M&J Underground, Inc v. Village of Bourbonnais
Opinion
NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).
2022 IL App (3d) 210349-U
Order filed October 19, 2022
IN THE
APPELLATE COURT OF ILLINOIS THIRD DISTRICT
2022
M&J UNDERGROUND, INC. ) Appeal from the Circuit Court ) of the 21st Judicial Circuit, Plaintiff-Appellant, ) Kankakee County, Illinois.
)
v. ) Appeal No. 3-21-0349 ) Circuit No. 19-L-157 VILLAGE OF BOURBONNAIS, )
) Honorable Adrienne W. Albrecht, Defendant-Appellee, ) Judge, Presiding.
JUSTICE McDADE delivered the judgment of the court.
Justices Hauptman and Peterson concurred in the judgment.
ORDER
¶1 Held: The circuit court’s order granting defendant’s motion to dismiss plaintiff’s second amended complaint with prejudice is reversed. The matter is remanded to the circuit court for further proceedings.
¶2 Plaintiff, M&J Underground, Inc., executed a construction contract with defendant, Village of Bourbonnais (the “Village”), after successfully bidding on the Village’s public improvement project. Performance of the contract imposed additional unanticipated costs on M&J for managing preexisting but unknown soil and water conditions on the project site. After multiple delays and monetary disputes, M&J informed the Village that it was suspending work
on the project. The Village terminated the contract and hired a new contractor. M&J brought suit in the circuit court for breach of contract. After allowing two amendments, the court dismissed M&J’s second amended complaint with prejudice. M&J now appeals, specifically challenging the dismissal of two counts in the second amended complaint.
¶3 FACTS
¶4 On June 8, 2018, M&J entered into a written contract with the Village to provide underground utility construction services in connection with an improvement project. M&J was chosen as the project contractor after submitting a bid proposal and contract offer, which the Village accepted. During the bidding process, there was no easement that allowed either the Village or M&J on the designated project site. Instead, Tyson Engineering, Inc., prepared soil boring specifications for the Village. The boring results were not reflective of the actual soil conditions because they had been taken at elevations significantly higher than the surface of the project site and did not show any water conditions for the site specified.
¶5 Under the contract, M&J would furnish labor, equipment and materials for its construction and installation of a lift station, sanitary sewer along US Route 45/52 (the “highway”). The work was to be completed by May 15, 2019. The contract also expressly imposed certain requirements and restrictions on M&J in relation to its performance of the work: (1) M&J had sole responsibility for knowledge of the ground conditions on the project site, including doing soil borings if necessary; (2) M&J could not rely on any soil borings provided by the Village as a convenience, nor could the need to obtain easements be used to excuse delays; (3) M&J had full control over the means and methods of performing the job; and (4) any extra work that was not approved in advance by a written change order would not be compensated. The completed work to be performed was valued at $1.8 million.
¶6 After M&J’s bid and proposal were accepted, the contract was prepared by the Village and executed by the parties, M&J immediately began encountering multiple impediments to its performance. At the outset, work on the project was delayed for six months because the Village had not secured an easement critical to its performance. The Village eventually secured authorization for M&J to begin performance, and the work started on January 9, 2019. Soon after, performance was halted again after M&J discovered an unforeseen subsurface water condition. This condition required an engineering review of the soil and hydraulic conditions, the securing of an excavation permit from the Illinois Department of Transportation (“IDOT”), and the performance of soil boring tests. These unanticipated activities imposed additional costs on M&J and further delayed performance on the project.
¶7 The project continued to be plagued by problems and the delays persisted. During the delays, M&J continued to provide the labor, equipment, supplies and materials necessary to perform the work as required by the contract. It also continued discussions with representatives of the Village who repeatedly told M&J that its change orders were being processed and led M&J to believe that the Village would pay for the additional costs and expenses related to the water conditions. On March 4, 2019, the Village finally signed Change Order No. 1, approving payment to M&J of $94,100 for these costs accrued in January and February 2019 due to the water condition.
¶8 Assured that its costs would be covered, M&J continued performing under the contract. A portion of the work required it to bore under the highway. The contract provided that boring would be performed by a method known as “augered [sic] jack and bore,” which required installing horizontal casing platforms under the highway and simultaneously excavating the soil with rotating cutting head. Because of the water conditions, M&J believed that this method
would result in a collapse of and damage to the highway. It retained a soil engineer to review the conditions and advise it on how to proceed. The engineer determined that the project could not be performed using the method prescribed in the contract. M&J advised the Village and contacted IDOT, which stated that the permit issued to the Village only allowed excavation by the augered jack and bore method. IDOT explained that it was not aware of the water conditions when it issued the permit and advised M&J that no dewatering would be allowed under the highway. M&J advised the Village of this decision. The Village explained that the choice of means and methods of completing the project was up to M&J, which would be responsible for any additional cost for completing the project.
¶9 On September 30, 2019, the Village informed M&J that going forward, M&J would be solely responsible for any additional costs in connection with performing its contractual obligations. M&J ultimately ceased performance on the project and the Village advised M&J on October 30, 2019, that it would be retaining a replacement contractor. M&J filed its initial complaint, alleging breach of contract. The Village filed a motion to dismiss the initial complaint and M&J twice amended the complaint. M&J’s second amended complaint is the one at issue in this appeal. It alleged six counts including a breach of contract claim (count I) and a request for accounting (count VI).
¶ 10 In count I, M&J alleged that the Village “breached the covenant of good faith and fair dealing by making certain representations but then acting in a completely contrary manner.” It contended that the Village’s representative told M&J that change orders were being processed and advised M&J to proceed with performance. M&J also contended that the Village failed to provide it with accurate information regarding soil conditions and boring requirements. M&J argued that inaccurate boring information resulted in the delays. In count I, M&J claimed that
because of the Village’s behavior, M&J incurred (1) labor and equipment costs of $583,354; (2) delay costs of $209,658.80; and (3) costs for additional time and lost production of $34,000.
Free access — add to your briefcase to read the full text and ask questions with AI
2022 IL App (3d) 210349-U (M&J Underground, Inc v. Village of Bourbonnais) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.