Minton v. Intercontinental Terminals Company, LLC

District Court, S.D. Texas·Decided October 5, 2023·No. 4:21-cv-00143·Unknown

Opinion

UNITED STATES DISTRICT COURT October 06, 2023 SOUTHERN DISTRICT OF TEXAS Nathan Ochsner, Clerk HOUSTON DIVISION

MINTON et al., § Plaintiffs, § v. § No. 4:21-cv-00143 § INTERCONTINENTAL § TERMINALS COMPANY, LLC et § al., § Defendants. § ______________________________ § § IN RE: INTERCONTINENTAL § No. 4:19-cv-1460 TERMINALS COMPANY, LLC § DEER PARK FIRE LITIGATION §

OPINION AND MEMORANDUM This is a mass tort suit arising out of a fire at Defendant Intercontinental Terminals Company LLC’s (“ITC”) storage tank facility in Deer Park.1 Pending before the Court is ITC’s motion for summary judgment on Plaintiffs’ gross negligence claim. ITC’s MSJ, ECF No. 270; see also In re Intercontinental Terminals Company LLC Deer Park Fire Litigation, 4:19-cv-01460 (“Munoz”), ITC’s MSJ, ECF Nos. 1466, 1467.2

1 On September 29, 2022, based on the parties’ consent, this bellwether consolidated case was deconsolidated from the Munoz consolidated case and transferred to this Court to conduct all proceedings pursuant to 28 U.S.C. § 636(c). Order Transferring, ECF No. 12; see also Munoz, 4:19-cv-1460, Order Transferring, ECF No. 1332. This order is filed in both cases so that the remaining plaintiffs are aware of the actions in this bellwether consolidated case. 2 Plaintiffs filed a response. Pls.’ Response, ECF Nos. 314, 315; Munoz, 4:19-cv-1460, ECF Nos. 1511, 1512. ITC filed a reply. ITC’s Reply, ECF No. 303; Munoz, 4:19-cv-1460, ECF No. 1521. At the hearing on September 27, 2023, the Court announced from the bench that ITC’s motion for summary judgment would be denied. This Opinion and

Memorandum explains the Court’s ruling. After a thorough consideration of the briefing, evidence, and applicable law, the Court finds that there are genuine issues of material fact precluding summary judgment because a reasonable jury could find

that ITC’s failure to implement remote motor operated valves (“MOVs”), a lower explosive limit monitor (“LEL monitor”), and a deluge system at Tank 80-8 was grossly negligent. Therefore, ITC’s motion for summary judgment is denied. I. BACKGROUND

This action concerns a fire at ITC Deer Park that burned from March 17, 2019 to March 20, 2019. Most of the Plaintiffs in the consolidated action are residents of the surrounding community who sued for personal injuries they allegedly suffered

because of their exposure to the toxic chemicals released into the atmosphere from the fire (“PI Plaintiffs”). The remaining Plaintiffs are various businesses who have sued for financial damages they allegedly suffered because of the fire’s impact on the surrounding area, including the waterways (“Commercial Plaintiffs”).

A. ITC’s HAZOP Assessment In 2014, ITC installed a butane injection system at Tank 80-8 at ITC Deer Park, which facilitated the combination of injected butane with stored naphtha. ECF

Nos. 270-2 at 160, 271-1; Munoz, 4:19-cv-1460, ECF Nos. 1511-2 at 160; 1512-1. As part of the installation, ITC conducted a Hazard and Operability (“HAZOP”) assessment that identified hazards the new injection system posed, consequences of

those hazards with and without safeguards in place, and recommendations for mitigation of any remaining hazards, which according to ITC policy, had to be initiated within three months to a year. ECF Nos. 315-1 at 13–14; 315-3 at 2; Munoz,

4:19-cv-1460, ECF Nos. 1512-1 at 13–14; 1512-3 at 2. On August 13 and 15, 2014, a team at ITC, which included Vice President Carl Holley, reviewed the HAZOP assessment. ECF No. 315-1 at 13–14; Munoz, 4:19-cv-1460, ECF No. 1512-1 at 13– 14.

To reduce the high risk of catastrophic fire, the HAZOP assessment issued three safety recommendations—installation of: (1) MOVs which are “valve[s] designed, installed, and maintained for the primary purpose of achieving rapid

isolation of plant items containing hazardous substances in the event of a failure of the primary containment system including, but not limited to, leaks from pipework, flanges, and pump seals;”3 (2) LEL monitors which detect flammable gases and trigger an alarm if gas or vapor exceeds a set level;4 and (3) a deluge system at the

pump which could supply water immediately upon fire detection.5 ITC decided to

3 Carl Holley’s Deposition Testimony, ECF No. 315-2 at 300–01; Munoz, 4:19-cv-1460, ECF No. 1512-2 at 300–01.

4 ECF No. 315-2 at 333; Munoz, 4:19-cv-1460, ECF No. 1512-2 at 333.

5 ECF No. 315-2 at 333; Munoz, 4:19-cv-1460, ECF No. 1512-2 at 333. install MOVs in November 2022, eight years later at the next time Tank 80-8 would be taken out of service, but did not assign target dates for installation of any LEL

monitors or a deluge system. ECF Nos. 315-1 at 13–14; 315-2 at 142; Munoz, 4:19- cv-1460, ECF Nos. 1512-1 at 13–14; 1512-2 at 142. As a result, none of these recommendations were in place at the time of the fire, five years after the HAZOP

assessment. B. The Fire On March 16, 2019, two truckloads of butane were injected into Tank 80-8. ITC Tank Truck Unloading Report, ECF No. 271-43; Munoz, 4:19-cv-1460, ECF

