Mitchell & Associates, Inc. v. Global Systems Integration, Inc.

CourtCourt of Appeals of Georgia
DecidedJune 17, 2020
DocketA20A0599
StatusPublished

This text of Mitchell & Associates, Inc. v. Global Systems Integration, Inc. (Mitchell & Associates, Inc. v. Global Systems Integration, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchell & Associates, Inc. v. Global Systems Integration, Inc., (Ga. Ct. App. 2020).

Opinion

FIRST DIVISION BARNES, P. J., GOBEIL and PIPKIN, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

DEADLINES ARE NO LONGER TOLLED IN THIS COURT. ALL FILINGS MUST BE SUBMITTED WITHIN THE TIMES SET BY OUR COURT RULES.

June 12, 2020

In the Court of Appeals of Georgia A20A0599. MITCHELL & ASSOCIATES, INC. v. GLOBAL SYSTEMS INTEGRATION, INC.

BARNES, Judge.

This case arises out of a subcontractor agreement (“the Agreement”) between

Mitchell & Associates, Inc. and Global Systems Integration, Inc. (“GSI”). Mitchell

filed suit seeking payment on certain invoices due under the Agreement. GSI

counterclaimed, seeking a refund of amounts previously paid to Mitchell for

unsatisfactory work, as well as the profits GSI lost as the result of Mitchell’s failure

to perform under the Agreement as promised. Mitchell now appeals from an order of

the Cherokee County Superior Court granting it summary judgment on its breach of

contract claim and granting GSI summary judgment on its counterclaims. Mitchell

asserts that in granting judgment in favor of GSI, the trial court erred in finding that the terms of the Agreement did not preclude GSI’s claim for lost profits; in failing to

apply the Agreement’s ten-day notice provision to GSI’s claim for a refund; and in

refusing to give a March 2017 amendment to the Agreement retroactive effect. For

reasons explained more fully below, we find no error in the trial court’s conclusion

that the Agreement did not bar GSI’s recovery of the lost profits sought in this case.

Accordingly, we affirm the trial court’s grant of summary judgment to GSI on that

claim. We further find, however, that the trial court erred in awarding GSI a refund

of monies previously paid to Mitchell, because such damages were barred by GSI’s

failure to comply with the Agreement’s ten-day notice provision. We therefore

reverse that portion of the order awarding GSI a refund.

Summary judgment is proper when there is no genuine issue of material fact

and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). “In

reviewing a grant or denial of summary judgment, we owe no deference to the trial

court’s ruling and we review de novo both the evidence and the trial court’s legal

conclusions.” Muscogee County Board of Tax Assessors v. Pace Indus., 307 Ga. App.

532, 532-533 (705 SE2d 678 (2011). “Similarly, the construction of a contract,

including the existence or nonexistence of any ambiguities found therein, represents

a question of law for the court, subject to a de novo standard of review on

2 appeal.”(Citations omitted.) Kerwood v. Dinero Solutions, 292 Ga. App. 742, 742

(666 SE2d 40) (2008).

The relevant facts are undisputed and show that GSI contracted with its client,

AxleTech, Inc. (“the Client”), to provide certain technical and/or computer services.

In July 2016, the parties entered the Agreement pursuant to which GSI subcontracted

with Mitchell to provide some of those services. Paragraph 6 of the Agreement

provided, in relevant part:

6. Professional Standards and Warranties. [Mitchell] warrants and represents that: (i) the Services will be performed with care, skill and diligence in accordance with the applicable professional or industry standards, will be technically accurate and complete, and will be in strict accordance with the requirements of any applicable Work Order pursuant to which [Mitchell] is providing the Services; . . . and (iv) as GSI’s subcontractor, [Mitchell] will comply with all the obligations imposed upon GSI as if it stood in the shoes of GSI while performing the Services and shall not do anything that gives rise to a claim by GSI’s Client that GSI is in breach of its obligations to the Client. In the event of any breach of the foregoing representations and warranties, GSI shall have, in addition to any remedies it may have at law, (i) the right to withhold fees payable to the extent GSI’s Client withholds payment to GSI for any issue with [Mitchell’s] work; and (ii) require [Mitchell] to[,] at GSI’s discretion, either re-perform any Services which GSI believes, in its sole discretion, to be non-satisfactory, at [Mitchell’s] expense or

3 refund/credit GSI for the costs of such Services to the extent actually paid by GSI. GSI will inform [Mitchell] regarding these issues within ten (10) working days.

