agreement was executed on June 7, 2000 as one package, and the parties held the closing on December 19, 2000.
As further
evidence that the parties viewed this deal “as a single whole,” Section 12.10 of the APSA identifies the different parts of the agreement and states that
collectively
they “embody the entire agreement and understanding of the Parties.”
Second, it is clear that the parties negotiated one single consideration for the entirety of the deal, including the BTB agreement. Mirant’s arguments that consideration for the APSA was separate or distinct from that of the BTB agreement are, at best, misguided.
Further, Mir-ant’s focus on the exchange of money as the only evidence of consideration is misplaced. Consideration is a bargained-for promise or performance.
See
Restatement (Second) of Contracts § 71 (1979). The consideration for the BTB agreement is not, as Mirant suggests, the monthly payments made by Mirant to PEPCO. Nor was the consideration for the power generating facilities the $2.65 billion dollars paid by Mirant. Instead, as stated by Mirant’s counsel at oral argument, “the consideration the parties negotiated for was a whole deal.” That is to say, there was one amount as consideration for this overall agreement; that single amount reflected the negotiated value of the entire transac
tion — PEPCO agreed to sell its generating facilities and lease its properties and inter-connective capabilities, and grant certain easements; Mirant agreed to pay $2.65 billion and take on the PPAs.
The third and final
Howard University
factor asks whether the performance required by the alleged separate agreement can be divided from the performance required by the remainder of the agreement. Performance is divisible where the alleged severable obligations “can be apportioned into corresponding pairs of part performances so that the parts of each pair are properly regarded as agreed equivalents.”
Restatement of Contracts (Second) § 183;
see also Howard Univ.,
408 A.2d at 1219 (“whether performance of each party is divided into two or more parts, the number of parts due from each party being the agreed exchange for a corresponding part by the other party”). PEPCO’s obligations under the BTB agreement
were not the “agreed equivalent” of the “agreed exchange” for Mir-ant’s monthly payment obligations under the BTB agreement. Instead, Mirant’s payment of $2.65 billion and assumption of the PPAs along with the BTB, was the agreed exchange and negotiated equivalent of PEPCO’s transfer of its generating facilities, lease and easement agreements, and inter-connection agreements. Because the parties’ respective obligations under the BTB are not the “agreed exchange” for the other party’s performance under the BTB, performance of the BTB is not divisible from performance of the APSA.
Each of the
Howard University
factors points in this case to one single and indivisible agreement: there was assent by the parties “to all the promises as a single whole”; there was “a single consideration covering [the] various parts of the agreement”; and the performance is not divisible.
Howard Univ.,
408 A.2d at 1219. Nothing in the record or arguments gives any indication to the contrary; nor is there any evidence that the parties intended any part of the agreement to be severable from the whole. The record is clear that, as the district court found, “the furthest thing from the minds of the parties when they entered into the APSA, and agreed to a contract price of $2.65 billion, was that ... the Back-to-Back Agreement would be treated as contractual commitment[ ] separate from and independent of [the] sale ... of [Pepco’s] electric generation facilities.”
As the parties to this agreement did not intend it to be severable from the agreement as a whole, we hold that the BTB agreement is not separate or severable from the remaining portions of the APSA. Consequently, the district court was correct to refuse Mirant’s motion to reject its obligations under the BTB agreement under § 365 of the Bankruptcy Code.
B
As we have determined that the BTB agreement is not severable and thus not eligible for § 365 rejection, determination of the applicable standard a debtor must meet for rejection is unnecessary. Nevertheless, we should recognize that the purpose of § 365 rejection is to free the debt- or from agreements that would hinder or disable reorganization.
See, e.g., National Labor Relations Board v. Bildisco & Bildisco,
465 U.S. 513, 104 S.Ct. 1188, 1197, 79 L.Ed.2d 482 (1984) (“The fundamental purpose of reorganization is to prevent a debtor from going into liquidation ____ Thus, the authority to reject an executory contract is vital to the basic purpose of a Chapter 11 reorganization, because rejection can release the debtor’s estate from burdensome obligations that can impede a successful reorganization.”);
In re Nat’l Gypsum Co.,
208 F.3d 498, 504 (5th Cir.2000) (holding that the purpose of § 365 is to “release the debtor’s estate from burdensome obligations that can impede successful reorganization”);
Richmond Leasing Co.,
762 F.2d at 1310 (“[§ 365] ... serves the purpose of making the debtor’s rehabilitation more likely”). Mirant is currently operating under a plan of reorganization approved on December 9, 2005, which provides for continuing performance under the BTB agreement
and
for payment to all its pre-petition creditors in full. Consequently it does not appear on the record before us that performance of the BTB obligations is causing any hindrance to Mirant’s successful reorganization.