No. 1467-43. Plaintiffs allege that Tank 80-8’s circulation pump ran from March 16, 2019 into the following day, and on the morning of March 17, 2019, the liquid level in Tank 80-8 rapidly decreased without alarm—approximately thirty minutes later,

the fire ignited. ECF No. 315-2 at 272, 274, 277; Munoz, 4:19-cv-1460, ECF No. 1512-2 at 272, 274, 277. Fifteen storage tanks containing chemicals burned—the fire was extinguished days later, on March 20, 2019. Harris County Fire Marshal’s Office Report, ECF

No. 270-53 at 4; Munoz, 4:19-cv-1460, ECF No. 1466-53 at 4. In response to the fire, ITC’s emergency response teams arrived on scene and tried to extinguish the fire but were unable to do so. ECF No. 315-2 at 286, 288; Munoz, 4:19-cv-1460,

ECF No. 1512-2 at 286, 288. Plaintiffs contend that had the above recommendations been in place, ITC could have contained the fire and this event would not have been catastrophic. ECF No. 314 at 12; Munoz, 4:19-cv-1460, ECF No. 1511 at 12.

C. Plaintiffs’ Gross Negligence Claims Plaintiffs bring claims for injuries allegedly suffered because of the fire, including negligence and gross negligence claims against ITC. ECF No. 85; Munoz,

4:19-cv-1460, ECF No. 544. Regarding their negligence and gross negligence claims, the bellwether Plaintiffs enumerated ITC’s allegedly negligent acts or omissions, including: failing “to maintain equipment;” failing “to have in place a fixed fire foam suppression

system for fire prevention, control or direct extinguishment of any flammable or combustible liquid fire within their tanks;” failing “to have access to dry chemical and/or foam fire suppression materials to extinguish the fire after it started;” causing

and permitting the “release of volatile organic compounds and chemicals resulting in a continuous toxic cloud over La Porte, Deer Park and other parts of Harris County, Texas;” and failing to use ordinary care in monitoring the release of air contaminants. . . . ” ECF No. 85 ¶ 23; Munoz, 4:19-cv-1460, ECF No. 544 ¶ 23.

They alleged that “[t]he acts or omissions . . . involved an extreme degree of risk of which they had actual, subjective awareness of the risk involved, but nevertheless proceeded with conscious indifference to the rights, safety, or welfare of others.”

ECF No. 85 ¶ 25; Munoz, 4:19-cv-1460, ECF No. 544 ¶ 25. II. THE STANDARD OF REVIEW ON SUMMARY JUDGMENT Summary judgment is appropriate when the movant has established that the

pleadings, affidavits, and other evidence available to the court demonstrate that no genuine issue of material fact exists, and the movant is thus entitled to judgment as a matter of law. FED. R. CIV. P. 56(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Minton v. Intercontinental Terminals Company, LLC, (S.D. Tex. 2023).

Minton v. Intercontinental Terminals Company, LLC (Minton v. Intercontinental Terminals Company, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Henderson v. Norfolk Southern Corp.
55 F.3d 1066 (Fifth Circuit, 1995)
Oliver v. Scott
276 F.3d 736 (Fifth Circuit, 2002)
TIG Insurance v. Sedgwick James of Washington
276 F.3d 754 (Fifth Circuit, 2002)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
Universal Services Co. v. Huy Hieng Khaov Ung
904 S.W.2d 638 (Texas Supreme Court, 1995)
Guadalupe-Blanco River Authority v. Pitonyak
84 S.W.3d 326 (Court of Appeals of Texas, 2002)
Lee Lewis Construction, Inc. v. Harrison
70 S.W.3d 778 (Texas Supreme Court, 2002)
Mobil Oil Corp. v. Ellender
968 S.W.2d 917 (Texas Supreme Court, 1998)
Wal-Mart Stores, Inc. v. Alexander
868 S.W.2d 322 (Texas Supreme Court, 1994)
Transportation Insurance Co. v. Moriel
879 S.W.2d 10 (Texas Supreme Court, 1994)
Ardoin v. ANHEUSER-BUSCH, INC.
267 S.W.3d 498 (Court of Appeals of Texas, 2008)
Diamond Shamrock Refining Co., LP v. Hall
168 S.W.3d 164 (Texas Supreme Court, 2005)
North American Van Lines, Inc. v. Emmons
50 S.W.3d 103 (Court of Appeals of Texas, 2001)
Turner v. Franklin
325 S.W.3d 771 (Court of Appeals of Texas, 2010)
McDorman Ex Rel. Connelly v. TEXAS-COLA LEASING CO., LP
288 F. Supp. 2d 796 (N.D. Texas, 2003)
Lonny Acker v. General Motors, L.L.C.
853 F.3d 784 (Fifth Circuit, 2017)
Louis Koerner, Jr. v. Vigilant Insurance Company
910 F.3d 221 (Fifth Circuit, 2018)
U-Haul International, Inc. v. Waldrip
380 S.W.3d 118 (Texas Supreme Court, 2012)