MJF ELECTRICAL CONTRACTING INC. v. TOMS RIVER BOARD OF EDUCATION

CourtDistrict Court, D. New Jersey
DecidedMarch 26, 2021
Docket3:20-cv-07336
StatusUnknown

This text of MJF ELECTRICAL CONTRACTING INC. v. TOMS RIVER BOARD OF EDUCATION (MJF ELECTRICAL CONTRACTING INC. v. TOMS RIVER BOARD OF EDUCATION) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MJF ELECTRICAL CONTRACTING INC. v. TOMS RIVER BOARD OF EDUCATION, (D.N.J. 2021).

Opinion

NOT FOR PUBLICATION

UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

MJF ELECTRICAL CONTRACTING, INC., Plaintiff, Civil Action No. 20-7336 (MAS) (LHG) " MEMORANDUM OPINION TOMS RIVER BOARD OF EDUCATION AND MASER CONSULTING, P.A., Defendants.

SHIPP, District Judge This matter comes before the Court upon Defendant Maser Consulting, P.A.’s (*Maser” or “Defendant”) Motion to Dismiss Plaintiff MJF Electrical Contracting, Inc.°s (*MJF” or “Plaintiff’} Complaint. (ECF No. 7.) Plaintiff opposed (ECF No. 12), and Maser replied (ECF No. 14). The Court has carefully considered the parties’ submissions and decides the matter without oral argument pursuant to Local Civil Rule 78.1. For the reasons set forth below, Defendant’s Motion is granted. I. BACKGROUND! Toms River Board of Education (“TRBOE™) is a New Jersey board of education constituted, authorized, and governed by the laws of the State of New Jersey. (Compl. J 3, ECF No. 1.) “Maser is a professional engineering firm organized and existing under the laws of the

For the purposes of a motion to dismiss, the Court accepts as true and summarizes the factual allegations of the Complaint. See Phillips v. Cnty. of Allegheny, 515 F.3d 224, 233 (3d Cir. 2008).

State of New Jersey.” (/d. 75.) “Maser is the [TRBOE’s] engineer and provides [TRBOE] with architectural and professional engineering services.” (/d. J 6.) Plaintiff alleges that “[iJn or about 2018, the [TRBOE] retained Maser to assist it with the *Rebuilding our Schools[,]’ [Toms River Regional Schools’ (“TRRS”)] Energy Savings Improvement Program (“ESIP”) and to prepare the drawings and specifications for the project known as ‘ESIP Lighting Replacement & Associated Work @ Various Locations Within The Toms River Regional School District’ (the “Project”).” (Ud. 4 11.) Among other things, the Project consisted of “the replacement of lights in existing fixtures at 24 different TRRS locations, including the removal and replacement of emergency exit signs and the removal and replacement of emergency lighting/battery units.” (/d. J 12.) In or around December 7, 2018, MJF submitted a bid to the TRBOE for the Project. □□□□ {| 36-37.) “In preparing its bid for the Project. Plaintiff relied upon the Project drawings and specifications prepared by the [TRBOE] and Maser.” (/d. § 38.) But according to Plaintiff, the drawings “materially misrepresented” certain conditions relating to the Project. (/d. 55.) Maser’s drawings allegedly depicted “the locations of the lighting fixtures, which would receive new lights, as well as the locations of the emergency exit signs and emergency lighting/battery units which were to be replaced.” (/d. 7 13.) Critically, however, Plaintiff alleges that the Project drawings “depicted the installation, by use of a symbol, in certain locations. of ‘branch circuit wiring concealed in walls and above ceiling[s]* in only certain. limited locations in the Project drawings.” (id. §§ 14-15.) Plaintiff alleges that “[b]y using the concealed branch wiring symbol in these few limited locations,” and “because the concealed branch wiring symbol did not accompany the symbols for the new emergency exit signs and emergency lighting/battery units, the [TRBOE] and Maser represented to MJF and the other bidders, that concealed branch wiring was nor needed in

locations for the new emergency exit signs and the new emergency lighting/battery units.” (Jed. § 16.) Relatedly, Plaintiff alleges that on November 21, 2018, twelve days prior to the date for receipt of bids for the Project, “the [TRBOE] and Maser issued a “Question and Answer Document” concerning bidding for the Project. This Q&A Document was issued by Maser to all prospective bidders including [P]laintiff.” (/d. 4 25.) The Q&A Document noted that not “all emergency exit fixtures, as called out on the drawings” were replacements of existing fixtures. (/d. J] 26-27.) Rather, some of the emergency exit fixtures, as called out in the drawings, were new and the “[cJontractor [was] to price this item as shown on the drawings for each school.” (/d. § 27.) Plaintiff alleges that the answer to this question implied “that only some of the exit signs and emergency lighting/battery units were new, meaning that they were not replacements.” (/d. J 30.) Furthermore. Plaintiff maintains that the other implication of the above Q&A answer was that ‘replacements’ were in the same location as pre-existing emergency exit signs and emergency lighting/battery units in the schools.” (/d. 4 32.) According to Plaintiff, the TRBOE and Maser could have easily provided Plaintiff and the other bidders with a complete and comprehensive list and location of all exit signs and emergency lighting/battery units which were ‘new (meaning that concealed branch wiring was needed) and all exit signs and emergency [lighting/battery units) which were ‘replacements’ of pre-existing [fixtures] (meaning that no concealed branch wiring was needed). (/d. § 34.) Plaintiff maintains that “in preparing its bid for the Project, Plaintiff... relied upon the answer(s]... in the Q&A Document.” (/d. { 38.) Ultimately. “Plaintiff was the low bidder for 17 of the locations included in the Project.” (id. § 40.) In July 2019, however, “soon after commencement of its work under the Contract, Plaintiff informed the [TRBOE] and Maser that Plaintiff was performing additional and

