Mitternight Boiler Works, Inc. v. ICL Specialty Products, Inc.

District Court, S.D. Alabama·Decided August 26, 2026·No. 1:24-cv-00294·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF ALABAMA SOUTHERN DIVISION

MITTERNIGHT BOILER WORKS, ) INC., ) ) Plaintiff/Counterclaim Defendant, ) ) v. ) Civ. Act. No.: 1:24-CV-294-TFM-B ) ICL SPECIALTY PROUCTS, INC., ) ) Defendant/Counterclaim Plaintiff. )

MEMORANDUM OPINION AND ORDER

Pending before the Court are Plaintiff’s Motion for Judgment on the Pleadings (Doc. 59, filed 9/17/25), Defendant’s Motion to Strike Expert Opinion of William Newell (Doc. 83, filed 12/19/25), Plaintiff’s Motion to Exclude Defendant’s Expert Witness (Doc. 84, filed 12/19/25), Plaintiff’s Motion for Summary Judgment (Doc. 75, filed 11/21/25) and Defendant’s Motion for Summary Judgment (Doc. 77, filed 06/30/25). Each party timely submitted their respective responses and replies. See Docs. 68, 70, 87, 88, 90, 94, 96, 97, 99, 100. Having considered the motions, responses, replies, evidentiary submissions in support of the motions, and relevant law, the Court finds as follows: Plaintiff’s motion for judgment on the pleadings (Doc. 59) is due to be GRANTED, Defendant’s motion to strike Plaintiff’s expert (Doc. 83) is due to be DENIED, Plaintiff’s motion to strike Defendant’s expert (Doc. 84) is due to be DENIED, and both motions for summary judgment (Docs. 75, 77) are due to be GRANTED in part and DENIED in part. I. PARTIES AND JURISDICTION Plaintiff/Counterclaim Defendant Mitternight Boiler Works Inc., (“Plaintiff” or “Mitternight”) is an Alabama corporation with its principal place of business in Alabama and is therefore a citizen of Alabama for jurisdictional purposes. Defendant ICL Specialty (“Defendant” or “ICL Specialty”) is a corporation formed under the laws of Delaware with its principal place of business in Missouri and is therefore a citizen of Delaware and Missouri for jurisdiction purposes. The amount in controversy exceeds $75,000. See Doc. 1 at 5-6. The Court has subject matter jurisdiction and venue over this matter pursuant to 28 U.S.C. § 1332 (diversity jurisdiction).1 The parties do not contest jurisdiction or venue, and the Court finds sufficient support exists

for both. II. BACKGROUND A. Factual Background On or around July 27, 2022, the parties entered into a Framework Agreement regarding the potential purchase of goods by ICL from Mitternight. See Doc. 77-1 at 2; Doc. 75 at 3. The parties executed the Framework Agreement after ICL sought bids for the fabrication of industrial equipment, specifically a tube bundle, and ICL awarded the project to Mitternight. Doc. 75 at 4. On or around August 2, 2022, ICL issued a Purchase Order to Plaintiff for fabrication of the tube bundle pursuant to the terms of the Framework Agreement. Doc. 77-1 at 3. Mitternight

acknowledged receipt of the Purchase Order on or around August 4, 2022. Doc. 75 at 4. Mitternight’s order acknowledgement estimated delivery of the tube bundle 50 weeks after receipt and issuance of approved shop drawings from ICL. Id. The initial Purchase Order contained a delivery date of September 1, 2023. Doc. 77-1 at 4. However, revised purchase orders were later entered which set a delivery date of December 31, 2023. Id.

1 Plaintiff’s original complaint included an additional Defendant, ICL Europe Cooperatief U.A. See Doc. 1-2. However, the parties filed a motion to dismiss ICL Europe Cooperatief U.A., which the Court granted. See Docs. 86, 89, 92, 101. Thus, ICL Europe Cooperatief U.A. was dismissed from this action with prejudice. The Framework Agreement provided that Mitternight was to give written notice to ICL for any delay in delivery of a product. Id. at 2; Doc. 77-4 at 6. The Framework Agreement further provides that “delay of more than 28 days with respect to the delivery date shall be deemed a material breach of this Agreement and Purchaser shall have the right to terminate this Agreement unilaterally with immediate effect.” Doc. 77-4 at 6. For other alleged breaches not related to the

