306 Ga. 6 FINAL COPY
S18G0876, S18G1107. MILLIKEN & COMPANY v. GEORGIA POWER COMPANY (two cases).
WARREN, Justice.
In 2013, a small business jet crashed into a Georgia Power
Company transmission pole on Milliken & Company’s property near
the Thomson-McDuffie Regional Airport in Thomson, Georgia. The
two pilots were injured and the five passengers died. In the wake of
the crash, the pilots and the families of the deceased passengers filed
a total of seven lawsuits against multiple defendants, including
Georgia Power and Milliken. The complaints in those seven suits
alleged that a transmission pole located on Milliken’s property was
negligently erected and maintained within the airport’s protected
airspace. The record evidence shows that Georgia Power
constructed the transmission pole on Milliken’s property for the
purpose of providing electricity to Milliken’s manufacturing-plant
expansion, and that the pole was constructed pursuant to a 1989 Easement between Georgia Power and Milliken. In each of the
seven suits, Milliken filed identical cross-claims against Georgia
Power, alleging that Georgia Power was contractually obligated to
indemnify Milliken “for all sums that Plaintiffs may recover from
Milliken” under Paragraph 12 of the 1989 Easement, which
provides:
[Georgia Power] Company, its successors or assigns shall hold [Milliken], its successors or assigns harmless from any damages to property or persons (including death), or both, which result from [Georgia Power] Company’s construction, operation or maintenance of its facilities on said easement areas herein granted.
Georgia Power moved for summary judgment on the cross-
claims. The trial court granted summary judgment to Georgia
Power in all seven actions, reasoning that Paragraph 12 of the 1989
Easement operates as a covenant not to sue, rather than as an
indemnity agreement, because it “nowhere contains the word
‘indemnity’” and “it is not so comprehensive regarding protection
from liability.” All seven cases were appealed to the Court of Appeals.1
Case No. S18G0876
The Court of Appeals affirmed the trial court’s grant of
summary judgment in favor of Georgia Power in the six cases
underlying our Case No. S18G0876. Milliken & Co. v. Ga. Power
Co., 344 Ga. App. 560 (811 SE2d 58) (2018). In its opinion, the Court
of Appeals did not rely on the trial court’s rationale that the 1989
Easement provision was a covenant not to sue. Id. at 564. Instead,
employing a “right for any reason” approach, it held that the
provision was an indemnity agreement and affirmed the trial court
by applying Georgia’s anti-indemnity statute, OCGA § 13-8-2 (b), to
determine that Paragraph 12 of the Easement was “void as against
public policy” — a theory argued before the trial court but not argued
or briefed before the Court of Appeals. Milliken & Co., 344 Ga. at
1 Six of the seven cases were consolidated on appeal and underlie our
Case No. S18G0876. The remaining case had been dismissed and refiled below, which led to a trial court order disposing of that case later than the other cases (although the order did so for the same reasons). As a result, that case was appealed after a new term of the Court of Appeals had begun and is the sole case underlying our Case No. S18G1107, which we discuss at the end of this opinion. 562-564. To support its holding, the Court of Appeals quoted the
pleadings filed in support of Milliken’s cross-claims, which alleged
that “Georgia Power is contractually liable to Milliken ‘for all sums
that Plaintiffs may recover from Milliken.’” Id. at 561 (emphasis
supplied). Reasoning that “Milliken’s cross-claims against Georgia
Power are necessarily based on the contention that the easement
provision at issue makes Georgia Power contractually liable to
indemnify Milliken for any damages that the plaintiffs recover
against Milliken caused solely by Milliken’s negligence,” id. at 564,
the Court of Appeals concluded that “assuming the easement
provision requires the contractual indemnity alleged in Milliken’s
cross-claims, the provision makes Georgia Power liable to indemnify
Milliken for damages caused solely by Milliken’s negligence and is
void and unenforceable as against public policy as provided in OCGA
§ 13-8-2 (b).” Id. (emphasis supplied).
We granted Milliken’s petition for certiorari and posed a single
question: Did the Court of Appeals err in its construction and
application of OCGA § 13-8-2 (b)? Because our answer to that question is yes, we vacate the Court of Appeals’ judgment and
remand the case for the Court of Appeals to consider, in the first
instance, the trial court’s rationale for granting Georgia Power’s
motions for summary judgment and any other arguments properly
before the Court of Appeals.
1. On appeal from a grant of summary judgment, we review
legal questions de novo and review the evidence in the light most
favorable to the nonmoving party to determine whether there is a
genuine issue of material fact. Barnett v. Caldwell, 302 Ga. 845,
845-846 (809 SE2d 813) (2018).