unanticipated work on the Project consisting variously of the installation of concealed branch circuit wiring between the ‘new’ exit signs and ‘new’ emergency lighting/battery units (the *Additional Work’).” (/d. 9 42.) Plaintiff reports, by way of one example, “at Beachwood Elementary School, one of the 17 locations included in the Contract, there were 191 ‘new’ “emergency” fixtures, whereas there were only a small number of pre-existing fixtures to be removed. The situation at Beachwood was replicated at the remaining 16 locations covered by the Contract.” (/d. 44.) Although Plaintiff reports attempting to negotiate additional compensation for the Additional Work and clarifications of the scope of its work, Plaintiff alleges that the negotiations have not produced additional compensation. (/d. J] 45-52.) Plaintiff filed this action on June 16, 2020. (ECF No. |.) The Complaint alleges breach of contract, fraudulent inducement, unjust enrichment, and quantum meruit claims against TRBOE. (id. J§ 53-76.) Plaintiff brings a single negligent misrepresentation claim against Maser. (/d. 77-88.) In the Motion now before the Court, Maser moves to dismiss Plaintiff's negligent misrepresentation claim.” Il. LEGAL STANDARD District courts undertake a three-part analysis when considering a motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6). Malleus v. George, 641 F.3d 560, 563 (3d Cir. 2011). “First, the court must *tak[e] note of the elements a plaintiff must plead to state a claim."” /d. (quoting Ashcroft v. fgbal. 556 U.S. 662. 675 (2009)) (alteration in original). Second, the court must accept as true all of the plaintiff's well-pled factual allegations and “construe the complaint in the light most favorable to the plaintiff.” Fowler v. UPMC Shadyside, 578 F.3d 203, 210 (3d Cir. 2009) (quotation omitted). In doing so, the court is free to ignore legal conclusions or

> TRBOE has answered the Complaint. (ECF No. 13.)

factually unsupported accusations that merely state “the-defendant-unlawfully-harmed-me.” Iqbal, 556 U.S. at 678 (citing Bell Atl, Corp. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Karen Malleus v. John George
641 F.3d 560 (Third Circuit, 2011)
Burtch v. Milberg Factors, Inc.
662 F.3d 212 (Third Circuit, 2011)
Phillips v. County of Allegheny
515 F.3d 224 (Third Circuit, 2008)
Hunt v. United States Tobacco Co.
538 F.3d 217 (Third Circuit, 2008)
Fowler v. UPMC SHADYSIDE
578 F.3d 203 (Third Circuit, 2009)
Petrillo v. Bachenberg
655 A.2d 1354 (Supreme Court of New Jersey, 1995)
Polzo v. County of Essex
960 A.2d 375 (Supreme Court of New Jersey, 2008)
Carter Lincoln-Mercury, Inc. v. Emar Group, Inc.
638 A.2d 1288 (Supreme Court of New Jersey, 1994)
Kaufman v. I-Stat Corp.
754 A.2d 1188 (Supreme Court of New Jersey, 2000)
Conforti & Eisele, Inc. v. John C. Morris Assoc.
489 A.2d 1233 (New Jersey Superior Court App Division, 1985)
Conforti & Eisele, Inc. v. John C. Morris Assocs.
418 A.2d 1290 (New Jersey Superior Court App Division, 1980)
Dynalectric Co. v. Westinghouse Electric Corp.
803 F. Supp. 985 (D. New Jersey, 1992)
Bracco Diagnostics Inc. v. Bergen Brunswig Drug Co.
226 F. Supp. 2d 557 (D. New Jersey, 2002)
People Express Airlines, Inc. v. Consolidated Rail Corp.
495 A.2d 107 (Supreme Court of New Jersey, 1985)
H. Rosenblum, Inc. v. Adler
444 A.2d 66 (New Jersey Superior Court App Division, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
MJF ELECTRICAL CONTRACTING INC. v. TOMS RIVER BOARD OF EDUCATION, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mjf-electrical-contracting-inc-v-toms-river-board-of-education-njd-2021.