Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc.
Opinion
Pursuant to Ind. Appellate Rule 65(D),
FILED
this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of Feb 01 2012, 8:46 am establishing the defense of res judicata, collateral estoppel, or the law of the CLERK
case. of the supreme court, court of appeals and
tax court
ATTORNEYS FOR APPELLANT: ATTORNEYS FOR APPELLEE:
GLENN D. BOWMAN JULIA BLACKWELL GELINAS CYNTHIA M. LOCKE MAGGIE L. SMITH CHRISTINE M. RIESNER JAMES DIMOS Stewart & Irwin, P.C. BRIAN M. FALCON Indianapolis, Indiana Frost Brown Todd, LLC Indianapolis, Indiana
IN THE
COURT OF APPEALS OF INDIANA
MITCHELL & STARK CONSTRUCTION ) COMPANY, INC., )
)
Appellant, )
)
vs. ) No. 36A04-1103-CT-79 )
STRAND ASSOCIATES, INC., as successor ) In interest to SIECO, INC., )
)
Appellee. )
APPEAL FROM THE JACKSON SUPERIOR COURT The Honorable Bruce Markel, III, Judge Cause No. 36D01-0608-CT-12
February 1, 2012
MEMORANDUM DECISION - NOT FOR PUBLICATION
DARDEN, Judge
STATEMENT OF THE CASE
Mitchell & Stark Construction Company, Inc., (“the Contractor”) appeals the trial court’s grant of summary judgment in favor of Strand Associates, Inc., (“the Engineers”) in Mitchell & Stark’s third party indemnification action against Strand.
We affirm.
ISSUE
Whether the trial court erred in granting summary judgment in favor of Strand.
FACTS
The city of Seymour, Indiana (“the City”) owns and maintains the Von Fange Ditch (“the Ditch”), a legal drain and sewer line that flows through the west side of the City. Many years ago, the Ditch was declared to be in a flood plain, which restricted its use and required surrounding property owners to maintain flood insurance. In the mid- 1990’s, the Indiana Department of Natural Resources studied the Ditch and determined that concerns about the flood plain might have been overestimated.
In 1994, the City contracted with the Engineers1 to review the Department’s study and advise the City about long and short term solutions for improvements to the Ditch. In 1997, the City hired the Engineers to design those improvements and help the City implement them. In the initial design phase, the City and the Engineers anticipated they
1
The contract was originally executed between the City and SIECO, Inc. The Engineers acquired SIECO in 2002.
would need to excavate the Ditch and reconstruct it. However, when the Engineers’ modeling for the flow of water was completed, it was determined that the construction and improvements to the Ditch did not need to be as extensive as they previously believed. Further, the time frame for getting permits to do the excavation and reconstruction exceeded the time allotted for the project. The City therefore revised the scope of the project to merely include pulling back vegetation in the bottom of the Ditch to make sure the water flowed and replacing pipes.
After the City and the Engineers determined the scope of the work and specifications for the Ditch project, they included this information in a “Proposal, Specifications, and Contract Documents” provided as part of the public bidding process. During this process, the Contractor submitted the lowest bid, and the City accepted it. (Supp. App. 356).
Before the Contractor began working on the Ditch project, the City and the Engineers entered into an agreement, which provided that the Engineers were to observe the Contractor’s work and report its observations to the City. However, the contract expressly prohibited the Engineers from supervising the Contractor and released the Engineers from any responsibility for the Contractor’s acts or omissions while working on the Ditch project. Specifically, the agreement provided in relevant part as follows:
Engineer . . . shall not . . . supervise, direct or have control over Contractors’ work nor shall Engineer have authority over or responsibility for the means, methods, techniques, sequences or procedures or construction selected by Contractors, for safety precautions and programs incident to the work of Contractors or for any failure of Contractors to
comply with laws, rules, regulations, ordinances, codes, or orders applicable to Contractors furnishing or performing their work.
Accordingly, Engineer can neither guarantee the performance of the construction contracts by Contractor nor assume responsibility for Contractors failure to furnish and perform their work in accordance with the Contract Documents.
(App. 68). There was no contractual relationship between the Engineers and the Contractor.
The City and the Contractor also entered into an agreement, which provided in relevant part that the Contractor was to promptly and carefully remove all excess soil from the Ditch. Industry practice contemplates that a contractor will determine how he is going to both remove and dispose of the soil. The contractor typically factors the costs for these options into its bid. If there is a possibility that the soil is contaminated, it must be disposed of in a regulated landfill, which is an expensive undertaking for a contractor. If the soil is not contaminated, adjacent property owners might request the soil for their own use, which is a less expensive option for a contractor.
Here, the Contractor included the cost of soil removal in its bid and explained that, consistent with the industry practice, it intended to determine how it would remove and dispose of the Ditch’s soil. The original plan for disposing of the soil was to find a low ground that needed fill and dump it. However, Thomas Greemann, an owner of five acres of property adjacent to the Ditch, told the Contractor that he wanted dirt from the Ditch added to his property to get as much of his property as possible out of the floodway. The Contractor and Greemann subsequently entered into a private agreement
pursuant to which the Contractor would put only “clean,” or uncontaminated, soil on Greemann’s property. (Supp. App. 223). Although the City, the Engineers, and the Contractor never tested the soil because they had no reason to believe it might be contaminated, the Contractor specifically represented to Greemann that it would put only clean or uncontaminated soil upon his property.
Several years after the Ditch project was completed, Greemann entered into an agreement for the sale of his property adjacent to the Ditch. In conjunction with the sale, an Environmental Site Assessment was performed and revealed that the soil from the Ditch that the contractor had deposited on Greemann’s property was contaminated with lead, arsenic, petroleum, and other contaminants. The sale of the property was cancelled, and Greemann was required to remediate the contamination.
In June 2007, Greemann filed a complaint against the City, the Jackson-Jennings Farm Bureau Cooperative Association, Inc., which operated a bulk fertilizer facility and stored treated wood on the property immediately to the east of Greemann’s’ property, and the Contractor alleging negligence, nuisance, trespass, and strict liability based upon the failure of the City and the Contractor to “comply with applicable federal, state, and local laws and regulations.” (App. 24-32). Greemann also sought to recover the remediation costs pursuant to the Indiana Environmental Act.
Almost two years later, in June 2009, the Contractor filed a third-party complaint against the Engineers wherein it alleged that the Engineers had a common law duty to indemnify it for all damages of judgments the Contractor might be ordered to pay
Greemann. The Engineers filed a motion for summary judgment, which the trial court granted. The Contractor appeals.
DECISION
The Contractor argues that the trial court erred in granting the Engineers’
summary judgment motion. Specifically, the Contractor argues that the Engineers have a common law duty to indemnify it for all damages or judgments it might be ordered to pay Greemann.
Free access — add to your briefcase to read the full text and ask questions with AI
Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc. (Mitchall & Stark Construction Company, Inc. v. Strand Associates, Inc., as successor In interest to Sieco, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.