“As a general rule[,] a party may contract away liability to the
other party for the consequences of his own negligence without
contravening public policy, except when such agreement is
prohibited by statute.” Lanier at McEver v. Planners and Engineers
Collaborative, 284 Ga. 204, 205 (663 SE2d 240) (2008) (citation and
punctuation omitted). When the easement at issue here was
executed, OCGA § 13-8-2 (b) provided one such public-policy
limitation: A covenant, promise, agreement, or understanding in or in connection with or collateral to a contract or agreement relative to the construction, alteration, repair, or maintenance of a building structure, appurtenances, and appliances, including moving, demolition, and excavating connected therewith, purporting to indemnify or hold harmless the promisee against liability for damages arising out of bodily injury to persons or damage to property caused by or resulting from the sole negligence of the promisee, his agents or employees, or indemnitee is against public policy and is void and unenforceable . . . .
(Emphasis supplied.)2 In analyzing the text of OCGA § 13-8-2 (b),
we have explained that an indemnification provision is void if it “(1)
relate[s] in some way to a contract for ‘construction, alteration,
repair, or maintenance’ of certain property and (2) promise[s] to
indemnify a party for damages arising from that own party’s sole
negligence.” Kennedy Dev. Co. v. Camp, 290 Ga. 257, 259 (719 SE2d
442) (2011) (emphasis supplied).3
(a) Against this backdrop, we turn to the 1989 Easement and
2 Several amendments that are not relevant to our decision have been
made to OCGA § 13-8-2 (b) over the years.
3 In Kennedy, we analyzed another version of OCGA § 13-8-2 (b), but
given that former OCGA § 13-8-2 (b) is materially the same, the analysis in Kennedy also applies here. evaluate it under former OCGA § 13-8-2 (b). With respect to the first
of the two conditions contained in former OCGA § 13-8-2 (b), the
1989 Easement that contains Paragraph 12 also gave Georgia Power
a right-of-way to
construct, erect, install, operate, maintain, inspect, reconstruct, repair, rebuild, renew and replace thereon a substation and overhead and underground electric transmission, distribution and communication lines, with necessary or convenient towers, frames, poles, wires, manholes, conduits, transformers, switches, breakers and communication equipment, with the necessary wires, fixtures, appliances, protective wires and devices, buildings, sewers, drains, fences and other facilities in connection therewith . . . including the right . . . to clear, grade, fill, excavate, ditch and drain said substation tract[.]
This language relates “to the construction, alteration, repair,
or maintenance of a building structure, appurtenances, and
appliances, including moving, demolition, and excavating connected
therewith.” Former OCGA § 13-8-2 (b). See, e.g., Newton’s Crest
Homeowners’ Assn. v. Camp, 306 Ga. App. 207, 216 (702 SE2d 41)
(2010) (first condition met where “[a]lthough [indemnitor] did not
actually construct any buildings on the subdivision property, its work on the property consisted of, among other things, clear-cutting
and grading the land, installing utility lines, and putting in
streets”); see also Kennedy, 290 Ga. at 259 (noting that with respect
to the first condition, Georgia courts have “consistently construed”
the statute “broadly”). Moreover, Milliken admits that the 1989
Easement was requested in order to provide the electricity needed
to facilitate Milliken’s own construction of an addition to its new
manufacturing plant in 1989. In other words, it is “relative to the
construction, alteration, repair, or maintenance of a building
structure, appurtenances, and appliances,” as the statute requires.
Given that Georgia courts have “consistently construed” OCGA § 13-
8-2 (b) “broadly,” we conclude that the terms of the 1989 Easement
satisfy the first condition of former OCGA § 13-8-2 (b).
(b) The question then becomes whether Paragraph 12 — i.e.,
the indemnity provision in the 1989 Easement — satisfies the
second condition contained in former OCGA § 13-8-2 (b). The statute
prohibits “covenant[s], promise[s], or understanding[s]” made in
connection with, or collateral to, contracts or agreements satisfying the first condition and “purporting to indemnify or hold harmless
the promisee against liability for damages arising out of bodily
injury to persons or damage to property caused by or resulting from
the sole negligence of the promisee, his agents or employees, or
indemnitee.” Former OCGA § 13-8-2 (b) (emphasis supplied). In
contrast to the statute, the plain terms of Paragraph 12 require
Georgia Power to hold Milliken harmless from “any damages to
property or persons . . . which result from [Georgia Power]
Company’s construction, operation or maintenance of its facilities on
said easement areas herein granted.” (Emphasis supplied.)
