Milton D. Taylor Construction Co. v. Ohio Department of Transportation

572 N.E.2d 712, 61 Ohio App. 3d 222, 1988 Ohio App. LEXIS 5349
CourtOhio Court of Appeals
DecidedDecember 20, 1988
DocketNo. 88AP-348.
StatusPublished
Cited by1 cases

This text of 572 N.E.2d 712 (Milton D. Taylor Construction Co. v. Ohio Department of Transportation) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milton D. Taylor Construction Co. v. Ohio Department of Transportation, 572 N.E.2d 712, 61 Ohio App. 3d 222, 1988 Ohio App. LEXIS 5349 (Ohio Ct. App. 1988).

Opinion

Peggy L. Bryant, Judge.

Plaintiff-appellant, Milton D. Taylor Construction Co., appeals from a judgment of the Ohio Court of Claims in favor of defendant-appellee, Ohio Department of Transportation, on plaintiff’s claim for breach of contract.

Pursuant to bid, plaintiff was awarded a contract with defendant to construct a culvert under a roadway in Mahoning County to accommodate a stream draining from a nearby reservoir. Under that contract, plaintiff was to construct a pipe arch with concrete headwalls at both the inlet and outlet of the culvert. While plaintiff’s contract with defendant provided design and general construction details of the contract, it did not specify the forms that plaintiff was to use in preparing for and forming the headwalls.

Employing a method apparently utilized by others in the industry, plaintiff used a wooden form into which concrete was poured to shape the concrete headwalls. The form included stringers, which blocked a portion of the opening of the pipe and culvert. On June 15, 1982, the forms were assembled and the concrete was poured. On the evening of June 15, rain began to fall and continued into the next day. Over a period of approximately twenty-eight *224 hours, 1.84 inches of rain fell. When the company returned to the project on June 17, it found that the headwall and forms, together with a portion of the pipe arch, had lifted out of place into the air and were damaged.

Pursuant to Section 107.15 of the Construction and Material Specifications, plaintiff repaired the damage to the project at a cost of $30,470.04 and sought reimbursement from defendant. Defendant refused payment, contending that the damage to the project was caused through the fault or negligence of the contractor under Section 107.16 of the Construction and Material Specifications. Plaintiff then initiated a lawsuit in the Ohio Court of Claims, contending that defendant breached its contract with plaintiff by its failure to reimburse plaintiff for the cost of repairing the damage to the construction. A hearing was held before a referee, who, following several days of testimony, prepared a report, including findings of fact and conclusions of law. Therein, the referee recommended that judgment be entered for defendant. The trial court accepted the referee’s report and recommendation and entered judgment accordingly. Plaintiff appeals, setting forth five assignments of error:

“1. The Court of Claims, by its referee, erred as a matter of law in failing to consider that ‘unforeseeable causes’ and not merely ‘acts of God’ entitle a contractor to additional compensation for work performed and subsequently damaged during construction.
“2. The Court of Claims erred as a matter of law, in failing to find that the collapse of a pipe arch on a construction project was an unforeseeable condition, without the fault of appellant, and entitling appellant to costs of repair and replacement.
“3. The Court of Claims, by its referee, erred as a matter of law in requiring a construction contractor to establish defective design by the owner before it could recover under a contract clause allowing payment to the contractor for damage occasioned to work by unforeseeable causes.
“4. The Court of Claims, by its referee, erred as a matter of law in failing to award damages on a construction project, which [damages] were not disputed, representing * * * [the contractor’s] costs to rebuild a portion of the project.
“5. The Court of Claims erred, as a matter of law, in failing to other than simply confirm the report of a referee without any consideration given to objections filed by appellant.”

Plaintiff combines the first three assignments of error into its first proposition of law, which it sets forth as the following:

*225 “A contractor who submits a claim for additional compensation for work damaged after completion upon an Ohio Department of Transportation construction project is entitled, pursuant to ODOT construction and material specifications, to consideration of the claim on the basis of whether it is due to unforeseeable causes which go beyond the definition of an act of God as may be defined in prior legal precedent.”

In its first proposition of law, then, plaintiff contends that the referee erred in failing to consider whether the circumstances presented by the construction project at issue constituted an unforeseeable condition outside the control of plaintiff. Plaintiff suggests that had the referee so considered the facts presented at the hearing, he would have concluded that the pipe’s rising into the air, and the damage caused thereby, resulted from an unforeseeable cause outside the control of the contractor, and therefore compensable under Section 107.16.

Section 107.16 of the defendant’s Construction and Material Specifications states the following:

“Contractor’s Responsibility for Work. Until final written acceptance of the project by the Director, the Contractor shall have the charge and care thereof and shall take every precaution against injury or damage to any part thereof by the action of the elements or from any other cause, whether arising from the execution or from the nonexecution of the work. The Contractor shall rebuild, repair, restore, and make good all injuries or damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof except damage to the work due to unforeseeable causes beyond the control of and without the fault or negligence of the Contractor, including but not restricted to acts of God, of the public enemy or governmental authorities.” (Emphasis added.)

We note, preliminarily, pursuant to the foregoing language, two exceptions exist to the contractor’s responsibilities under this section: a general category of damage due to unforeseeable causes beyond the control of and without the fault or negligence of the contractor; and, a second category, included within the first, and specified as damage caused by acts of God, of the public enemy or governmental authorities.

In the case before us, plaintiff suggests that, while the referee considered whether the facts and circumstances of this case fell within the definition of an act of God as set forth in Piqua v. Morris (1918), 98 Ohio St. 42, 120 N.E. 300, the referee incorrectly failed to consider whether the facts and circumstances constituted unforeseeable causes beyond the control of the contractor.

*226 Initially, we agree with the referee that the rainfall herein does not constitute an act of God. More specifically, approximately 1.84 inches of rain fell over a period of twenty-eight hours. Testimony at the hearing established that that constituted a rainfall of a one-year frequency; in other words, one could expect a rainfall of that severity every year. Piqua v. Morris, supra, defines an “act of God” as follows:

“The term ‘act of God’ in its legal significance, means any irresistible disaster, the result of natural causes, such as earthquakes, violent storms, lightning and unprecedented floods.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
572 N.E.2d 712, 61 Ohio App. 3d 222, 1988 Ohio App. LEXIS 5349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milton-d-taylor-construction-co-v-ohio-department-of-transportation-ohioctapp-1988.