Millstone Dev. v. Berry, Unpublished Decision (5-9-2002)

Ohio Court of Appeals·Decided May 9, 2002·No. No. 01AP-907 (REGULAR CALENDAR).·Unpublished

Opinion

OPINION
Plaintiff, Millstone Development, Ltd. ("Millstone"), is a real estate developer which began construction of a large multi-family apartment complex in 1997. Millstone hired defendant James Berry ("Berry") to install the heating, ventilation, and air conditioning units at the project. However, the relationship between Millstone and Berry soured, and he was terminated in the fall of 1997.

On December 10, 1997, Millstone sued Berry for breach of contract seeking damages as a result of defective and incomplete work which Berry had performed. A few days before trial was to begin, Berry filed for Chapter 7 bankruptcy protection with the United States Bankruptcy Court for the Southern District of Ohio. Berry's bankruptcy petition was dismissed on August 6, 1999, "for want of prosecution." The bankruptcy stay was lifted, and on February 7, 2000, plaintiff's complaint proceeded to trial before Franklin County Court of Common Pleas Magistrate, Pat Sheeran. Magistrate Sheeran issued a decision on February 10, 2000, wherein he recommended that the trial court award damages in favor of Millstone in the amount of $55,499 plus prejudgment interest in the amount of $12,024.78. The trial court adopted the magistrate's report and entered judgment in favor of Millstone on March 8, 2000. Millstone Development, Ltd. v. Berry (1997), Franklin County Court of Common Pleas case No. 97CVH-12-10871.

In January 1998, after Millstone filed its lawsuit against Berry, Berry and defendant Giuseppe Pingue ("Pingue") entered into a land installment contract whereby Berry purchased from Pingue .838 acres of land improved with a 2,700 square foot office and warehouse facilitiy. Berry occupied this property and made payments thereon until just after Magistrate Sheeran issued his decision against Berry, and only days before that decision was adopted by the trial court. Specifically, on February 29, 2000, Berry and Pingue rescinded the land installment contract, and Berry transferred all of his interest in the property back to Pingue. On May 19, 2000, Millstone commenced this lawsuit against Berry and Pingue, claiming that the February 2000 rescission constituted a fraudulent transfer pursuant to R.C. 1336.04 and/or 1336.05. Millstone Development, Ltd. v. Berry, Franklin County Court of Common Pleas case No. 00CVH-05-4529.

Millstone's complaint against Berry and Pingue came before the court for trial on May 21, 2001. During the course of trial, the court heard the evidence and arguments concerning Millstone's claims of fraudulent conveyance, as well as the argument and testimony of defendant Pingue, expert witness Terry Watson, and Terry Conner, the managing member of Millstone. The trial court also accepted several exhibits offered by Millstone, as well as evidence concerning the failure of defendant Berry and his wife to appear before the court.

On June 12, 2001, the trial court announced a decision which included comprehensive findings of fact and conclusions of law. Particularly, the court reached several legal and factual conclusions concerning Berry's financial position, and the purported resale of the property to Pingue on February 29, 2000. These findings, which are now the subject of defendant Pingue's appeal, are set forth below:

3. According to the Bankruptcy Petition (Exhibit 10), Berry certified that his assets included his interest in the property located at 7522 Worthington-Galena Road (the "Property"), and that he had personal property of $11,752. Berry also represented in his Bankruptcy Petition that his liabilities totaled $107,569, of which included Millstone Development's claim in the Underlying Lawsuit valued at $35,000. Based upon the filings of Berry in his Bankruptcy Petition, Berry was insolvent in the summer of 1999.

4. The Property identified by Berry in his Bankruptcy Petition is the property he was purchasing from Defendant Pingue pursuant to a Land Installment Contract dated January 26, 1998. A copy of that Land Installment Contract was introduced into evidence as Exhibit 2. It was noted at the trial that the address of the Property has changed. A legal description of the Property is attached to these Findings of Fact and Conclusions of Law as Exhibit A.