Paragraph 12, then, indemnifies Milliken for damages resulting
from Georgia Power’s acts or omissions, whereas the statute would
prohibit an agreement that provides indemnity for damages
resulting from Milliken’s sole negligence. In short, Paragraph 12,
and thus the 1989 Easement, do not do that which the statute
prohibits.
Looking beyond the plain terms of the indemnity provision and
relying on the Court of Appeals’ reasoning below, Georgia Power argues that Paragraph 12 is void under OCGA § 13-8-2 (b) because
“as set forth in Milliken’s cross-claims, Milliken sought
indemnification from Georgia Power for ‘all sums that Plaintiff may
recover from Milliken.’” See Milliken & Co., 344 Ga. App. at 561-
562.4 To support this argument, Georgia Power cites cases holding
4 To the extent Georgia Power looks to the plain terms of Paragraph 12,
its primary argument is that the “any damage to property or person” language contained in that provision violates former OCGA § 13-8-2 (b) — but only when that language is read “in conjunction with” the language of Milliken’s cross- claims. For the reasons described below, that reading is no different than analyzing the text of Paragraph 12 alone. Georgia Power also argues that the phrase “any damages” in Paragraph 12 is an “all or nothing proposition” and therefore violates former OCGA § 13- 8-2 (b). Citing Frazer v. City of Albany, 245 Ga. 399 (265 SE2d 581) (1980), Georgia Power argues that even if Paragraph 12 requires indemnification for claims of Milliken’s concurrent negligence, “then it also purports to include claims for Milliken’s sole negligence because Paragraph 12 does not have the required carve out for Milliken’s sole negligence.” But the relevant provisions at issue in Frazer, unlike Paragraph 12, purported to indemnify or hold harmless an indemnitee without limitation, and therefore could have been construed as including claims of the indemnitee’s sole negligence. See Frazer, 245 Ga. at 401-402 (referencing one lease provision that provided that the “City shall indemnify and [hold the indemnitee harmless] against and from all claims by and on behalf of any person, firm or corporation arising from the contract or management or from any work or thing done on the project during the Lease term” and another in which the City held the indemnitee “harmless against any loss or damage to property, or any injury to or death of any person that may be occasioned by any cause whatsoever pertaining to the project or the use thereof.” (emphasis supplied and in original)). As explained above, Paragraph 12 contains language that limits its application to instances of “any damages . . . which result from [Georgia Power] Company’s construction, operation or maintenance of its facilities.” To the extent Milliken’s sole that indemnity provisions purporting to indemnify an indemnitee’s
sole negligence are invalid under OCGA § 13-8-2 (b). See, e.g.,
Kennedy, 290 Ga. at 258 (indemnity for “any and all . . . debts,
claims, actions, damages, judgments or costs . . . related to the
construction, maintenance, repair, or operation” of project, without
limitation based on who is at fault (punctuation omitted)); Lanier,
284 Ga. at 205-208 (indemnity for “any and all claims, losses, costs,
damages of any nature whatsoever [and] . . . any and all liability or
cause of action however alleged or arising, unless otherwise
prohibited by law,” without limitation based on who is at fault
(punctuation omitted)); Frazer v. City of Albany, 245 Ga. 399, 402
(265 SE2d 581) (1980) (indemnity for “all claims . . . arising from . .
. any work or thing done on the project [and] . . . any loss or damage
to property, or any injury to or death of any person that may be
occasioned by any cause whatsoever pertaining to the project or the
use thereof,” without limitation based on who is at fault
negligence is ever the cause of the relevant damages, then Paragraph 12 would not apply. (punctuation and emphasis omitted)); Nat. Candy Wholesalers, Inc.
v. Chipurnoi, 180 Ga. App. 664, 665-666 (350 SE2d 303) (1986)
(indemnity for “any claim by any of the exhibitor’s agents or
employees for injury, loss or damage,” without further limitation
(punctuation omitted)); Big Canoe Corp. v. Moore & Groover, Inc.,
171 Ga. App. 654, 655 (320 SE2d 564) (1984) (indemnity for “all
claims, suits, damages, costs, losses and expenses arising from
injury to any person, persons or property occurring on or about the
said premises and relating to the performance of this Agreement,”
without limitation based on who is at fault (punctuation omitted)).
In particular, Georgia Power points to our holding in Kennedy Dev.
Co. v. Camp that an assignment provision was invalid under OCGA
§ 13-8-2 (b) because it contained language “to the effect that a party
will indemnify and hold harmless the other party as to ‘any’ or ‘all’
claims, damages, losses, injuries, or the like arising from the subject
of the parties’ contractual relationship, ‘no matter the origin of the
claim or who is at fault,’” 290 Ga. at 260 (emphasis supplied), and
argues that it is analogous to the “all sums that Plaintiffs may recover from Milliken” language contained in Milliken’s cross-
claims, which arguably would include damages resulting from
Milliken’s sole negligence.
