Mitchell v. Beck

50 N.W. 305, 88 Mich. 342, 1891 Mich. LEXIS 543
CourtMichigan Supreme Court
DecidedNovember 13, 1891
StatusPublished
Cited by4 cases

This text of 50 N.W. 305 (Mitchell v. Beck) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell v. Beck, 50 N.W. 305, 88 Mich. 342, 1891 Mich. LEXIS 543 (Mich. 1891).

Opinion

Champlin, O. J.

' In the spring and early summer of 1889, the plaintiff, who was the owner of a steam-dredge, did some work therewith at the mill-docks of Smith & Daly, at Cheboygan, Mich., and the latter owed him therefor a balance of -about $760. As they did not pay this, he ceased to work for them. On August 12 of the same year he resumed the work on a promise that this balance would be paid at once. They paid him $300, and promised the balance the following day. On the 13th, and again on the 14th, of August he demanded his pay, and, not receiving it, on the latter day gave his engineer orders to remove the dredge-to the mill of D. C. Pel ton, refusing to work longer-under the contract with Smith & Daly.

On the evening of the same day he met the defend[344]*344ant, Beck, at the Grand Central Hotel office, and the contract was made which is the subject of this controversy. It is claimed by the plaintiff that defendant was having a large amount of lumber sawed at this mill under contract with Smith & Daly. Mr. Smith, of the firm of Smith & Daly, had seen both parties during the day, and brought about this interview.

Plaintiff’s version of his talk at the hotel with Beck is substantially as follows: Beck said he wanted plaintiff to go on and complete the dredging; that it was of as much importance to him and benefit to him as to Smith & Daly, because he could not get vessels to go there and ship his lumber on account of the shallow water; that if plaintiff would go on and complete the work he would give him his note for the amount as soon as the work was finished; and that any of the banks at Cheboygan would cash the note. This, plaintiff says, he regarded as equivalent to a cash contract, and on the strength of it remained and completed the work. Plaintiff says that Beck agreed to pay for all the work from and including the 12th of August, and on completing the work plaintiff made out the bill, and presented it to A. It. Beck.

Defendant does not admit the conversation as stated by plaintiff, but admits that he had a conversation with him, and says that -his agreement was to indorse or accept Smith & Daly’s paper for $500. He says that he expected to hold back money due Smith & Daly for sawing to cover his liability to plaintiff. When the bill was presented to him he mistook the amount for $1,900, and said he did not think that he had held back that amount, and when it was explained that the bill was only for $1,415 he was silent.

There is no dispute as to the amount of the bill, or that the work was done and well done. The mill burned the day the dredging was finished.

[345]*345It appears that Beck was an officer and stockholder in the A. R. Beck Lumber Company, a corporation, and the defense to the action rests upon two grounds:

1. That the agreement relied upon by the plaintiff is void under the statute of frauds.
2. That defendant had no personal interest in the dredging, except as a member of the corporation, and that whatever he said or did was as an agent of the corporation.

Proof was introduced in the case tending to support both of these theories. The plaintiff, under the charge of the court, recovered a judgment.

Error is assigned—

1. Upon certain language used by counsel in his closing address to the jury.
2. In the court's not directing a verdict in favor of the defendant after the testimony was closed.
3. Upon the following instructions given by the court to the jury, viz.:
“ « — If you find that the defendant, Beck, did agree to pay the plaintiff for the dredging done at Smith & Daly's mill from and including August 12, 1889, and that his leading object was not to secure credit for Smith & Daly, but to subserve his own business purposes, and to reap the benefit for himself, real or supposed, and such benefit to himself, or the benefit which he reaped, was the real consideration of his promise, then his undertaking was a valid one, and does not come within the operation of the statute of frauds.
“ l — If you find that Mr. Beck himself was to receive a direct benefit in exchange for which his promise or undertaking ivas given, it is wholly immaterial whether Smith & Daly were originally also liable or not.''
c — But if you find that the contract was made by this individual, without disclosing his agency, for the benefit of the A. R. Beck Lumber Company, without any reference to the Smith & Daly Lumber Company's interests, then your verdict will be for the plaintiff to the full amount of the labor rendered after the 14th, so that your verdict, if it is for the plaintiff, will be for $1,198.50.''
d — If the defendant is liable at all, he is liable to [346]*346the full amount of $1,198.50, and interest from tbe time the labor was performed up to the present time.”

We do not think that the language of counsel in closing the case to the jury was such a departure from appropriate argument as to call for a reversal of the judgment.1

Neither do we see any error in the instructions of the-court, under the testimony which was introduced before the jury. The case was fairly presented to the jury upon the theory of both parties, — one that it was an Original undertaking on the part of Beck, and the other that it was merely a collateral agreement to the undertaking of Smith & Daly. The plaintiff relied upon his own testimony in the case.that the undertaking was to pay. in full for the work which he did after a certain date. The defendant claimed that he undertook to-[347]*347become security for the amount of $500 for Smith & Daly. The court was therefore correct in charging the jury that, if the plaintiff was entitled to recover at all, he was entitled to recover for the full amount claimed, and unless he was entitled to the full amount claimed he was not entitled to anything.

His instruction was also correct upon the question of' the individual liability of Beck in entering into the contract without disclosing his' agency, although he might have been in fact merely an agent acting for the A. R. Beck Lumber Company.

We discover no error in the record, and the judgment is affirmed.

Morse, McGrath, and Long, JJ., concurred. Grant, J., did not sit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moon v. Greenlee
195 P. 1100 (Supreme Court of Colorado, 1921)
Johnson v. Cunningham
99 Kan. 466 (Supreme Court of Kansas, 1917)
Monroe Lumber Co. v. Bezeau
158 N.W. 880 (Michigan Supreme Court, 1916)
McCormick v. Detroit, Grand Haven & Milwaukee Railway Co.
104 N.W. 390 (Michigan Supreme Court, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
50 N.W. 305, 88 Mich. 342, 1891 Mich. LEXIS 543, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-v-beck-mich-1891.