Minnkota Power Cooperative, Inc. v. Manitowoc Co.

669 F.2d 525
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 13, 1982
DocketNo. 80-1923
StatusPublished
Cited by4 cases

This text of 669 F.2d 525 (Minnkota Power Cooperative, Inc. v. Manitowoc Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Minnkota Power Cooperative, Inc. v. Manitowoc Co., 669 F.2d 525 (8th Cir. 1982).

Opinion

BRIGHT, Circuit Judge.

Manitowoc Company, Inc., (Manitowoc) appeals from an adverse judgment entered after a jury awarded Minnkota Power Cooperative, Inc., (Minnkota) and Baukol-Noo-nan, Inc., (Baukol-Noonan), $217,300 in damages, and from a separate judgment dismissing Manitowoc’s third party claim against Sanderson and Porter, Inc., (Sand-erson and Porter). Minnkota and Baukol-Noonan brought this action against Manito-woc for damages sustained when a construction crane operated by a Manitowoc employee, but owned by Peter Kiewit Sons’ Company, Inc., (Kiewit), struck an overhead electric power line running between Minnk-ota’s power plant and Baukol-Noonan’s coal mine. This power interference damaged Minnkota’s transformer and deprived Bau-kol-Noonan of electricity necessary to continue its coal mining operation. The judgment represented damages of $189,700 to Minnkota and $27,600 to Baukol-Noonan.

In response to Manitowoc’s numerous assertions of error, we grant a partial new [527]*527trial to determine whether to attribute fault to Kiewit under an aspect of the borrowed servant doctrine and, if necessary, an appropriate reduction of damages against Manitowoc. We affirm the judgments in other respects.

I. Procedural Background.

Minnkota and Baukol-Noonan brought this action 1 for damages against Manitowoc and Kiewit, alleging the negligence of both defendants. Manitowoc had sold Kiewit the crane which caused the accident. Mani-towoc impleaded Sanderson and Porter as a third party defendant, alleging that Sand-erson and Porter’s negligent design of the Minnkota power plant contributed to plaintiffs’ damages. Prior to trial, plaintiffs settled with Kiewit for $7,000 and released Kiewit from all liability claims.

We recognize that such a settlement may diminish the amount of damages plaintiffs may recover from the remaining defendants. The Supreme Court of North Dakota has determined that in certain instances a plaintiff’s damages must be reduced by an amount proportionate to the percentage of negligence attributed by the factfinder to the released tortfeasor. See Bartels v. City of Williston, 276 N.W.2d 113 (N.D.1979).2

The trial court submitted to the jury the issue of Manitowoc’s negligence and plaintiffs’ damages, and dismissed Manitowoc’s third party negligence claim against Sand-erson and Porter for insufficient evidence. The court refused to instruct the jury to determine Kiewit’s relative degree of fault on the ground that Manitowoc failed to prove any causal negligence attributable to the released codefendant.

Before trial, the court ruled that Manito-woc could not call experts to testify concerning Sanderson and Porter’s allegedly negligent design of the Minnkota transformer. The court determined that allowing the expert testimony after Manitowoc failed to make timely disclosure of its experts’ identity and the basis of their proposed testimony would prejudice the plaintiffs.

After trial, Manitowoc moved for a new trial, asserting twenty-two alleged errors in the trial court’s rulings, and, alternatively, sought a setoff on the judgment for the $7,000 plaintiffs received in their settlement with Kiewit. The trial court denied these motions and on this appeal Manitowoc reasserts several allegations of error made in its motions for new trial and partial setoff.

Manitowoc raises the following claims of error on appeal:

1) The trial court abused its discretion in barring Manitowoc from calling expert witnesses to testify regarding Sanderson and Porter’s allegedly negligent design of the transformer.
2) The trial court erred in several evi-dentiary rulings.
3) The trial court erred in its instruction on proximate cause.
4) The trial court erred in refusing to instruct on negligence attributable to the released defendant Kiewit, by imputing the negligence of a Manitowoc employee [528]*528to Kiewit under the joint enterprise theory or the borrowed servant doctrine.
5) The trial court erred in refusing to set off the $7,000 settlement against plaintiffs’ recovery.

After reviewing the record, we have determined that the trial court erred in refusing to instruct on the borrowed servant doctrine as a basis for attributing fault to the released codefendant, Kiewit, and for reducing the damages assessed against Manitowoc. See Bartels v. City of Willi-ston, supra, 276 N.W.2d at 122.

Accordingly, we remand for a new trial only on the issue of Kiewit’s liability under the borrowed servant doctrine.

II. Factual Background.

Prior to the incident in question, Square Butte Cooperative (Square Butte) began building a power plant on property adjacent to Minnkota’s Power Station, near Center, North Dakota. Square Butte hired Kiewit to do the excavation and foundation work for the plant. To perform that work, Kiew-it purchased a large crane from Manitowoc, a crane manufacturing company. Pursuant to the purchase contract, Manitowoc sent one of its employees, Carman Way, to supervise assembly of the crane at the construction site and to instruct Kiewit’s employees in the operation of the crane.

According to the record, the crane’s purchaser ordinarily supplies an operator to assist in the operation and movement of the crane unit during assembly. Because Kiew-it did not have an operator available, Kiew-it’s equipment superintendent asked Way to operate the crane. Way ran the crane for Kiewit during its assembly and parked it near an earthen embankment upon completion of assembly.

On Monday; July 21, 1975, Way again operated the crane to move it away from the embankment so that Kiewit could put it to work. To move the crane, Way had to raise and rotate the boom. During this movement, Way hit the overhead power line running from the start-up transformer on Minnkota’s power plant to Baukol-Noo-nan’s coal mine. The collision damaged the transformer, causing the mine to close until the transformer could be repaired.

With this factual background, we discuss the issues presented on this appeal.

III. Discovery Sanction.

Manitowoc complains that the district court abused its discretion by refusing to permit Manitowoc’s expert witnesses to testify regarding the allegedly negligent design of Minnkota’s transformer. In March 1979, Manitowoc had failed to answer fully plaintiff’s interrogatories concerning Mani-towoc’s expert witnesses and any reports it had on the design of the transformer. Manitowoc answered by asserting that it had made no decision on whether to use an expert witness, and that its report on the transformer was protected as work product and because it contained communications protected by the attorney-client privilege.

Although the trial court ordered discovery completed by December 20, 1979, Manitowoc did not file supplemental responses to the March 1979 interrogatories until March 12, 1980. Plaintiffs moved to strike the responses and to bar Manitowoc’s expert testimony. In a pretrial hearing on April 2, 1980, the court excluded Manito-woc’s proposed expert testimony because Manitowoc’s failure to comply with the discovery deadline would prejudice the plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
669 F.2d 525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/minnkota-power-cooperative-inc-v-manitowoc-co-ca8-1982.