Having determined that the district court’s order denying Mirant’s first motion to reject was not error, we turn now to review the March 1 and March 16, 2005 district court orders requiring Mirant to perform its obligations under the BTB agreement pending resolution of its second motion to reject.
II
In appeal number 05-10419, Mirant raises two points of error: first, the district court’s withdrawal from the bankruptcy court of Mirant’s second motion to reject and related pleadings to allow the district court to decide these motions; and second, the district court’s order requiring Mirant to perform its obligations under the BTB agreement pending court approval of Mir-ant’s requested rejection under § 365. Each issue will be considered in turn:
Mirant classifies the district court’s withdrawal of the second motion to reject and related proceedings from the bankruptcy court as a “complete disruption of
the court system.” Mirant contends that the district court erred in withdrawing these pleadings from the bankruptcy court. Matters under Chapter 11 are within the district court’s original jurisdiction, and reference to and withdrawal from the bankruptcy court of bankruptcy matters is left to the discretion of the district court. 28 U.S.C. § 157(a) (2005). Thus, as PEP-CO correctly notes, an order withdrawing referral of a matter from bankruptcy court
is not
a final appealable order, and thus, this court has no appellate jurisdiction to review an appeal from such an order.
See In re Matter of Lieb,
915 F.2d 180, 183 (5th Cir.1990) (finding no appellate jurisdiction to review a district court’s determination regarding withdrawal as the order was “neither final nor collateral”);
see also Caldwellr-Baker Co. v. Parsons,
392 F.3d 886 (7th Cir.2004) (citing cases from the First, Second, Third, Fifth, Seventh, Ninth, Tenth and Eleventh Circuits, finding that
no circuit
considering the issue has found appellate jurisdiction to review a grant or denial of withdrawal).
In its final point of error in this second appeal, Mirant raises questions relating to the portions of the March 1 and March 16, 2005 orders requiring it to perform its obligations under the BTB agreement during the pendency of its second motion to reject. Mirant argues that unless and until an executory contract is assumed or rejected, Mirant has no legal obligation to perform under that contract. Thus, Mirant contends that the district court erred in requiring it to perform under the BTB pending rejection.
Mirant’s position is contrary to “the universally accepted rule that a trustee [or debtor] cannot accept the benefits of an executory contract without accepting the burdens as
well.”
Schokbeton Indus., Inc. v. Schokbeton Prods. Corp.,
466 F.2d 171, 175 (5th Cir.1972);
see also Bildisco,
104 S.Ct. at 1199 (“If the debtor ... continue[s] to receive benefits from the other party to an executory contract pending a decision to reject or assume the contract ... the debt- or ... is obligated to pay.”) (internal citations omitted).
Mirant argues that it has received no post-petition benefit from the BTB agreement and thus does not fall under this generally accepted principle. This contention has no basis. Mirant has made no attempts or offers to compensate PEPCO for the $500 million discount Mirant received on the sale price of the generating facilities; it continues to distribute electricity along PEPCO’s lines using the inter-connection agreements; it continues to operate plants on land owned by PEPCO per the lease agreements; it continues to access certain generating and transfer facilities per the easement agreements; and so on. Each day of operation Mirant benefits from the rights and privileges it obtained
in exchange for
the obligations associated with the assignment of the over-market PPAs and the requirements of the BTB agreement. Mirant will continue to receive these benefits as PEPCO is required by the automatic stay to perform under all these on-going portions of the APSA, unless and until rejection is approved. Despite Mirant’s cites to general bankruptcy principles, there is no authority to support the position that Mirant may force PEPCO to continue performance under the BTB while Mirant discontinues and refuses payment without court permission, indeed in defiance of court order.
By the time the district court issued the March orders, Mirant had been directly or indirectly ordered to perform under the BTB at least four times.
Further, to the extent Mirant argues that its second motion to reject cured any problems with its prior non-performance this argument is wholly without merit.
Thus, the district
court did not err in ordering Mirant to perform under the BTB pending rejection approval.
Ill
For the reasons stated herein, we hold that the BTB agreement is not severable from the APSA and is thus not eligible for rejection under 11 U.S.C. § 365. Further, we hold that the order of the district court withdrawing Mirant’s second motion to reject and related pleadings from the district court is not a final appealable order. Consequently, we have no appellate jurisdiction to review the withdrawal. Additionally, we find that the district court did not err in ordering Mirant’s performance under the BTB agreement pending resolution of the second motion to reject. For these reasons, the district court order of December 9, 2004 involved in appeal no. 05-10038, and the March 1, and March 16, 2005 orders involved in appeal 05-10419 are affirmed.
Mirant is cautioned that, while we welcome legitimate appeals, any future appeals that continue the pattern of attempts to reject the BTB agreement or efforts to refuse payment pending rejection may well invite the most severe sanctions available to this court.
AFFIRMED; SANCTIONS WARNING ISSUED.