Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc.

CourtIndiana Court of Appeals
DecidedFebruary 1, 2012
Docket36A04-1103-CT-79
StatusUnpublished

This text of Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc. (Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc., (Ind. Ct. App. 2012).

Opinion

Pursuant to Ind. Appellate Rule 65(D),

FILED this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of Feb 01 2012, 8:46 am establishing the defense of res judicata, collateral estoppel, or the law of the CLERK case. of the supreme court, court of appeals and tax court

ATTORNEYS FOR APPELLANT: ATTORNEYS FOR APPELLEE:

GLENN D. BOWMAN JULIA BLACKWELL GELINAS CYNTHIA M. LOCKE MAGGIE L. SMITH CHRISTINE M. RIESNER JAMES DIMOS Stewart & Irwin, P.C. BRIAN M. FALCON Indianapolis, Indiana Frost Brown Todd, LLC Indianapolis, Indiana

IN THE COURT OF APPEALS OF INDIANA

MITCHELL & STARK CONSTRUCTION ) COMPANY, INC., ) ) Appellant, ) ) vs. ) No. 36A04-1103-CT-79 ) STRAND ASSOCIATES, INC., as successor ) In interest to SIECO, INC., ) ) Appellee. )

APPEAL FROM THE JACKSON SUPERIOR COURT The Honorable Bruce Markel, III, Judge Cause No. 36D01-0608-CT-12

February 1, 2012

MEMORANDUM DECISION - NOT FOR PUBLICATION DARDEN, Judge

STATEMENT OF THE CASE

Mitchell & Stark Construction Company, Inc., (“the Contractor”) appeals the trial

court’s grant of summary judgment in favor of Strand Associates, Inc., (“the Engineers”)

in Mitchell & Stark’s third party indemnification action against Strand.

We affirm.

ISSUE

Whether the trial court erred in granting summary judgment in favor of Strand.

FACTS

The city of Seymour, Indiana (“the City”) owns and maintains the Von Fange

Ditch (“the Ditch”), a legal drain and sewer line that flows through the west side of the

City. Many years ago, the Ditch was declared to be in a flood plain, which restricted its

use and required surrounding property owners to maintain flood insurance. In the mid-

1990’s, the Indiana Department of Natural Resources studied the Ditch and determined

that concerns about the flood plain might have been overestimated.

In 1994, the City contracted with the Engineers1 to review the Department’s study

and advise the City about long and short term solutions for improvements to the Ditch.

In 1997, the City hired the Engineers to design those improvements and help the City

implement them. In the initial design phase, the City and the Engineers anticipated they

1 The contract was originally executed between the City and SIECO, Inc. The Engineers acquired SIECO in 2002. 2 would need to excavate the Ditch and reconstruct it. However, when the Engineers’

modeling for the flow of water was completed, it was determined that the construction

and improvements to the Ditch did not need to be as extensive as they previously

believed. Further, the time frame for getting permits to do the excavation and

reconstruction exceeded the time allotted for the project. The City therefore revised the

scope of the project to merely include pulling back vegetation in the bottom of the Ditch

to make sure the water flowed and replacing pipes.

After the City and the Engineers determined the scope of the work and

specifications for the Ditch project, they included this information in a “Proposal,

Specifications, and Contract Documents” provided as part of the public bidding process.

During this process, the Contractor submitted the lowest bid, and the City accepted it.

(Supp. App. 356).

Before the Contractor began working on the Ditch project, the City and the

Engineers entered into an agreement, which provided that the Engineers were to observe

the Contractor’s work and report its observations to the City. However, the contract

expressly prohibited the Engineers from supervising the Contractor and released the

Engineers from any responsibility for the Contractor’s acts or omissions while working

on the Ditch project. Specifically, the agreement provided in relevant part as follows:

Engineer . . . shall not . . . supervise, direct or have control over Contractors’ work nor shall Engineer have authority over or responsibility for the means, methods, techniques, sequences or procedures or construction selected by Contractors, for safety precautions and programs incident to the work of Contractors or for any failure of Contractors to

3 comply with laws, rules, regulations, ordinances, codes, or orders applicable to Contractors furnishing or performing their work. Accordingly, Engineer can neither guarantee the performance of the construction contracts by Contractor nor assume responsibility for Contractors failure to furnish and perform their work in accordance with the Contract Documents.

(App. 68). There was no contractual relationship between the Engineers and the

Contractor.

The City and the Contractor also entered into an agreement, which provided in

relevant part that the Contractor was to promptly and carefully remove all excess soil

from the Ditch. Industry practice contemplates that a contractor will determine how he is

going to both remove and dispose of the soil. The contractor typically factors the costs

for these options into its bid. If there is a possibility that the soil is contaminated, it must

be disposed of in a regulated landfill, which is an expensive undertaking for a contractor.

If the soil is not contaminated, adjacent property owners might request the soil for their

own use, which is a less expensive option for a contractor.

Here, the Contractor included the cost of soil removal in its bid and explained that,

consistent with the industry practice, it intended to determine how it would remove and

dispose of the Ditch’s soil. The original plan for disposing of the soil was to find a low

ground that needed fill and dump it. However, Thomas Greemann, an owner of five

acres of property adjacent to the Ditch, told the Contractor that he wanted dirt from the

Ditch added to his property to get as much of his property as possible out of the

floodway. The Contractor and Greemann subsequently entered into a private agreement

4 pursuant to which the Contractor would put only “clean,” or uncontaminated, soil on

Greemann’s property. (Supp. App. 223). Although the City, the Engineers, and the

Contractor never tested the soil because they had no reason to believe it might be

contaminated, the Contractor specifically represented to Greemann that it would put only

clean or uncontaminated soil upon his property.

Several years after the Ditch project was completed, Greemann entered into an

agreement for the sale of his property adjacent to the Ditch. In conjunction with the sale,

an Environmental Site Assessment was performed and revealed that the soil from the

Ditch that the contractor had deposited on Greemann’s property was contaminated with

lead, arsenic, petroleum, and other contaminants. The sale of the property was cancelled,

and Greemann was required to remediate the contamination.

In June 2007, Greemann filed a complaint against the City, the Jackson-Jennings

Farm Bureau Cooperative Association, Inc., which operated a bulk fertilizer facility and

stored treated wood on the property immediately to the east of Greemann’s’ property, and

the Contractor alleging negligence, nuisance, trespass, and strict liability based upon the

failure of the City and the Contractor to “comply with applicable federal, state, and local

laws and regulations.” (App. 24-32). Greemann also sought to recover the remediation

costs pursuant to the Indiana Environmental Act.

Almost two years later, in June 2009, the Contractor filed a third-party complaint

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wank v. Saint Francis College
740 N.E.2d 908 (Indiana Court of Appeals, 2000)
Mahan v. American Standard Insurance Co.
862 N.E.2d 669 (Indiana Court of Appeals, 2007)
Lytle v. Ford Motor Co.
696 N.E.2d 465 (Indiana Court of Appeals, 1998)
Markley Enterprises, Inc. v. Grover
716 N.E.2d 559 (Indiana Court of Appeals, 1999)
Sears, Roebuck and Co., Inc. v. Boyd
562 N.E.2d 458 (Indiana Court of Appeals, 1990)
Mullen v. Cogdell
643 N.E.2d 390 (Indiana Court of Appeals, 1994)
Bailey v. Shelter Mutual Insurance
615 N.E.2d 508 (Indiana Court of Appeals, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mitchall-stark-construction-company-inc-v-strand-associates-inc-as-indctapp-2012.