Miree Painting v. Woodward Const.

627 So. 2d 389, 1992 WL 246093
CourtCourt of Civil Appeals of Alabama
DecidedOctober 2, 1992
Docket2910435
StatusPublished
Cited by2 cases

This text of 627 So. 2d 389 (Miree Painting v. Woodward Const.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miree Painting v. Woodward Const., 627 So. 2d 389, 1992 WL 246093 (Ala. Ct. App. 1992).

Opinion

In March 1981 Woodward Construction Design, Inc. (Woodward), as general contractor, and Miree Painting Company, Inc. (Miree), as subcontractor, entered into a written agreement calling for Miree to provide the painting for a townhouse project owned by Athens Development Corporation (ADC). The total contract price was $39,468, to be paid by Woodward to Miree in partial payments, based on performance and subject to approval by ADC's supervising architect. The contract between the parties contained the following termination provision:

"If the subcontractor persistently or repeatedly fails or neglects to carry out the work in accordance with the contract documents or otherwise to perform in accordance with this agreement and fails within seven days after receipt of written notice to commence and continue correction of such default or neglect with diligence and promptness, the contractor may, after seven days following receipt by the subcontractor of an additional written notice and without prejudice to any other remedy he may have, terminate the subcontract and finish the work by whatever method he may deem expedient. If the unpaid balance of the contract sum exceeds the expense of finishing the work, such excess shall be paid to the subcontractor, but if such expense exceeds such unpaid balance, *Page 391 the subcontractor shall pay the difference to the contractor."

Miree began painting on the job in July 1988 and by November 1988 had drawn partial payments from Woodward totalling $29,468. However, due to the supervising architect's dissatisfaction with the quality of Miree's work, Woodward refused to pay Miree the final $10,000 of the contract price and instead hired another subcontractor to complete the job. Woodward claims that before hiring the second subcontractor, it provided Miree with notice pursuant to the terms of the termination provision in the contract.

Miree sued Woodward, demanding the remaining $10,000 of the contract price. Woodward, alleging that Miree had inadequately performed under the contract, counterclaimed for $14,611, the amount Woodward paid to the second subcontractor to complete the job.

An ore tenus proceeding was held in February 1990, after which the trial court entered an order finding that Miree's work was defective and that Woodward, as required by the termination provision, had given Miree two written notices before terminating the contract and hiring another subcontractor. Accordingly, the court entered a judgment against Miree and for Woodward for $4,611, the difference between the amount claimed by Miree and the amount Woodward had paid to the second subcontractor.

Miree subsequently filed a motion for new trial, alleging that the trial court's findings as to notice were in error. Miree's motion was granted, and by stipulation of the parties, the original trial transcript was resubmitted for decision by the court.

On March 26, 1992, the trial court entered a final order, wherein it again found that Woodward had provided adequate notice and again entered a judgment for Woodward and against Miree in the amount of $4,611. Miree appeals.

The dispositive issue on appeal is whether Miree received proper notice before termination of the contract.

Miree contends that Woodward did not, as required by the termination provision, provide it with two written notices at least seven days apart before waiting an additional seven days to terminate the contract and hire another subcontractor to finish the painting job. It further maintains that Woodward's failure to provide sufficient notice before putting the second subcontractor on the job prevented it from completing its work as called for by the contract. Consequently, Miree argues that the $4,611 judgment for Woodward is erroneous and that Woodward actually owes it $10,000.

In its order entered after the initial trial, the trial court found that Miree had received a first notice from Woodward on November 14, 1988, and a second notice on December 22, 1988. However, the order of the trial court following retrial of the case does not contain specific findings as to the dates Miree received notice. Where the trial court does not make specific findings of fact concerning an issue, the reviewing court will assume that the trial court made those findings necessary to support its judgment, unless such findings would be clearly erroneous and against the weight and preponderance of the evidence. Thomas v. Davis, 410 So.2d 889 (Ala. 1982).

Further, because the trial court was presented with ore tenus evidence in this case, the court's judgment based on that evidence is presumed to be correct and will not be disturbed on appeal unless a consideration of the evidence and all reasonable inferences therefrom reveals that the judgment is plainly and palpably erroneous or manifestly unjust.Arzonico v. Wells, 589 So.2d 152 (Ala. 1991).

Miree asserts on appeal that it received only one written notice prior to Woodward's termination of the contract: a letter from Woodward's president, dated November 14, 1988, citing Miree for poor workmanship and asking that immediate attention be given to the problem. At trial Miree's president testified that, despite the November 14 letter, he did not learn that there was a serious question regarding his company's performance until around December 22, 1988, when Woodward's president informed him by telephone that the supervising architect had refused to approve the final payment of $10,000. *Page 392 According to testimony, Miree's president then contacted the architect by phone and was told that he, the architect, was dissatisfied with Miree's work. Miree's president testified that he informed the architect at that time that if he found something else wrong with Miree's work, "I will be glad to get it straight."

Miree's president testified further that on January 9, 1989, he went to the job site and found painters from another company on the job. However, he stated that he did not actually receive written notice of Woodward's intent to terminate the contract until January 19, 1989, when he received a letter, postmarked January 13, 1989, from Woodward's president indicating that another subcontractor had been hired to complete the job. Enclosed with this letter was a copy of another letter, dated December 22, 1988, originally sent by the supervising architect to Woodward's president, expressing dissatisfaction with Miree's performance and recommending that Woodward hire another painting company.

Miree contends that the telephone conversations with Woodward and the supervising architect on December 22, 1988, cannot constitute a second notice. It further maintains that the letter it received from Woodward on January 19, 1989 (with the enclosure from the architect), may not be considered as a second written notice, because Woodward had already substituted another subcontractor for Miree before the letter was received. We agree.

The termination provision in the contract clearly provides that the notice contemplated must be in writing. Further, it is also clear from the language of this provision that Woodward could not terminate the contract with Miree and complete the work by some other method until seven days had elapsed from Miree's receipt of a second written notice. A court cannot refine away the terms of a contract that are expressed with sufficient clarity to convey the intent and meaning of the parties. Kinnon v. Universal Underwriters Insurance Co.,418 So.2d 887 (Ala. 1982).

Woodward contends that notwithstanding the letter of January 19, 1989, it provided Miree with at least two other

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King v. City of Birmingham
885 So. 2d 802 (Court of Civil Appeals of Alabama, 2004)
Baker v. Wilbourn
895 So. 2d 965 (Court of Civil Appeals of Alabama, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
627 So. 2d 389, 1992 WL 246093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miree-painting-v-woodward-const-alacivapp-1992.