Mkr Services, LLC v. Dean Hart Const.

16 So. 3d 562
CourtLouisiana Court of Appeal
DecidedJuly 8, 2009
Docket44,456-CA
StatusPublished

This text of 16 So. 3d 562 (Mkr Services, LLC v. Dean Hart Const.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mkr Services, LLC v. Dean Hart Const., 16 So. 3d 562 (La. Ct. App. 2009).

Opinion

16 So.3d 562 (2009)

MKR SERVICES, L.L.C., Plaintiff-Appellee
v.
DEAN HART CONSTRUCTION, L.L.C., d/b/a Dean Hart Construction Company, Defendant-Appellant.

No. 44,456-CA.

Court of Appeal of Louisiana, Second Circuit.

July 8, 2009.

*563 William H. Hallack, Jr., West Monroe, Breithaupt, Dunn, Dubos, & Shafto by Michael L. DuBos, Monroe, for Appellant.

Gregory Scott Moore, for Appellee.

Before BROWN, STEWART, and MOORE, JJ.

BROWN, Chief Judge.

In 2004, MKR Services, L.L.C. ("MKR") approached Dean Hart Construction, L.L.C. ("DHC") for assistance in designing and building an upscale 11-unit apartment complex in West Monroe, Louisiana. Before the parties reduced their agreement to writing, DHC prepared a proposal of the project to assist MKR in obtaining financing from Richland State Bank. After MKR and DHC presented the proposal to Richland State Bank, MKR advised DHC that it needed to present a construction contract and a set of plans to Richland State Bank in order to receive a loan for the project.

On March 7, 2006, MKR and DHC entered into a contract entitled "Dean Hart Construction Company, L.L.C., Lump Sum Construction Contract." This contract, written by DHC, stated that the lump sum price for the work to be performed was $605,000, or more specifically $55,000 per unit. The contract further split the design/build process into multiple phases, with certain amounts of money due at different phases and, in the event of cancellation, escalating cancellation fees dependent on which phase the project was in. Lastly, the contract also provided that MKR could make alterations, deviations, additions, or omissions from the drawings, plans, and specifications, but that DHC shall value or appraise such alterations, and add to or deduct from the amount any excess or deficiency occasioned by such changes. Any requested changes were required to be documented by a written change order signed by both DHC and MKR.

After being paid for work performed in phases I and II, DHC began performing work as set forth in phase III. During phase III, DHC sent Diane Humble, a decorator, to MKR for the selection of building materials. The building materials that MKR had to select from did not reference any prices or designate which materials were within the construction budget.[1] Furthermore, during phase III the plans were submitted to several governmental and utility entities in order to obtain approval of the plans and to secure any permits needed.[2]

*564 After receiving responses from the governmental and utility entities, Bill Brasher, an operations manager for DHC, began conducting an estimation of construction costs. Brasher met with MKR on October 11, 2006, and informed it that the project would incur cost increases of $94,505. DHC claimed that the increase was a result of changes to the plans required by the governmental and utility entities, the additional costs associated with the more expensive building materials selected by MKR and the costs of adding one more a/c unit per apartment, as requested by MKR.[3]

A subsequent meeting was held between MKR and DHC on October 24, 2006. At this meeting DHC informed MKR that it could not build the apartment complex for $605,000 unless plans were made to reduce or eliminate costs. No agreement was reached by the parties.

On January 3 and 9, 2007, DHC sent correspondence to MKR placing them in default for not approving the final plans and specifications within a timely manner. Further, the correspondence requested payment of $27,485.15 for MKR's alleged default.

MKR filed suit against DHC on February 14, 2007, alleging a bad faith breach of contract and requesting damages. DHC answered MKR's suit and filed a reconventional demand on March 6, 2007. MKR filed its answer to the reconventional demand on March 26, 2007, and an amended answer on May 1, 2008.

Trial was held on June 25-26, 2008. The trial court found that DHC breached its obligation to construct the apartment complex for the lump sum price of $605,000, rendered judgment in favor of MKR in the amount of $13,075, and dismissed DHC's reconventional demand. The judgment amount comprised the monies that MKR paid DHC in phases I and II, as well as a portion of the amount MKR paid DHC for a partially completed site clearing.

DHC has appealed the adverse judgment, and MKR answered the appeal. We affirm.

Discussion

Contracts have the effect of law for the parties thereto. La. C.C. art. 1983. To interpret a contract, courts must determine the common intent of the parties. La. C.C. art. 2045. When the words of a contract are clear and explicit and lead to no absurd consequences, no further interpretation may be made in search of the parties' intent. La. C.C. art. 2046.

There are three basic types of construction contracts recognized by Louisiana jurisprudence: lump sum contracts, cost plus percentage of the cost contracts (percentage contracts), and cost plus a fixed fee contract. Schiro-Del Bianco Enterprises, Inc. v. NSL, Inc., 99-1237 (La. App. 4th Cir.05/24/00), 765 So.2d 1087, writ denied, 00-2509 (La.11/13/00), 774 So.2d 146. The difference between both the cost plus a fixed fee contract and the percentage contract, and a lump sum contract, is that the two former types of contracts assure the contractor's profit, whereas on a lump sum contract it is possible that the contractor's anticipated and expected profit may turn into a loss because of a low bid or the rising prices of materials and/or labor. Standard Oil Co. of Louisiana v. Fontenot, 198 La. 644, 4 So.2d 634 (1941).

In the case sub judice, the trial court determined that the parties entered into a lump sum contract, and that as a result of DHC's refusal to perform its obligation for the agreed upon amount, it had breached *565 the contract. The trial court further found that there was no evidence to support DHC's position that the additional costs it was demanding were the result of alterations requested by MKR and/or governmental entities. The trial court determined, however, that DHC's breach was not committed in bad faith. After reviewing the record we do not find that the trial court erred in making its determinations.

The parties executed a contract entitled "Dean Hart Construction Company, L.L.C., Lump Sum Construction Contract." The only price referenced in the document, which DHC drafted, was the lump sum price of $605,000, and that amount included "all labor and materials, sales tax and permits required for completion of the work in accordance with the Final Drawings, Plans and Specifications attached hereto." The final drawings, plans and specifications, however, were not attached thereto. Thus, it appears as if DHC put the proverbial cart before the horse by blindly contracting to build MKR an upscale 11-unit apartment complex for the lump sum price of $605,000 prior to actually making the determination if such was feasible and/or profitable.

DHC contends that it could have constructed the apartment complex for the agreed upon price were it not for the additional costs occasioned by MKR's design changes and "extravagant" material selections and the required changes of governmental and utility entities. The evidence in the record reflects that DHC presented MKR an overages list which detailed the exact overage amount that resulted from the required and requested changes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. Lare
779 So. 2d 808 (Louisiana Court of Appeal, 2000)
Schiro-Del Bianco Enterprises v. Nsl
765 So. 2d 1087 (Louisiana Court of Appeal, 2000)
Bond v. Broadway
607 So. 2d 865 (Louisiana Court of Appeal, 1992)
Standard Oil Co. of Louisiana v. Fontenot
4 So. 2d 634 (Supreme Court of Louisiana, 1941)
MKR Services, L.L.C. v. Dean Hart Construction, L.L.C.
16 So. 3d 562 (Louisiana Court of Appeal, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
16 So. 3d 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mkr-services-llc-v-dean-hart-const-lactapp-2009.