M&J Underground, Inc v. Village of Bourbonnais

2022 IL App (3d) 210349-U
CourtAppellate Court of Illinois
DecidedOctober 19, 2022
Docket3-21-0349
StatusUnpublished

This text of 2022 IL App (3d) 210349-U (M&J Underground, Inc v. Village of Bourbonnais) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M&J Underground, Inc v. Village of Bourbonnais, 2022 IL App (3d) 210349-U (Ill. Ct. App. 2022).

Opinion

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

2022 IL App (3d) 210349-U

Order filed October 19, 2022 ____________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

M&J UNDERGROUND, INC. ) Appeal from the Circuit Court ) of the 21st Judicial Circuit, Plaintiff-Appellant, ) Kankakee County, Illinois. ) v. ) Appeal No. 3-21-0349 ) Circuit No. 19-L-157 VILLAGE OF BOURBONNAIS, ) ) Honorable Adrienne W. Albrecht, Defendant-Appellee, ) Judge, Presiding. __________________________________________________________________________

JUSTICE McDADE delivered the judgment of the court. Justices Hauptman and Peterson concurred in the judgment. ____________________________________________________________________________

ORDER

¶1 Held: The circuit court’s order granting defendant’s motion to dismiss plaintiff’s second amended complaint with prejudice is reversed. The matter is remanded to the circuit court for further proceedings.

¶2 Plaintiff, M&J Underground, Inc., executed a construction contract with defendant,

Village of Bourbonnais (the “Village”), after successfully bidding on the Village’s public

improvement project. Performance of the contract imposed additional unanticipated costs on

M&J for managing preexisting but unknown soil and water conditions on the project site. After

multiple delays and monetary disputes, M&J informed the Village that it was suspending work on the project. The Village terminated the contract and hired a new contractor. M&J brought suit

in the circuit court for breach of contract. After allowing two amendments, the court dismissed

M&J’s second amended complaint with prejudice. M&J now appeals, specifically challenging

the dismissal of two counts in the second amended complaint.

¶3 FACTS

¶4 On June 8, 2018, M&J entered into a written contract with the Village to provide

underground utility construction services in connection with an improvement project. M&J was

chosen as the project contractor after submitting a bid proposal and contract offer, which the

Village accepted. During the bidding process, there was no easement that allowed either the

Village or M&J on the designated project site. Instead, Tyson Engineering, Inc., prepared soil

boring specifications for the Village. The boring results were not reflective of the actual soil

conditions because they had been taken at elevations significantly higher than the surface of the

project site and did not show any water conditions for the site specified.

¶5 Under the contract, M&J would furnish labor, equipment and materials for its

construction and installation of a lift station, sanitary sewer along US Route 45/52 (the

“highway”). The work was to be completed by May 15, 2019. The contract also expressly

imposed certain requirements and restrictions on M&J in relation to its performance of the work:

(1) M&J had sole responsibility for knowledge of the ground conditions on the project site,

including doing soil borings if necessary; (2) M&J could not rely on any soil borings provided by

the Village as a convenience, nor could the need to obtain easements be used to excuse delays;

(3) M&J had full control over the means and methods of performing the job; and (4) any extra

work that was not approved in advance by a written change order would not be compensated.

The completed work to be performed was valued at $1.8 million.

2 ¶6 After M&J’s bid and proposal were accepted, the contract was prepared by the Village

and executed by the parties, M&J immediately began encountering multiple impediments to its

performance. At the outset, work on the project was delayed for six months because the Village

had not secured an easement critical to its performance. The Village eventually secured

authorization for M&J to begin performance, and the work started on January 9, 2019. Soon

after, performance was halted again after M&J discovered an unforeseen subsurface water

condition. This condition required an engineering review of the soil and hydraulic conditions, the

securing of an excavation permit from the Illinois Department of Transportation (“IDOT”), and

the performance of soil boring tests. These unanticipated activities imposed additional costs on

M&J and further delayed performance on the project.

¶7 The project continued to be plagued by problems and the delays persisted. During the

delays, M&J continued to provide the labor, equipment, supplies and materials necessary to

perform the work as required by the contract. It also continued discussions with representatives

of the Village who repeatedly told M&J that its change orders were being processed and led

M&J to believe that the Village would pay for the additional costs and expenses related to the

water conditions. On March 4, 2019, the Village finally signed Change Order No. 1, approving

payment to M&J of $94,100 for these costs accrued in January and February 2019 due to the

water condition.

¶8 Assured that its costs would be covered, M&J continued performing under the contract.

A portion of the work required it to bore under the highway. The contract provided that boring

would be performed by a method known as “augered [sic] jack and bore,” which required

installing horizontal casing platforms under the highway and simultaneously excavating the soil

with rotating cutting head. Because of the water conditions, M&J believed that this method

3 would result in a collapse of and damage to the highway. It retained a soil engineer to review the

conditions and advise it on how to proceed. The engineer determined that the project could not

be performed using the method prescribed in the contract. M&J advised the Village and

contacted IDOT, which stated that the permit issued to the Village only allowed excavation by

the augered jack and bore method. IDOT explained that it was not aware of the water conditions

when it issued the permit and advised M&J that no dewatering would be allowed under the

highway. M&J advised the Village of this decision. The Village explained that the choice of

means and methods of completing the project was up to M&J, which would be responsible for

any additional cost for completing the project.

¶9 On September 30, 2019, the Village informed M&J that going forward, M&J would be

solely responsible for any additional costs in connection with performing its contractual

obligations. M&J ultimately ceased performance on the project and the Village advised M&J on

October 30, 2019, that it would be retaining a replacement contractor. M&J filed its initial

complaint, alleging breach of contract. The Village filed a motion to dismiss the initial complaint

and M&J twice amended the complaint. M&J’s second amended complaint is the one at issue in

this appeal. It alleged six counts including a breach of contract claim (count I) and a request for

accounting (count VI).

¶ 10 In count I, M&J alleged that the Village “breached the covenant of good faith and fair

dealing by making certain representations but then acting in a completely contrary manner.” It

contended that the Village’s representative told M&J that change orders were being processed

and advised M&J to proceed with performance. M&J also contended that the Village failed to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landers v. Andrews Fronczek
532 N.E.2d 265 (Appellate Court of Illinois, 1988)
International Supply Co. v. Campbell
907 N.E.2d 478 (Appellate Court of Illinois, 2009)
W. E. Erickson Construction, Inc. v. Congress-Kenilworth Corp.
503 N.E.2d 233 (Illinois Supreme Court, 1986)
Evans and Associates, Inc. v. Dyer
615 N.E.2d 770 (Appellate Court of Illinois, 1993)
Cwikla v. Sheir
801 N.E.2d 1103 (Appellate Court of Illinois, 2003)
Vogt v. Round Robin Enterprises, Inc.
2020 IL App (4th) 190294 (Appellate Court of Illinois, 2021)
Tufo v. Tufo
2021 IL App (1st) 192521 (Appellate Court of Illinois, 2021)
People ex rel. Peterson v. Omen
124 N.E. 860 (Illinois Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
2022 IL App (3d) 210349-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mj-underground-inc-v-village-of-bourbonnais-illappct-2022.