delay of more than 28 days, the Framework Agreement requires written notice of intent to terminate for an alleged material breach and a mandatory 14-day cure period, unless the breach cannot be remedied in which case immediate termination is available. Id. at 12. Additionally, the Framework Agreement includes a nonwaiver clause. Id. at 14. The parties worked together and exchanged additional information and specifications in order for Plaintiff to build out a new and complete set of shop drawings. Doc. 75 at 5. This was necessary because the only materials to work from were old engineering drawings from the 1980s that were prepared for the original tube bundle. Id. at 4. Mitternight submitted the initial shop drawings for ICL’s review and approval on November 17, 2022. Id. at 5. ICL returned its

comments on the drawings on January 25, 2023. Id. Mitternight submitted revised shop drawings on March 22, 2023, which ICL returned and approved on May 4, 2023. Id. Mitternight also submitted Inspection and Testing Protocol (“ITP”) to ICL for approval on March 31, 2023, and asserts that ICL never returned the signed and approved ITP at any point. See id. at 5. On March 26, 2024, ICL issued a notice to Mitternight that it was considering a declaration of a contractor default and termination of the contractual agreements because the tube bundle was required to be delivered on or before December 31, 2023 based on the dates listed in the purchase order but, based on the most recent schedule provided by Mitternight, the project would not be completed until June 2024 or later. Doc. 77-1 at 4; Doc. 77-12. The March 26, 2024 notice did not reference any alleged issues with workmanship or any other default besides untimely delivery. See Doc. 77-12. On April 15, 2024, Mitternight responded that the substantial delays resulted from ICL’s failure to timely return approved, necessary drawings, welding procedures, and the ITP, along with ICL’s required change in radiographic inspection which resulted in Mitternight moving from two x-rays of each weld to three. Doc. 75 at 7-8. On April 25, 2024, ICL instructed

Mitternight to stop making new welds on the project and to only work on portions of the project that had already been started. Id. at 8. On May 15, 2024, ICL corresponded with Mitternight and again stated that Mitternight was unable to timely deliver the tube bundle and that ICL had the right to terminate the agreement on that basis. Doc. 77-15. Additionally, ICL proposed moving the tube bundle from Mitternight’s property and transfering it to an undisclosed third-party for completion of the tube bundle, along with any key documentation, drawings, and other materials associated with the tube bundle. Id. Further, ICL declined further payment for any outstanding work or past change orders. Id. On May 23, 2024, Mitternight responded that it would agree to release the tube bundle and requested documentation so long as ICL agreed to pay it for the

Free access — add to your briefcase to read the full text and ask questions with AI

Mitternight Boiler Works, Inc. v. ICL Specialty Products, Inc., (S.D. Ala. 2026).

Mitternight Boiler Works, Inc. v. ICL Specialty Products, Inc. (Mitternight Boiler Works, Inc. v. ICL Specialty Products, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Doe v. MySpace, Inc.
528 F.3d 413 (Fifth Circuit, 2008)
Jeffery v. Sarasota White Sox, Inc.
64 F.3d 590 (Eleventh Circuit, 1995)
Ortega v. Christian
85 F.3d 1521 (Eleventh Circuit, 1996)
Mize v. Jefferson City Board of Education
93 F.3d 739 (Eleventh Circuit, 1996)
City of Tuscaloosa v. Harcros Chemicals, Inc.
158 F.3d 548 (Eleventh Circuit, 1998)
Theresa St. George v. Pinellas County
285 F.3d 1334 (Eleventh Circuit, 2002)
Neal Horsley v. Geraldo Rivera
292 F.3d 695 (Eleventh Circuit, 2002)
Neal Horsley v. Gloria Feldt
304 F.3d 1125 (Eleventh Circuit, 2002)
Louise Cook v. Sheriff of Monroe County
402 F.3d 1092 (Eleventh Circuit, 2005)
United States v. Ronald Keith Brown
415 F.3d 1257 (Eleventh Circuit, 2005)
Rosario v. American Corrective Counseling Services, Inc.
506 F.3d 1039 (Eleventh Circuit, 2007)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
American Dental Assoc. v. Cigna Corp.
605 F.3d 1283 (Eleventh Circuit, 2010)