Mittry v. BonneVille County

222 P. 292, 38 Idaho 306, 1923 Ida. LEXIS 89
CourtIdaho Supreme Court
DecidedNovember 27, 1923
StatusPublished
Cited by11 cases

This text of 222 P. 292 (Mittry v. BonneVille County) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mittry v. BonneVille County, 222 P. 292, 38 Idaho 306, 1923 Ida. LEXIS 89 (Idaho 1923).

Opinion

MCCARTHY, J.

— This is an action against appellant county to recover the balance of the contract price for the erection of a courthouse. 'The complaint alleges that the respondent copartnership and appellant county entered into a written contract by which the former agreed to erect a courthouse for the latter for the contract price of $152,525; that said building was erected and completed in accordance with the contract and was accepted by the architects; that in accordance with a provision of the contract authorizing such alterations as might be ordered by the architect, certain alterations were made at a cost of $6,816.73, making the total cost $159,341.73; that appellant has paid respondent $140,461.08, leaving a balance of $18,880.65; that respondent presented a claim for this balance to the board of county commissioners, which was rejected. Within the sis months allowed by the statute respondent sued for the balance. To this complaint appellant demurred generally' and specially. It also answeréd alleging that the contract was ultra vires and void under the provisions of Const., VIII, 3, and C. S., [309]*309secs. 3463 and 3464. These questions are also raised by the affirmative defense. The facts alleged in that regard are as follows: The people of appellant county voted bonds in the amount of $250,000 for procuring a courthouse site and building a courthouse. $40,000 of said fund was used for a site. Respondent’s contract covered only part of the work of erecting the courthouse and other contracts were let covering other parts. The total amount of these contracts exceeded the amount left of the $250,000, which had been voted by the people. By reason of these facts appellant had no funds available for the payment of the balance of the contract price. 'The court found that the contract was let, the work and alterations were completed in ■ accordance with the contract, and the full contract price, including the alterations, was $159,341.73. As to the validity of the contract and claim the court made the following finding:

‘1 That at the time the said contract was made and entered into by the plaintiffs and the defendant, and delivered to the plaintiffs, there was in the courthouse construction fund of said County out of which the expenditures to be made under the terms of said contract, were to be paid, the sum of $167,810.00, all of which was unappropriated and no contracts had been made by defendant payable out of said unappropriated balance of said fund; that said sum had been raised through the sale of bonds of the said County, authorized by vote of the qualified electors of said County for the purpose; and that all formalities in respect to advertising for bids and letting said contract were complied with prior to the execution and delivei*y of said contract.”

Respondent had judgment for the balance of $18,880.65, with interest, from which this appeal is taken.

Appellant assigns the overruling of the demurrer as error, claiming the complaint was insufficient because it did not negative the idea that the contract was in violation of the constitutional and statutory provisions above mentioned. The court did not err in this respect. These matters were affirmative defenses and properly treated as such.

[310]*310Specifications of error numbered 12, 13, 14 and 15 deal with rulings of the court as to the admission and exclusion of evidence. We find no reversible error here.

The vital question in the case is whether the evidence is sufficient to support the finding that there was sufficient money available, properly appropriated, for the payment- of respondent’s claim at the time it was presented. Respondent contends that this question cannot be considered, because appellant does not properly specify in its brief the particulars in which the evidence is insufficient. While we do not commend the form in ^hich the question is presented, yet we think that, in substance and effect, the specifications of error in the findings may be considered as specifications of the insufficiency of the evidence.

The facts shown by the evidence are as follows: On June 3, 1919, the people of appellant county at an election authorized the issuance and sale of $250,000 of county bonds to build a courthouse and jail. These were sold at a premium of $3,175. Nighty-five dollars was added to the fund through the auction sale of some county property. The total available was thus $253,260. Approximately $12,500 was paid the architects. Thirty-one thousand six hundred and fifty dollars was paid for the foundation. Thirty-seven thousand five hundred dollars was paid for the site. All this happened before respondent’s contract was let. At the time of the letting of that contract there was only $167,810 in the courthouse fund. May 1, 1920, the board of commissioners ordered a call for bids for the erection and completion of the courthouse and jail. June 7th, at a meeting of the board the bids were opened and acted upon as shown by the following quotation from the minutes:

“June 7th, 1920. ‘This being the time heretofore fixed for receiving proposals for the erection and completion of a court house pursuant to an order and call for bids for the same made and entered on the first day of May, in the pursuance to the same the following bids and proposals under said order were submitted to this board at 2:00 p. m. on [311]*311tbe above named date. The board proceeded to open said proposals which were found to be as follows, to wit: For the erection and completion of said buildings less furniture and fixtures, as per plans and specifications as prepared by Fisher & Akin: D. J. Sweeney, $158,000; Salih Brothers, $162,320; North Pacific Construction Company, $152,525. The North Pacific Construction Company bid being the lowest and best bid," Andrew Burkman made a motion seconded by Christian Anderson that the contract for the erection of the court house be awarded to the North Pacific Construction Company, and a contract be • drawn to that effect. In the matter of bids for plumbing and heating for said court house, Bonneville County, Idaho, the following bids were submitted: George Tway, $23,165; Tarbet Heating & Plumbing Company, $20,900. The Tarbet Heating & Plumbing Company’s bid being the lowest and best bid, Andrew Burkman made a motion seconded by Christian Anderson, that said contract be awarded to the Tarbet Heating & Plumbing Company, and said contract be drawn to that effect.”

December 13, 1920, the county commissioners decided, on the advice of the architect, that certain additions should be made, to wit, an iron cornice and a fire wall. They asked only respondent to bid and accepted his bid of $5,975. It thus appears that June 7th the amount of money in the fund was $167,810 and the commissioners let contracts for the erection of the building and installing of the plumbing and heating totaling $173,425, and the addition of the extras brings the amount up to $179,400, being $11,590 in excess of the amount available. It certainly cannot be denied that both respondent’s contract and that of the heating and plumbing company were necessary for the erection and completion of the courthouse as authorized by the election and as contemplated by the call for bids and by the resolution authorizing the contracts. It is clearly proved that the cost of erecting the courthouse exceeded the income and revenue available for such purposes, and that therefore the indebtedness could not be incurred unless the necessary funds were [312]*312provided by an authorized bond issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re University Place/Idaho Water Center Project
199 P.3d 102 (Idaho Supreme Court, 2008)
University of Idaho Foundation, Inc. v. Civic Partners, Inc.
199 P.3d 102 (Idaho Supreme Court, 2008)
City of Pocatello v. Peterson
473 P.2d 644 (Idaho Supreme Court, 1970)
H. J. McNeel, Inc. v. Canyon County
277 P.2d 554 (Idaho Supreme Court, 1954)
Village of Heyburn v. Security Savings & Trust Co.
49 P.2d 258 (Idaho Supreme Court, 1935)
Lumbermen's Trust Co. v. Town of Ryegate
50 F.2d 219 (D. Montana, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
222 P. 292, 38 Idaho 306, 1923 Ida. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mittry-v-bonneville-county-idaho-1923.