Mishara Construction Co. v. International Brotherhood of Electrical Workers

554 F.2d 488
CourtCourt of Appeals for the First Circuit
DecidedMay 3, 1977
DocketNos. 76-1410, 76-1411 and 76-1418
StatusPublished
Cited by3 cases

This text of 554 F.2d 488 (Mishara Construction Co. v. International Brotherhood of Electrical Workers) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mishara Construction Co. v. International Brotherhood of Electrical Workers, 554 F.2d 488 (1st Cir. 1977).

Opinion

PER CURIAM.

The issue in this case is whether defendants, International Brotherhood of Electrical Workers, AFL-CIO and its Local Union 284 of Pittsfield, Massachusetts, violated the secondary boycott prohibition of the Labor Management Relations Act, 29 U.S.C. § 158(b)(4)(ii)(B), by threatening and coercing Philip Renzi & Sons, Inc. (Renzi) and Bernard Roy in order to get them to cease working as electrical subcontractors for the Mishara Construction Corporation (Mishara) during the construction of Rose Manor, a housing project for the elderly in Pittsfield, Massachusetts.

[489]*489Mishara instituted this action in March, 1971, seeking damages under 29 U.S.C. § 1871 for alleged violations by both defendants of the secondary boycott provision. The case was referred to a master in January, 1974, pursuant to Fed.R.Civ.P. 53. The sole issue before the master was the question of liability. In July, 1975, after twenty-two days of hearings, the master filed his report recommending that judgments enter for both defendants. Mishara objected to the report. The district court ruled that the report lacked sufficiently specific findings and remanded the case to the master in November, 1975, to make subsidiary findings. The master filed his subsidiary findings in March, 1976, still concluding that judgment should enter for the defendants. Mishara filed essentially the same objections again. The district court adopted the master’s findings and subsidiary findings on June 17, 1976, and directed that judgment be entered for defendants.

Renzi was the electrical subcontractor to Mishara, the general contractor, at the Rose Manor construction site in Pittsfield, Massachusetts. The Rose Manor job, to put it mildly, was fraught with labor strife throughout its existence. Construction began late in 1966, and in April, 1967, the Carpenters’ Union had a labor dispute with Mishara, struck the project, and set up picket lines. In June of 1967, Mishara replaced the striking carpenters with nonunion carpenters in an attempt to break the strike, but many of Mishara’s other employees and those of its subcontractors, including Renzi’s employees, were unwilling to cross the picket line.

The Carpenters’ Union and Mishara agreed to submit the dispute to binding arbitration on September 11, 1967. A few days after the removal of the Carpenters’ picket lines, the Laborers’ Union requested a contract. When it and Mishara were unable to reach agreement, the Laborers set up a picket line.

On the few days when there were no picket lines, Renzi’s electricians went to work. On the first morning of the Laborers’ strike, Renzi’s electricians showed up outside the gate. They refused to cross the picket line, and they were told by Renzi’s superintendent, Pigott, to go to another Renzi job site in the area.

On several occasions, electricians crossed the picket lines to perform various jobs for Renzi, but these jobs were mostly related to equipment maintenance or other work not intended to forward the project as a whole, but rather to maintain the status-quo.

Renzi frequently requested that Local 284 supply him with electricians. Local 284 and the International made efforts to find employees for Renzi, but they were not successful. They contend that there was a dearth of electricians for the many construction projects in the area at the time and that this was not the only project for which Renzi was having difficulty finding sufficient labor.

Two considerations stemming directly from the labor strife also hurt Renzi’s attempts to find a sufficient work force: first, that union workers are reluctant to cross picket lines; and second, that the project’s general labor problems posed the threat of shutdown at any time. Electricians who could find steady work elsewhere were more likely to take it rather than work at the Rose Manor job site.

Renzi made other attempts to find employees. Renzi’s foreman, Pigott, went to some of the men at other Renzi jobs and [490]*490asked them to work at Rose Manor, but, to a man, they were unwilling. Pigott was not even able to convince men who had been laid off from another job to come to work at Rose Manor. Another Renzi representative Beaudoin, made attempts to find men in the Providence, Rhode Island area, but he was also unsuccessful.

Unable to man the job with union electricians, Renzi arranged to have a nonunion company from Boston, Rotman Electric, perform the electrical work from early January of 1968 until April 30 of that year. On April 30, Renzi sent a telegram to Mishara which indicated that one Bernard Roy, a nonunion electrical contractor, would take over the work.

Roy and his men began work on May 1, 1968. Donald Soule, who became the Business Manager for Local 284 on July 19, 1968, discovered that some of the workers were being paid less than scale. Renzi had a written contract with Local 99 of the IBEW in Providence, his home base, but did not have a written contract with Local 284 of Pittsfield. Soule charged Renzi with violation of section 10 of the Local 284 agreement, which is the same as that section of the Local 99 agreement.

On August 9, 1968, a joint conference committee consisting of four committee members, two from the union and two from the employers, met to consider the charges of substandard wages. Renzi did not contest the charges. Roy was terminated on August 21 and stopped working on August 22. Mishara terminated Renzi and employed Rotman to complete the work shortly after Roy’s termination.

The master initially found that while there was no written agreement between Renzi and Local 284, the parties “acted under” an agreement which included the clause contained in section 10 of Local 284’s standard contract. That section provides that

“[T]he subletting, assigning or the transfer of any work in connection with electrical work to any person, firm or corporation not complying with the terms of this Agreement by the Employer, will be sufficient cause for cancellation of this Agreement, after the facts have been determined by the International Office of the Union.”

In his later subsidiary findings, the master did not retract his conclusion but somewhat confusingly said that “even if the parties at times acted as though there was an agreement, it would be impossible to reconstruct the terms of such a purported agreement from the actions of the parties.” He went on to find, assuming the parties were bound by such an agreement, that the provision set out above was valid under the proviso created for the construction industry in 29 U.S.C. § 158(e) because it did not require subcontractors to recognize the union but only to maintain union terms or standards. The master observed, moreover, that even if the challenged language could be characterized as an unfair labor practice under 29 U.S.C. § 158

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
554 F.2d 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mishara-construction-co-v-international-brotherhood-of-electrical-workers-ca1-1977.