*287 LENT, J.

In this suit plaintiff seeks to reform a land sale contract and appeals from a decree in favor of defendants. The trial court found there was no antecedent agreement to which the written contract could be reformed. We affirm the result.

The essential facts are not in dispute. Where there may be dispute, we find the facts by trying the case "anew upon the record.” ORS 19.125(3).

On August 1, 1974, defendants purchased property within the boundaries of the City of Eugene for $27,000. Approximately two weeks later defendants sold the property to plaintiff for $47,500.

At the time defendants purchased the property, it contained a two-story residence at the front of the property, and a detached building at the rear of the lot. The rear building consisted of a one-bedroom, one-kitchen living unit and a three-car garage.

Shortly after defendants purchased the property, they commenced remodeling the detached building, intending to convert it for residential rental purposes. The remodeling was in progress when plaintiff viewed the property, and was not completed until after the contract of sale was executed. Defendants spent approximately $6,000 on this remodeling project, transforming the rear structure into a unit containing four bedrooms with separate locks and a common kitchen and bathroom. When defendants sold the property to plaintiff, they knew that plaintiff intended to use the property as "income property” and not as a residence for plaintiff. After the contract was executed and construction on the back building completed, defendants acted as rental agents for plaintiff, finding tenants for both the front and rear buildings.

In February or March of 1975, plaintiff heard rumors that the remodeling may have been completed without building permits. When he contacted defendants regarding this disquieting news, he was assured *288 that there was no problem and that the necessary papers would be forthcoming. Plaintiff did not receive further word from defendants, and in April, 1976, the City of Eugene notified plaintiff that the rear building had been remodeled without the required permits and must be restored to its original condition. Plaintiff also learned that the lot was zoned as a single-family residential area, and, therefore, that his use of two structures for separate rental purposes would be viola-tive of the zoning ordinance.

The written land sale contract between plaintiff and defendants contains only a lot and block description of the parcel of property involved and does not describe any structures as part of the sale. Plaintiff now contends that either because of mutual mistake or mistake on his part accompanied by inequitable conduct on the part of defendants, that instrument does not reflect the true agreement of the parties. He argues that the agreement was for the purchase of a parcel of property with two structures on it, each suitable for residential rental purposes. He asks that the written contract be reformed to conform with that agreement, that it be decreed that defendants cannot perform that agreement and that defendants pay damages for its breach.

Plaintiff relies chiefly upon Webb v. Culver, 265 Or 467, 509 P2d 1173 (1973). There we granted the equitable relief of reformation where the seller had led the buyer mistakenly to believe that the buyer was acquiring more property than was described in the contract. We said:

"Plaintiffs were misled by Culver’s conduct in constructing the fence, and in developing other parts of the property in such a way as to make it appear that the fence marked the true line. This conduct can be looked upon as an implied representation by Cul-ver that he was selling all of the land encompassed by the fence. It would be inequitable to permit him now to assert that the boundary described in the contract was controlling.” 265 Or at 470.

*289 In Webb the only misrepresentation by conduct was as to a pure question of fact; i.e., the amount of property that was included in the sale. Assuming, for the sake of argument, that defendants in this case were not laboring under the same mistake as was the plaintiff, and that defendants’ conduct amounted to a misrepresentation, we note.that the representation goes to the use to which the property may legally be put. It is not clear at all whether such a misrepresentation is one of law, of fact, or one of mixed law and fact. Compare, however, Gamble et ux v. Beahm, 198 Or 537, 257 P2d 882 (1953). We do not believe that the result of this case should turn on selection of one of those categories to characterize defendants’ conduct. As will be discussed later herein we choose to dispose of this case upon our selection of policy to be applied in a case where one seeks to have a court of equity reform his lawful contract to one which is unlawful.

It is the settled rule that a party requesting reformation must prove the existence of an antecedent agreement to which the erroneous subsequent instrument should be made to conform. Frick v. Hoag, 277 Or 135, 559 P2d 879 (1977); Mayer/Kleinknecht v. Bassett, 263 Or 334, 501 P2d 782 (1972); Manning Lumber Co. v. Voget, 188 Or 486, 216 P2d 674 (1950). Once such agreement is proved, equity may give it effect by making the instrument express correctly the real agreement between the parties.

The trial court disposed of the case by finding the evidence to be insufficient to establish the antecedent agreement for which plaintiff contended. Although the letter opinion is not found in the trial court file, the court apparently issued a letter opinion which we quote from plaintiff’s Abstract of Record:

"The Court has reviewed the memoranda which were submitted by counsel and considered the views expressed during the recent oral argument. With respect to the plaintiff’s first cause of suit, the Court does not regard reformation as a proper remedy in this case. The Court is not persuaded that the parties *290 reached a definite agreement that the property in question would contain two structures, each suitable as a residential rental unit. The absence of an antecedent agreement on thispoint [sic] precludes the Court from reforming the contract under any of the alternative legal theories advanced by the plaintiff.
"The Court is aware of the misleading physical condition of the property at the time of sale. It is apparent that one or both of the parties mistakenly assumed that the properly [sic] [property] legally could contain two rental units. Rescission rather them reformation is the proper remedy for a contract induced by an erroneous factual assumption which is not integrated into the agreement of the parties. The contract as written accurately reflects the agreement of the parties and must be enforced.”

We reach the same result in the denial of reformation but by a different route.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wetterman v. Monaco Coach Corp.
141 F. Supp. 2d 1263 (D. Oregon, 2001)
Mariah Investments, Ltd. v. McCabe
986 P.2d 1209 (Court of Appeals of Oregon, 1999)
Shizuo Ono v. Coos County
831 P.2d 66 (Court of Appeals of Oregon, 1992)
City of Lakewood v. Mavromatis
817 P.2d 90 (Supreme Court of Colorado, 1991)
South Creek Associates v. Bixby & Associates, Inc.
781 P.2d 1027 (Supreme Court of Colorado, 1989)
Soursby v. Hawkins
763 P.2d 725 (Oregon Supreme Court, 1988)
Soursby v. Hawkins
737 P.2d 145 (Court of Appeals of Oregon, 1987)
Ogan v. Ellison
682 P.2d 760 (Oregon Supreme Court, 1984)
Mountain Fir Lumber Co. v. Employee Benefits Insurance
679 P.2d 296 (Oregon Supreme Court, 1984)
Ogan v. Ellison
668 P.2d 470 (Court of Appeals of Oregon, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
593 P.2d 1163, 286 Or. 285, 1979 Ore. LEXIS 761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-v-chernecki-or-1979.