MISSOURI ROOFING COMPANY, INC. v. United States
This text of 357 F. Supp. 918 (MISSOURI ROOFING COMPANY, INC. v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
MISSOURI ROOFING COMPANY, INC., a corporation, Plaintiff,
v.
UNITED STATES of America (GSA), Defendant.
United States District Court, E. D. Missouri, E. D.
*919 Kenney, Leritz & Reinert, St. Louis, Mo., for plaintiff.
Daniel Bartlett, Jr., U. S. Atty., J. Patrick Glynn, Asst. U. S. Atty., St. Louis, Mo., for defendant.
MEMORANDUM OPINION
HARPER, Senior District Judge.
This matter is before the Court on the motion of defendant, United States of America, for summary judgment supported by Exhibits 1 through 26, filed with defendant's answer, which consisted of the General Services Administration Board of Contract Appeal's record in the instant case, and on the cross-motion of plaintiff, Missouri Roofing Company, Inc., for summary judgment supported by affidavit. Both motions, in effect, rely on the record of the General Services Administration Board of Contract Appeals, and there is no dispute as to the facts to be considered by this Court. This action is governed by the Wunderlich Act, 41 U.S.C. §§ 321 and 322. This Court has jurisdiction under 28 U.S.C. § 1346(a)(2).
Defendant, acting through its administrative agency, General Services Administration, Public Building Service, Region 6, awarded a lump sum contract (No. GS-06B-8311 [Ex. 1]) to plaintiff for $131,712.00 for the replacement of the built-up roofing and insulation at the Military Personnel Records Center located at 9700 Page Boulevard, St. Louis, Missouri. The contract provides for the assessment of liquidated damages of $40.00 per calendar day for each calendar day of delay beyond one hundred days from the date of receipt of the notice to proceed (Ex. 1 § 2.2). Section 5(d) of the General Provisions of the contract provides:
"The Contractor's right to proceed shall not be so terminated nor the Contractor charged with resulting damage if:
"(1) The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to * * * acts of the Government in either its sovereign or contractual capacity, * * *, [or] unusual weather conditions, * * *.
"(2) The Contractor, within ten days from the beginning of any such delay * * *, notifies the Contracting Officer in writing of the causes of delay.
*920 "The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension, and his findings of fact shall be final and conclusive on the parties, subject only to appeal as provided in Clause 6 of these General Provisions."
Section 5-3 of the contract provides in part that: "No part of the roofing materials shall be applied or laid during damp or rainy weather or while moisture of any kind is present in visible amount on the surface that is to be covered."
Plaintiff requested extensions at various times during the project, some of which were granted. Plaintiff alleges in its complaint that defendant acted in a capricious and arbitrary manner in failing to grant certain extensions plaintiff requested and that these decisions of defendant were so grossly erroneous as to imply bad faith. Plaintiff alleges that defendant has paid $129,212.00 on the contract, leaving a balance due of $2,500.00, and that defendant has refused to pay the balance, contending plaintiff is liable for liquidated damages. Plaintiff prays for judgment against defendant for the sum of $2,500.00, with interest at the rate of six percent from June 26, 1964, and for costs and attorneys fees.
Plaintiff has exhausted its administrative remedies in that it appealed to the General Services Administration Board of Contract Appeals and upon an adverse decision moved for reconsideration, whereupon the Board of Contract Appeals affirmed its prior decision.
Plaintiff, in its brief, contends that it was not granted the complete extension to which it was entitled because of the delays caused by the weather during the month of December, contends that defendant used an incorrect method for calculating the extensions of time to which plaintiff was entitled because of delays caused by the weather, and contends that defendant was obliged to grant it an extension for the delay resulting from defendant's late approval of the materials plaintiff proposed to use on the project.
Those portions of the opinion of the General Services Administration Board of Contract Appeals which are applicable to plaintiff's contentions state:
"* * * Although the Appellant received the notice to proceed on November 5, 1963, the record shows that the information required by Paragraphs 5-4(b) and 6-5 [a materials list and certificates] was not mailed to the Government until November 26, 1963. The record does not show the date on which this information was actually received by the Government but it does show that the Government gave its approval on December 3, 1963. In the opinion of the Board, the Government's approval was given within a reasonable time after it received the Appellant's submission. Accordingly, it must be held that any delay in the start of the work due to the late approval of the Appellant's materials list and certificates was due to the fault and negligence of the Appellant and was not caused by the Government.
* * * * * *
"The Contracting Officer, acting in response to the several requests which it had received from the Appellant, granted extensions of time for delays due to weather conditions during the months of December 1963, January, February, March, April, May, and June 1964. Inasmuch as there is no evidence that the weather conditions during these months were `unusually severe' within the meaning of Clause 5(d) of the General Provisions, it is quite clear that the several extensions of time were granted by the Contracting Officer under the provisions of Paragraph 5-3 of the specifications. The record shows that the Appellant accepted without objection or protest the various extensions of time which were granted for the months of December, January, February, March, and April. Furthermore, an examination *921 of the record shows that the Contracting Officer granted an extension of one full day for each day (except Saturdays and Sundays) when the Appellant did not work at the project site during the months of May and June 1964.
* * * * * *
"In appeals such as the present one, the Appellant has the burden of proving that its failure to complete the work within the time stipulated in the contract was due to causes which are excusable under the terms of the contract. In the opinion of the Board, the Contracting Officer granted extensions of time for all delays which the record showed were excusable. Accordingly, on the basis of the record before the Board, it must be held that the Appellant has failed to sustain its burden of proof and, therefore, it cannot be relieved of its obligation to pay the liquidated damages."
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
357 F. Supp. 918, 1973 U.S. Dist. LEXIS 14569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/missouri-roofing-company-inc-v-united-states-moed-1973.