Missouri, Kansas & Texas Railway Co. v. Steele

110 S.W. 171, 50 Tex. Civ. App. 634, 1908 Tex. App. LEXIS 644
CourtCourt of Appeals of Texas
DecidedMay 9, 1908
StatusPublished
Cited by10 cases

This text of 110 S.W. 171 (Missouri, Kansas & Texas Railway Co. v. Steele) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Missouri, Kansas & Texas Railway Co. v. Steele, 110 S.W. 171, 50 Tex. Civ. App. 634, 1908 Tex. App. LEXIS 644 (Tex. Ct. App. 1908).

Opinions

Appellee Steele sued to recover damages for personal injuries alleged to have been received by him through the negligence of appellant. Besides a general denial the appellant pleaded contributory negligence and assumed risk. A jury trial resulted in a verdict and judgment in favor of appellee for the sum of five thousand dollars, and appellant has appealed.

The material facts as shown by the evidence are as follows: On July 21, 1906, appellee was in the employ of appellant and engaged as night fireman at its creosote plant, situated southeast of Greenville, in Hunt County, Texas. It was his duty on each Saturday night, after the plant had shut down, to open the manheads of the boilers used in the operation of the plant, so that they might cool off preparatory to having them cleaned out. The boilers were three in number and lay longitudinally side by side and were encased in brick masonry. The manheads were sheets or pieces of iron about 18 inches long and about 16 inches wide, and there was one of them in each end of said boilers; the ones in front being situated at the bottom of the boilers and those in the rear in the top of the boilers, about 12 or fourteen feet from the ground or floor. There were two crews, a day and night crew, engaged in the operation of the tie or creosote plant. Appellee worked under the day fireman, Bob Johnson, and was subject to his direction and control. In removing the manheads in the rear end of the boilers it *Page 637 was necessary, for the safety of the employe engaged in that work, to use a ladder 12 or 14 feet long, and it was the duty of the day fireman, Johnson, to place such a ladder in position for appellee to stand on while knocking out said manheads. Appellee was instructed by the day fireman, Johnson, to knock out the manhead in the rear end of boiler No. 1, on the night he was injured, and showed him the tools to use in doing so. He also told appellee that, in doing the work, he would have to stand on the ladder then in position. This ladder had been placed by the said day fireman and was only 6 or 8 feet long and was in no way fastened or made secure to prevent it from slipping or falling. In obedience to the instructions then given him, appellee went up on the ladder, and while attempting to remove the manhead, the ladder upon which he was standing slipped or kicked out at the bottom, causing appellee to fall upon some iron pipes and the floor below and seriously and permanently injuring him. This occurred about nine o'clock at night, and the place where he was at work, because of the insufficient light furnished him by appellant, was so dark he could see but dimly the objects around him. At the time of the accident, appellee had been at work for appellant but about three weeks. He was inexperienced, had not been warned of the danger in using the short ladder, and had never before attempted to knock out the manhead he was then attempting to remove. When he ascended the ladder and began his efforts to remove the manhead and had unscrewed the bolts, he discovered that it was "stuck for some reason" and that it took a blow of considerable force to knock it in. In delivering the blow he stood with one foot on the ladder and the other on the brick masonry enclosing the boilers, and it was then the ladder "kicked from under him" and he was thrown upon the pipes and floor and injured. He did not know the length of the ladder required, to safely do this work, nor did he know at the time engaged therein, that the ladder upon which he was standing was not securely fastened. This ladder was not, in fact, fastened at all at the time it fell, and was too short to be used with safety in attempting to knock out the manhead without being fastened. Johnson, the day fireman, testified: "I always took the long ladder to go upon No. 1, when it was defective, because I would have to stand on the ladder while knocking out the manhead. The other was too short. I understood from the superintendent that it was my duty to instruct the night fireman in the work, as to the method of doing the work. I told the plaintiff he would have to stand on the ladder when he went to knock out No. 1. I suppose it was my duty as day fireman, to place the long ladder in position for the night fireman, for the reason that it would be too dark back there for him to put it in position himself for boiler No. 1." He further said: "If I should attempt to use the short ladder to stand on, then it might fall with me. I was afraid of that, that was the reason I did not use it." The blowoff pipe is 3 1/2 or 4 feet from the ground or floor and runs from the middle of No. 1 boiler to the middle of No. 3 boiler. The ladder on the night of the accident was back of boiler No. 1, leaning against the blowoff pipe on the outside of it. The evidence leaves it in doubt whether the position of the ladder was noticed by appellee before or after he started up on it, but he did notice it before it fell. He also discovered after he *Page 638 got up on the ladder that the top of it was not against the wall, but he thought the ladder was fastened.