This argument is viable if we look only to, and rely only upon,
the pleadings filed in support of Milliken’s cross-claims and ignore
the plain terms of the indemnity provision contained in the 1989
Easement. Yet the allegations lodged in Milliken’s cross-claims
cannot and do not alter the language contained in Paragraph 12, and
therefore cannot cause Paragraph 12 to violate former OCGA § 13-
8-2 (b). Indeed, as the title and language of that statute state,
former OCGA § 13-8-2 (b) concerns what renders a contract or
agreement void as against public policy, and specifically concerns
what “[a] covenant, promise, agreement, or understanding in or in
connection with or collateral to a contract or agreement” purports to
require. Former OCGA § 13-8-2 (b). It is therefore the language of
the contract or agreement itself, and not other extraneous language
(including Milliken’s cross-claims) characterizing or making
demands pursuant to it, that must be analyzed under the statute. See Ga. Ports Auth. v. Central of Ga. R. Co., 135 Ga. App. 859, 862
(219 SE2d 467) (1975) (the question of liability for indemnification
is determined “in accordance with the terms of the agreement”).
So understood, Paragraph 12 of the 1989 Easement between
Milliken and Georgia Power plainly does not satisfy the second
condition contained in former OCGA § 13-8-2 (b), and therefore does
not violate public policy. That is because Paragraph 12 applies only
to damages “which result from [Georgia Power] Company’s
construction, operation or maintenance of its facilities” on the
easement area. That language necessarily limits the indemnity to
damages “result[ing] from” Georgia Power’s acts or omissions and
necessarily excludes instances in which Georgia Power has not in
any way caused the damages. In other words, indemnification
applies only in those cases where damages “result from” Georgia
Power’s “construction, operation or maintenance of its facilities on
[the] easement areas,” whether those damages result from Georgia Power in whole or in part.5 This interpretation is consistent with
Georgia law; indeed, Georgia appellate courts have upheld or cited
with approval indemnity agreements that contained language
stating that, for example, indemnification would apply to losses
“arising out of” the indemnitor’s negligence, even when it was
possible for the provision to apply to the indemnitor’s full or partial
negligence. See, e.g., Lawyers Title Ins. Corp. v. New Freedom Mtg.
Corp., 285 Ga. App. 22, 29-30 (645 SE2d 536) (2007) (explaining that
“where, as here, an indemnification clause requires indemnification
of losses that ‘arise out of’ certain specified events but does not
explicitly mention the indemnitee’s negligence, the clause still
requires full indemnification although the indemnitee’s negligence
may have partially caused the loss”); Binswanger Glass Co. v. Beers
Constr. Co., 141 Ga. App. 715, 717-718, n. 1 (234 SE2d 363) (1977)
(upholding agreement that indemnitor contractor indemnify owner
5 Practically speaking, that means that indemnification could potentially
apply in certain instances where the combined negligence of Georgia Power and Milliken or even Georgia Power and other entities results in damages. But none of those scenarios would implicate the statute’s prohibition on indemnification for an indemnitee’s “sole negligence.” “from and against all claims, damages, losses and expenses
including attorneys’ fees arising out of or resulting from the
performance of the Work, provided that any such claim, damage,
loss or expense . . . is caused in whole or in part by any negligent act
or omission of the Contractor” or anyone whose acts the contractor
may be liable for, “regardless of whether or not it is caused in part
by a party indemnified hereunder” (punctuation omitted; emphasis
supplied)).
The agreements examined in those cases, like the indemnity
provision contained in Paragraph 12, avoided OCGA § 13-8-2 (b)’s
prohibition because they did not require indemnification when
damages were caused solely by the indemnitee’s negligence.6 And
6 Georgia Power does argue that any negligence by Milliken could only
be sole negligence in this case, and that Paragraph 12 must therefore be void under former OCGA § 13-8-2 (b). That argument goes like this: In addition to the 1989 Easement with Georgia Power, Milliken also had a 1973 Aviation Easement with the City of Thomson and McDuffie County that required Milliken to keep the airspace above its property clear for the airport’s use. Pointing to Plaintiffs’ allegations that the duty imposed by this 1973 Aviation Easement was non-delegable, Georgia Power suggests that by permitting Georgia Power to erect the transmission pole in the airspace protected by that easement, Milliken was solely negligent for the plane crash. The 1973 Aviation Easement, however, makes no mention of any duty there can be no indemnification for Milliken’s sole negligence here
because under that circumstance, none of the damages would have
resulted from Georgia Power’s construction, operation, or
maintenance of its facilities, as is required for Paragraph 12 to
apply. Thus, as a matter of contractual interpretation and as a
matter of common sense, Milliken’s “sole negligence” would not fall
within the indemnity provision’s language, because that language
limits the indemnity to damages caused, at least in part, by Georgia
Power. Indeed, if Milliken’s negligence contributed to damages also
caused by Georgia Power’s negligence, then it would not be “sole
negligence”; it would be combined or joint negligence, and thus
would not implicate former OCGA § 13-8-2 (b).
