Minger Construction, Inc. v. Clark Farms, Ltd., and Kevin W. Clark, AKA K.W. "Casey" Clark

CourtCourt of Appeals of Iowa
DecidedNovember 12, 2015
Docket14-1404
StatusPublished

This text of Minger Construction, Inc. v. Clark Farms, Ltd., and Kevin W. Clark, AKA K.W. "Casey" Clark (Minger Construction, Inc. v. Clark Farms, Ltd., and Kevin W. Clark, AKA K.W. "Casey" Clark) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Minger Construction, Inc. v. Clark Farms, Ltd., and Kevin W. Clark, AKA K.W. "Casey" Clark, (iowactapp 2015).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 14-1404 Filed November 12, 2015

MINGER CONSTRUCTION, INC., Plaintiff-Appellee,

vs.

CLARK FARMS, LTD., and KEVIN W. CLARK, aka K.W. “CASEY” CLARK, Defendants-Appellants. ________________________________________________________________

Appeal from the Iowa District Court for Dickinson County, David A. Lester,

Judge.

A subcontractor on a city’s sewer upgrade project and the sole

shareholder of the subcontracting company appeal a jury verdict in favor of the

contractor. AFFIRMED.

Andrea M. Smook of Cornwall, Avery, Bjornstad, Scott & Davis, Spencer,

for appellants.

Wade S. Davis of Stinson, Lenard & Street, L.L.P., Mankato, Minnesota,

for appellee.

Considered by Vaitheswaran, P.J., and Tabor and McDonald, JJ. 2

VAITHESWARAN, Presiding Judge.

A subcontractor on a city’s sewer upgrade project and the sole

shareholder of the subcontracting company appeal a jury verdict in favor of the

contractor. They assert the evidence was insufficient to support (1) a finding that

the subcontractor breached its contract and (2) a finding that the shareholder

was personally liable for damages.

I. BACKGROUND FACTS AND PROCEEDINGS

Minger Construction, Inc. contracted with the City of Terril to upgrade its

sewer system. Minger subcontracted with Clarks Farms, Ltd. to remove

processed human and food grade waste, known as sludge. The subcontract

agreement required Clark Farms “to furnish all labor, material, skill and

equipment necessary or required and to perform all the work . . . necessary to

complete” the project.

Kevin Clark was “the sole owner, the shareholder, the sole board member

and the president” of Clark Farms. Clark Farms failed to comply with certain

prerequisites to working on the public project. The company was incorporated in

2001 but was administratively dissolved in 2012, the year Clark Farms entered

into the contract with Minger. The company did not have its corporate status

reinstated until 2013. The company also failed to maintain a certified payroll and

observe specified safety practices. Minger notified Clark of these omissions and,

on multiple occasions, attempted to obtain compliance. Clark Farms did not

respond.

Clark Farms began removing sludge, but ran into problems, including

equipment failure. On September 25, 2012, Minger transmitted a notice to Kevin 3

Clark stating, “If you are not on the above-referenced project by tomorrow

morning 09-26-12 @ 7:00 AM—we will proceed to hire someone else and your

equipment will be held in escrow for reimbursement of added costs because you

are in breach of your contract.” Clark Farm employees went to the job site but,

according to Minger, did not perform their job duties.

Ten days after the September 25 notification, Minger terminated the

contract for failure to “satisfactorily meet[] the terms of the Default Notice.”

Minger hired a new company to complete the sludge removal and sued Clark

Farms and Clark for breach of the subcontract.

The case proceeded to a jury trial. The jury found Minger did what it was

required to do under the contract, Clark Farms breached its contract with Minger,

and Kevin Clark was personally liable for the breach. The jury awarded Minger

damages of $78,272.36. Clark Farms and Clark appealed.

II. Analysis

A. Breach of Contract

The jury was instructed Minger would have to prove the following

elements of its breach-of-contract claim:

(1) the existence of a contract, (2) the terms of the contract, (3) [Minger] had done what the contract requires, (4) [Clark Farms and Clark] breached the contract, and (5) the amount of any damage [Clark Farms’ and Clark’s] breach caused [Minger].

The defendants take issue with the jury’s findings on the third and fifth elements.

