This text of 81 Mo. App. 255 (Minnesota Thresher Manufacturing Co. v. Grant City Lumber & Hardware Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Minnesota Thresher Manufacturing Co. v. Grant City Lumber & Hardware Co., 81 Mo. App. 255, 1899 Mo. App. LEXIS 394 (Mo. Ct. App. 1899).

Opinion

GILL, J.

In August, 1896, one Cook negotiated for and purchased from the plaintiff a threshing outfit. The business was conducted through Goodsill, Cook’s relative, and who was the president and manager of the defendant Hardware Company at Grant City. The sale was concluded August 15, [257]*2571896, -when a writing incorporating the terms of the contract was signed by the parties, and there was also executed by Cook to the machine company three promissory notes — one for $750 due December 1, 1896, one for a like amount due December 1, 1897, and one for $550 due December 1, 189S, all bearing 8 per cent interest from date. To secure these notes Cook also executed a chattel mortgage covering the machine as also what is called an “earnings contract,” whereby he agreed to turn over to the company one-half the gross earnings of the thresher until the debt was paid. In addition to this, the plaintiff required, and the defendant by Goodsill, its president, signed, the following guaranty written on the back of the note maturing by its terms December 1, 1896:

“Eor value received I hereby guarantee the payment of the within note and interest three months after its maturity, or at any time thereafter, on demand of Minnesota Thresher Manufacturing Company, or order, hereby waiving notice, demand, protest, diligence in collecting and prejudice by renewals or extensions.
“Dated this 15th day of August, 1896.
“Grant City Lbr. & Hard. Co.
“A. G. Pt.”

■Cook made several payments on this note, aggregating about $190, but failing to pay the balance, plaintiff sued the defendant on the above guaranty.

In the trial of the case the circuit court, over plaintiff’s objection, permitted Goodsill, defendant’s manager, to testify, in effect, that a few days prior to the sale of the machine and the execution of ¡the written contract, and prior to the execution of the Cook notes and defendant’s written guaranty indorsed on the one first maturing, he (Goodsill) had a conversation with plaintiff’s agent at Kansas City wherein it was understood that defendant should guaranty the payment of said first note but with the condition or understanding that [258]*258plaintiff should not call on said guarantor for the payment of said note until plaintiff had made every effort to collect whatever was coming to it on the earnings contract and should have first foreclosed the chattel mortgage on the threshing outfit. And at the close of the evidence defendant asked and the court gave an instruction to the effect that if the jury found that the plaintiff and defendant entered into a verbal and entire contract by which the defendant as agent for the plaintiff was to sell to Oook the machine in question, was to take therefor Cook’s notes, chattel mortgage and also an earnings contract by which Cook was to pay to plaintiff half the gross receipts from the machine to be applied on the payment of the notes, “and that by the further terms of said original verbal contract the defendant was to take said notes, chattel mortgage, earnings contract and the contract of guaranty of this defendant and deliver to the plaintiff, and that the said plaintiff was to give careful and close attention to the collection of the one-half of the earnings of said machinery, and to apply first, the earnings to the discharge of the note sued on in this case, and if at the maturity of said note the plaintiff had not collected a sufficient amount on said earnings contract to fully discharge the note, then the plaintiff was to sell said machinery under said chattel mortgage to satisfy the balance due upon said note, and the defendant was only to be liable to pay upon said contract of guaranty whatever sum or balance there might be found to be due upon said note after applying the proceeds of said earnings contract, and selling said machinery under said chattel mortgage, and if the jury further believe that the defendant fully complied with all the terms of said original verbal contract on its part, and that the plaintiff has failed, refused or neglected to collect or apply the earnings of said machine upon said notes or to sell said machinery under said chattel mortgage and apply the proceeds thereof to the discharge of said note, then the jury are instructed that the plaintiff can not recover in this case, and they must find for the defendant.”

[259]*259Following such evidence and instructions the jury returned a verdict for defendant and from a judgment in accordance therewith plaintiff appealed.

It is an old and well established rule that no contemporaneous or antecedent verbal evidence can be used to add to, detract from, vary or modify the terms of a written contract. All prior or contemporaneous negotiations are treated as having been merged into the writing then or subsequently solemnly entered into by the parties. The very purpose of the writing is to make a lasting and permanent testimonial of the terms by which the parties intend to be bound — avoiding in the future all misunderstandings, defects of “slippery memory” or temptations to false swearing. In this case there seems to have been a clear departure from .this salutary rule of evidence. The action is based on a complete written contract, clear and explicit. The instrument, quoted in the foregoing statement, is in no sense clothed in dubious language. On its face it purports to be an absolute, unequivocal undertaking, whereby the defendant promised to stand good for the default of Oook, the maker of the note. Nor is there any question as to the sufficiency of the consideration. Eor value received the defendant “hereby guarantees the payment of the within note and interest three months after its maturity, or at any time thereafter, on demand of- the Minnesota Thresher Manufacturing Company or order, hereby waiving notice, demand, protest, diligence in collecting,” etc.

By the terms of this contract defendant pledged itself to answer for the default of the maker of the note. It agreed, absolutely and without condition, to pay the note and interest at any time three months after its maturity on demand of the plaintiff — waiving even any want of diligence on the part of the payee or holder in seeking its collection of the maker. But, under sanction of the trial court, the defendant-introduced oral evidence to vary and contradict the express terms of the contract; was allowed to prove that prior to the [260]*260execution of the instrument .the parties had certain verbal negotiations of quite a different character; that, instead of agreeing to pay the debt absolutely after the expiration of three months past due and without ref erence to any diligence in collecting it from the maker (as clearly declared in the writing), it was understood and agreed that defendant should not be required to pay the note, or balance due thereon, except on condition that the plaintiff had diligently sought and exhausted every relief on the earnings contract and had foreclosed the chattel mortgage on the machine. If this was not an instance of seeking to vary and modify the terms of a written contract by proof of antecedent verbal negotiations then it is difficult to conceive of one.

It is contended, -however, by the learned counsel for defendant that the contract was verbal and entire and that the giving of the written guaranty was only a part thereof— that this writing was made as part performance of the main contract, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wood v. White Eagle Oil & Refining Co.
274 S.W. 894 (Missouri Court of Appeals, 1925)
Supreme Lodge Knights of Pythias v. Dalzell
223 S.W. 786 (Missouri Court of Appeals, 1920)
Smith Sand & Gravel Co. v. Corbin
142 P. 1163 (Washington Supreme Court, 1914)
Hines v. Royce
106 S.W. 1091 (Missouri Court of Appeals, 1908)
Morrow v. Pryor
102 S.W. 582 (Missouri Court of Appeals, 1907)
Goodwin Manufacturing Co. v. Fritsch Foundry & Machine Co.
89 S.W. 911 (Missouri Court of Appeals, 1905)
Williams v. Kansas City Suburban Belt Railway Co.
85 Mo. App. 103 (Missouri Court of Appeals, 1900)
Norwich Union Fire Insurance v. Buchalter
83 Mo. App. 504 (Missouri Court of Appeals, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
81 Mo. App. 255, 1899 Mo. App. LEXIS 394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/minnesota-thresher-manufacturing-co-v-grant-city-lumber-hardware-co-moctapp-1899.