Contrary to Georgia Power’s contention, the indemnity
provision here does not purport to require Georgia Power to hold
being non-delegable, and Georgia Power points to no authority — either in statute or case law — supporting that proposition. Moreover, Plaintiffs’ complaints, in addition to alleging that Milliken was negligent in failing to keep the airspace above its property clear in accordance with the 1973 Aviation Easement, also allege that Georgia Power was separately negligent in its design and construction of the transmission line. Milliken harmless for “any damages” without limitation. Paragraph
12’s textual parameters, which limit indemnification to damages
resulting from Georgia Power’s negligence, distinguish the 1989
Easement from the indemnity agreements that have been
invalidated in other cases for purporting to require indemnity for
“any damages” or “all claims,” without limitation — or at least
without limitation to indemnitor or third-party negligence. See, e.g.,
Kennedy, 290 Ga. at 258; Lanier, 284 Ga. at 205-208; Frazer, 245 Ga.
at 402; Chipurnoi, 180 Ga. App. at 665-666; Big Canoe Corp., 171
Ga. App. at 655. Accordingly, because the indemnity agreement
does not meet both of the conditions set forth in OCGA § 13-8-2 (b),
the agreement is not void as against public policy, and the Court of
Appeals therefore erred by affirming the trial court’s grant of
summary judgment on that ground. On remand, the Court of
Appeals should address the other arguments raised by the parties,
on which we express no opinion.7
7 Georgia Power moves this Court to supplement the record to add a
defense verdict in favor of Milliken in one of the six cases (McCorkle v. Ga. Case No. S18G1107
One month after the opinion in Milliken & Co., 344 Ga. App.
560, was issued, a separate panel of the Court of Appeals issued an
unpublished “Rule 36” order summarily affirming the trial court in
the single case that is now our Case Number S18G1107. Milliken &
Co. v. Ga. Power Co., 345 Ga. App. XXII (Case No. A18A0516)
(March 26, 2018) (unpublished). Rule 36 allows the Court of Appeals
to affirm cases without opinion if: “(1) [t]he evidence supports the
judgment; (2) [n]o reversible error of law appears and an opinion
would have no precedential value; (3) [t]he judgment of the court
below adequately explains the decision; or (4) [t]he issues are
controlled adversely to the appellant for the reasons and authority
given in the appellee’s brief.” Court of Appeals Rule 36. Notably, in
its order, the Court of Appeals cited three of the grounds
Power Co., Civil Action No. 15EV000163D (Fulton County State Ct. 2015)) that is a part of this consolidated appeal because “the McCorkle portion of this appeal is moot and should be dismissed.” We leave it to the Court of Appeals on remand to determine if the appeal in that one case is moot and, if so, whether it should be dismissed. enumerated in Rule 36 but omitted one: “[t]he judgment of the court
below adequately explains the decision.” As a result, the Court of
Appeals neither affirmed nor rejected the trial court’s reasoning that
Paragraph 12 of the 1989 Easement was merely a “covenant not to
sue” and was not a “full indemnity agreement.” Therefore, in
accordance with our ruling in Case no. S18G0876, the Rule 36 order
appealed from in Case no. S18G1107 is also vacated and that case
also remanded for further proceedings consistent with this opinion.
Judgments vacated and cases remanded. All the Justices
concur, except Ellington, J., disqualified. Decided June 3, 2019.
Certiorari to the Court of Appeals of Georgia — 344 Ga. App.
560 and 345 Ga. App. XXII (Case no. A18A0516) (unpublished).
Drew Eckl & Farnham, Stevan A. Miller, Lisa R. Richardson;
Holland & Knight, Matthew D. Friedlander, Laurie W. Daniel, Phil
George, for appellant.
Tucker, Everitt, Long, Brewton & Lanier, Benjamin H.
Brewton; Balch & Bingham, Hugh B. McNatt, M. Anne Kaufold-
Wiggins, Brooke W. Gram, Tyler P. Bishop; Weinberg, Wheeler,
Hudgins, Gunn & Dial, David A. Dial, Carol P. Michel, Thomas J.
Strueber, for appellee.