Opinion. — The first assignment of error complains of the court's action in overruling appellant's challenge of the juror, Jesse, for cause. The bill of exception shows that this juror was one of a panel of twenty-four, from which the jury trying the case was selected, and that he had served as a juror for seven days in the District Courts of Hunt County during the preceding six months, four days in the District Court of the Sixty-second Judicial District at its February term, 1907, and three days in the District Court of the Eighth Judicial District, during its March term, 1907. The juror was challenged on the ground that having served as a juror in the District Courts of Hunt County for six days during the preceding six months he was disqualified to serve in this cause. The trial court held the juror was qualified and overruled appellant's challenge, whereupon appellant challenged the juror peremptorily. The contention of the appellee is, that inasmuch as the juror had served in different District Courts and had not served for six consecutive days in either or both, he was not disqualified. We do not find it necessary to decide whether the court's ruling upon the question was correct or not. The bill of exceptions does not show that appellant suffered any injury by this action of the court, and, if it erred in not sustaining the challenge, the error is harmless. It appears from the record that the appellant exhausted the six peremptory challenges allowed it by law, but it does not appear that either of the jurors who served in the trial of the case was obnoxious to appellant, or that it would have challenged either of them, had it not been forced to exhaust a challenge on the objectionable juror, Jesse. Snow v. Starr, 75 Tex. 411; Houston T. C. Ry. v. Terrell, 69 Tex. 650; Wolf v. Perryman, 82 Tex. 112; Paris Groc. Co. v. Burks, 17 Texas Ct. Rep., 892. The case is unlike San Antonio A. P. Ry. v. Lester, 99 Tex. 215. In that case it was shown that, because of the court's action in disallowing the challenge of the railway company, it was compelled to submit its case to jurors who did not possess the qualifications required by law and who were objectionable to it, and the Supreme Court held, in effect, that injury was apparent and reversed the case. That case does not, as we understand it, go to the extent of holding that the mere denial of the right to challenge a disqualified juror entitles the complaining party to a new trial. For such holding, it seems, would be in conflict with the cases of Snow v. Starr, Houston T. C. Ry. v. Terrell, and Wolf v. Perryman,supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Osterloh v. San Antonio Public Service Co.
77 S.W.2d 290 (Court of Appeals of Texas, 1934)
Home Ins. Co. v. Collins
55 S.W.2d 898 (Court of Appeals of Texas, 1932)
Morten Inv. Co. v. Trevey
8 S.W.2d 527 (Court of Appeals of Texas, 1928)
Moore v. Moore
299 S.W. 653 (Court of Appeals of Texas, 1927)
Russell v. Bailey
290 S.W. 1108 (Court of Appeals of Texas, 1927)
Pearson v. Texas & N, O. Ry. Co.
238 S.W. 1108 (Texas Commission of Appeals, 1922)
Gussett v. Nueces County
235 S.W. 857 (Texas Commission of Appeals, 1921)
Colgrove v. Falfurrias State Bank
192 S.W. 580 (Court of Appeals of Texas, 1917)
Decatur Cotton Seed Oil Co. v. Belew
178 S.W. 607 (Court of Appeals of Texas, 1915)
Farmers' Cotton Oil Co. v. Barnes
134 S.W. 369 (Court of Appeals of Texas, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
110 S.W. 171, 50 Tex. Civ. App. 634, 1908 Tex. App. LEXIS 644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/missouri-kansas-texas-railway-co-v-steele-texapp-1908.