5. Under the Land Installment Contract, Berry paid $20,000 down and made monthly payments beginning on January 26, 1998, in amounts ranging from $1,764 to $4,000. Most of the payments were in the amount of $2,000. The dates the payments were made and their amounts are set forth in Exhibit 4, which is a series of payment histories prepared by Pingue. Based upon the payment histories that Pingue produced in this case, the Plaintiff produced a summary statement describing the Berry payments and their proper application to the Land Installment Contract (Exhibit 9). Expert witness Terry Watson provided testimony concerning Exhibit 9. This Court finds that Exhibit 9 accurately reflects a summary of the payments that Berry made to Pingue pursuant to the Land Installment Contract and the proper application of those payments towards the purchase of the Property.

6. Under the Land Installment Contract, the purchase price of the Property was $160,000. Over the course of two years, Berry paid $65,081 to Pingue, of which $42,459.82 was applied towards principal.

7. Berry began making missing payments and making late payments towards the Land Installment Contract in September of 1999. Berry failed to make the September, 1999 payment, and was late making the payments due in October, November and December of 1999. Berry missed payments in January and February of 2000.

8. On February 7, 2000, the Underlying Lawsuit proceeded to trial before Magistrate Pat Sheeran, and on February 10, 2000, Magistrate Sheeran issued his report awarding damages in favor of Millstone Development in the amount of $55,499, plus prejudgment interest in the amount of $12,024.78. The total judgment in favor of Millstone Development was $67,523.78. Judge Beverly Pfeiffer adopted Magistrate Sheeran's report and entered judgment in favor of Millstone Development on March 8, 2000. Copies of Magistrate Sheeran's report and Judge Pfeiffer's Judgment were introduced as Exhibits 11A and 11B, respectively.

9. Terry Connor ("Connor") provided testimony concerning his efforts to collect on Millstone Development's judgment. It is clear that Berry was evading the collection efforts of Millstone Development, and was taking steps to hide his assets and transfer his assets for purposes of avoiding collection. Berry's evasive efforts continue through today inasmuch as he falsely represented to Roy Cline that he was not Jim Berry for purposes of avoiding service of the subpoenas that Millstone Development issued to him and his wife, Kathleen Hart, for their attendance at this trial.

10. This Court finds that Berry was insolvent as of February 29, 2000. This Court makes this finding based upon all of the evidence produced at trial, including the bankruptcy filings filed by Berry, Berry's evasive actions to avoid collection, Berry's evasive actions to avoid appearing before this Court , and the fact that Berry was not paying his debts as they became due. Under Ohio Revised Code § 1336.02(A)(2), a debtor who is not paying his debts as they become due is presumed to be insolvent. There was no evidence produced at the trial rebutting this presumption, and all of the evidence produced at trial indicated that Berry was insolvent in that his debts were greater than all of his assets at their fair valuation.

11. Expert witness Terry Watson provided expert testimony concerning the value of the Property as of February 29, 2000. That evidence was unrebutted.

Free access — add to your briefcase to read the full text and ask questions with AI

Millstone Dev. v. Berry, Unpublished Decision (5-9-2002), (Ohio Ct. App. 2002).

Millstone Dev. v. Berry, Unpublished Decision (5-9-2002) (Millstone Dev. v. Berry, Unpublished Decision (5-9-2002)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

South Union, Ltd. v. George Parker & Associates, AIA, Inc.
504 N.E.2d 1131 (Ohio Court of Appeals, 1985)
State v. Dehass
227 N.E.2d 212 (Ohio Supreme Court, 1967)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Cohen v. Lamko, Inc.
462 N.E.2d 407 (Ohio Supreme Court, 1984)
State v. Martin
483 N.E.2d 1157 (Ohio Supreme Court, 1985)
State v. Sage
510 N.E.2d 343 (Ohio Supreme Court, 1987)
Basil v. Vincello
553 N.E.2d 602 (Ohio Supreme Court, 1990)
Myers v. Garson
614 N.E.2d 742 (Ohio Supreme Court, 1993)
State v. Coleman
707 N.E.2d 476 (Ohio Supreme Court, 1999)
State v. Robb
88 Ohio St. 3d 59 (Ohio Supreme Court, 2000)