The Agreement further provided, in Paragraph 19, that “[n]either party shall be liable

to the other party under or in connection with this Agreement or any breach of the

same in any manner for any indirect, consequential, special or punitive damages.”

Between December 19 and 30, 2016, the Client informed GSI of a number of

issues it had with Mitchell’s services, and it subsequently refused to pay GSI for fees

and expenses billed by Mitchell in December 2016 and early January 2017. GSI

thereafter agreed to provide the Client with a revised invoice for the relevant time

period, deleting Mitchell’s time and expenses, and it provided the Client with that

invoice on January 12, 2017. On March 2, 2017, Mitchell contacted GSI seeking

payment of overdue invoices that Mitchell submitted under the Agreement. Mitchell

then learned for the first time that the Client was unhappy with its work and was

therefore disputing the fees and expenses GSI billed for Mitchell’s December and

January services. GSI explained that it was exercising its contractual right to withhold

payment and credit the amounts currently owed against amounts previously paid to

Mitchell for the unsatisfactory work. Mitchell responded that it would suspend work

4 under the Agreement until the payment issues were resolved, and requested an

amendment to Paragraph 6 that deleted GSI’s option of withholding payment or

seeking a refund from Mitchell if the Client refused to pay for Mitchell’s services.

The following day, GSI emailed Mitchell that in an act of “good faith,” GSI would

pay the outstanding invoices. GSI also agreed to Mitchell’s request to amend

Paragraph 6 of the Agreement. Thus, effective March 3, 2017, Paragraph 6 was

amended to provide that in the event Mitchell breached the provisions of that

Paragraph, GSI’s only remedy was to require Mitchell to re-perform its services, at

Mitchell’s expense. The ten-day notice provision found in Paragraph 19, however,

remained part of the Agreement.

Mitchell continued to perform work under the Agreement until August 2017.

After the Agreement ended, GSI refused to pay Mitchell’s final invoices (totaling

$37,500), claiming it was entitled to credit that amount against the amount previously

paid Mitchell for unsatisfactory work. In doing so, GSI asserted that the parties’

March 2017 amendment of Paragraph 6 did not apply retroactively – i.e., it did not

apply to any unsatisfactory work performed prior to March 2017.

After GSI refused to pay its final invoices, Mitchell filed the current lawsuit,

and GSI responded by filing its counterclaims. Following the close of discovery, the

5 parties filed cross-motions for summary judgment. The trial court held a hearing on

those motions and subsequently entered an order granting Mitchell summary

judgment on its claim for payment of the unpaid invoices and granting GSI summary

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Comtrol, Inc. v. H-K Corp.
214 S.E.2d 588 (Court of Appeals of Georgia, 1975)
Burritt v. Media Marketing Services, Inc.
420 S.E.2d 792 (Court of Appeals of Georgia, 1992)
Forsyth County v. WATERSCAPE SERVICES, LLC
694 S.E.2d 102 (Court of Appeals of Georgia, 2010)
Imaging Systems International, Inc. v. Magnetic Resonance Plus, Inc.
490 S.E.2d 124 (Court of Appeals of Georgia, 1997)
Kerwood v. Dinero Solutions, LLC
666 S.E.2d 40 (Court of Appeals of Georgia, 2008)
Aon Risk Services, Inc. v. Commercial & Military Systems Co.
607 S.E.2d 157 (Court of Appeals of Georgia, 2004)
Muscogee County Board of Tax Assessors v. Pace Industries, Inc.
705 S.E.2d 678 (Court of Appeals of Georgia, 2011)
Willesen v. Ernest Communications, Inc.
746 S.E.2d 755 (Court of Appeals of Georgia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Mitchell & Associates, Inc. v. Global Systems Integration, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchell-associates-inc-v-global-systems-integration-inc-gactapp-2020.