Our review of the fact findings is for substantial evidence. See Iowa Mortg. Ctr.,

L.L.C. v. Baccam, 841 N.W.2d 107, 110 (Iowa 2013). 4

1. Element 3

Clark Farms and Clark contend Minger did not do what the contract

required, as specified in the third element of the instruction and, specifically failed

to follow the default provision of the contract. The provision states:

17. (Default) That in case the Subcontractor shall fail when and if required by the Contractor, to correct, replace and/or re- execute faulty or defective work done and/or materials furnished under this Subcontract, or repeatedly and persistently to complete or proceed with this Subcontract within the schedule agreed to by the parties or the time herein provided for, . . . or to comply with any substantial term of this Subcontract, then the Contractor may give the Subcontractor a written notice to cure the Subcontractor’s default. If the Subcontractor fails within three (3) working days after receipt of the notice of default to commence and continue satisfactory correction of such default with diligence and promptness, then the Subcontractor shall be in default of this Subcontract and the Contractor, upon an additional three (3) calendar days notice in writing to the Subcontractor, shall have the right to terminate this Subcontract and finish the Subcontractor’s Work, replace and/or re-execute such faulty or defective Work or materials, either through its own employees or through a contractor or subcontractor of its choice, and to charge the cost thereof to the Subcontractor, together with any liquidated or actual damages caused by a delay in the performance of this Subcontract.

The defendants concede Minger’s September 25 notice “would be seen as the

notice of default required under Paragraph 17.” They argue Clark Farms

“show[ed] up on site and started working” as required by the default notice, “thus

curing their default within three working days.” In light of their actions, they

assert Minger “was required to give [them] an additional three day[] notice before

termination of the contract.”

A reasonable juror could have found otherwise. Patrick Minger testified

simply being at the job site was not enough; “[c]ommon sense” would dictate the

employees also had to be “producing.” Minger said “they weren’t producing.” 5

The jurors could have credited his testimony over Clark’s, who said he “had guys

over there working on the transfer of the material.” See Brokaw v. Winfield-Mt.

Union Cmty. Sch. Dist., 788 N.W.2d 386, 394 (Iowa 2010) (stating the fact finder

determines witness credibility and the weight of the evidence). The jury could

have surmised Clark Farms’s failure to perform productive work was essentially

the straw that broke the camel’s back.

Patrick Minger stated the engineering company on the project was giving

him “heat” to get the sludge cleared. Clark Farms did not accomplish this goal

and, in addition, failed to obtain the proper contractor certification, failed to pay

for the repair of its equipment, failed to pay its employees statutorily required

wages, failed to train its employees, failed to take proper safety precautions,

failed to perform the work in an “orderly and efficient manner,” and failed to use

the “means and methods necessary to accomplish the job.” In light of these

numerous omissions, the jury could have found the defendants did not cure the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Katchen v. Landy
382 U.S. 323 (Supreme Court, 1966)
Pierson v. Jones
625 P.2d 1085 (Idaho Supreme Court, 1981)
Boyd v. Boyd & Boyd, Inc.
386 N.W.2d 540 (Court of Appeals of Iowa, 1986)
Benson v. Richardson
537 N.W.2d 748 (Supreme Court of Iowa, 1995)
Briggs Transportation Co. v. Starr Sales Co.
262 N.W.2d 805 (Supreme Court of Iowa, 1978)
C. Mac Chambers Co. v. Iowa Tae Kwon Do Academy, Inc.
412 N.W.2d 593 (Supreme Court of Iowa, 1987)
Laya v. Erin Homes, Inc.
352 S.E.2d 93 (West Virginia Supreme Court, 1986)
Atlas Construction Co. v. Slater
746 P.2d 352 (Wyoming Supreme Court, 1987)
HOK Sport, Inc. v. FC Des Moines, L.C.
495 F.3d 927 (Eighth Circuit, 2007)
Cass v. Sands
713 N.W.2d 248 (Court of Appeals of Iowa, 2006)
White v. Winchester Land Development Corp.
584 S.W.2d 56 (Court of Appeals of Kentucky, 1979)
Morgan v. O'NEIL
652 S.W.2d 83 (Kentucky Supreme Court, 1983)
Chin v. Roussel
456 So. 2d 673 (Louisiana Court of Appeal, 1984)
Brokaw v. Winfield-Mt. Union Community School District
788 N.W.2d 386 (Supreme Court of Iowa, 2010)
Wescott & Winks Hatcheries v. F. M. Stamper Co.
85 N.W.2d 603 (Supreme Court of Iowa, 1957)
Northwestern National Bank of Sioux City v. Metro Center, Inc.
303 N.W.2d 395 (Supreme Court of Iowa, 1981)
Weltzin v. Nail
618 N.W.2d 293 (Supreme Court of Iowa, 2000)
Team Central, Inc. v. Teamco, Inc.
271 N.W.2d 914 (Supreme Court of Iowa, 1978)
Wyatt v. Crimmins
277 N.W.2d 615 (Supreme Court of Iowa, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
Minger Construction, Inc. v. Clark Farms, Ltd., and Kevin W. Clark, AKA K.W. "Casey" Clark, Counsel Stack Legal Research, https://law.counselstack.com/opinion/minger-construction-inc-v-clark-farms-ltd-and-kevin-w-clark-aka-iowactapp-2015.