Milliken Bros. v. City of New York

135 A.D. 598, 120 N.Y.S. 841, 1909 N.Y. App. Div. LEXIS 4024
CourtAppellate Division of the Supreme Court of the State of New York
DecidedDecember 31, 1909
StatusPublished
Cited by3 cases

This text of 135 A.D. 598 (Milliken Bros. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milliken Bros. v. City of New York, 135 A.D. 598, 120 N.Y.S. 841, 1909 N.Y. App. Div. LEXIS 4024 (N.Y. Ct. App. 1909).

Opinions

Ingraham, J.:

This was an action to foreclose a mechanic’s lien upon the. amount due by the city of New York to its contractor, the James D. [600]*600Murphy Company, who was building under a contract with the city of New York the Sixty-ninth Regiment armory. The defendants appellants interposed answers setting up certain- mechanics’ liens which they claimed to have filed against the amounts due by the city to the Murphy Company. The court dismissed the claims of these defendants appellants upon the ground that their liens were not filed in time, and from the judgment entered thereon these appellants appeal. The facts as' found by the trial judge are as follows : On the 26th day of January, 1904, the defendant James D. Murphy Company entered into a contract with the city of New York by the armory board for the erection and completion of an armory building in the city of New York in pursuance of certain plans and specifications in said contract for. the sum of $619,522.-33. This contract provided that the action of the architect by which the contractors were to be bound and concluded according -to the terms of the contract should be that evidenced by their final certificate; that the Murphy Company entered upon the performance of its contract ; that the time within which the said contract was to be completed was extended to and included the 8th day of October, 1906; that the said contract was substantially completed on the 8th day of October, 1906'; that on said day the architects named in said contract delivered to the city of New York through the armory board their final certificate in connection with the completion of the work mentioned in ■ the said contract, and filed with the armory board a certificate to the effect that the contractor, James D. Murphy Company, was entitled to payment of the amount remaining unpaid on its contract, to wit, $96,091.24, less the sum of $2,000 to be retained as a guaranty under the provisions of the contract and less the further sum of $1,000 to be retained for uncompleted work; that thereafter the board of armory commissioners of the city of New York issued its certificate to the general effect as the certificate of the architects for the payment of $93,091.24 and for the retaining of $1,000 on account of uncompleted work, and the further;sum of $2,000 in accordance with the contract; that on the 8th day of' October, 1906, the armory board adopted a resolution accepting the Sixty-ninth Regiment armory from the .contractors as completed with the reservation named in the resolution ; and the comptroller was authorized to pay to James D. Murphy Company the sum of [601]*601$93,091.24 for the execution of their contract for the erection of the Sixty-ninth Regiment armory, being the payment in full with a reservation therefrom of $1,000 until the marble tablet was properly installed, and a further reservation of $2,000 as provided in the contract for one year from the date of the issuance of the final certificate as a guaranty for the perfect working and efficiency of the steam heating apparatus; and that the roofs of the buildings should be made tight and any defects which might appear in the entire work remedied, and that these certificates were delivered to the proper official of the city of New York; that subsequently and on November 17, 1906, an assistant - engineer in the comptroller’s, office reported that the work was completed in a satisfactory manner, excepting the electric wiring and connections; that there were several serious defects in this electric work which would take several / weeks to remedy, and the engineer, therefore, recommended that $90,000 be paid the claimants at that time and that $3,091.24 be retained until such time as the defective work should have been made good. Acting upon this report the auditing bureau of the department of finance of the" city of New York refused to audit the claim of the defendant Murphy Company for the sum of $93,091.24 and withheld from the said sum the sum of $3,091.24 on account of the uncompleted and defective electrical wii’ing of the said building and until the same should be completed in accordance with the contract, and audited the claim of the defendant Jamos D. Murphy Company for the sum of $90,000; that on or about the 1st day of March, 1907, the comptroller paid to the Fourteenth Street Bank as assignee of the "Murphy Company on account of said contract the said sum of $90,000 ; that the marble tablet referred to in the resolution of the armory board was properly installed by the Murphy Company shortly, after the 8th day of October, 1906, and immediately thereafter the Sixtv-ninth Regiment of the New York National Guard entered into occupancy of the said building. The court further found that on October 8,1906, certain plumbing work required by the contract between the Murphy Company and the city, of New York to be done upon the said armol-y building was uncompleted, to wit, the installation of certain water lines over the ammunition rooms in said armory, and that subsequent to October 8, 1906, the Murphy Company caused said [602]*602water lines to be installed in the -building, and that said work was done during the month of November, 1906; that such plumbing work consisted of two or three-inch pipe; that the city of New ' York'still retains the sum of $6,091.24 out of the contract price, being $2,000 retained under the contract, $1,000 to cover the installation of the marble tablet mentioned in the resolution of the armory board of October 8, 1906 ; $3,091.24 to cover the • uncompleted electric work mentioned in the report of the engineer, dated November 17, 1906; that the notices of the alleged liens filed with the comptroller of the city of New York and the board of armory commissioners of the city'of New York by the defendants Jerome A. Jackson and others were not filed within .thirty days next after October 8,1906, the date of the completion by the defendant 'James D. Murphy Company of the work contemplated in its contract with the city of New York; that various sums of money'were deposited by the Fourteenth Street Bank, the assignee of the Murphy Company, with the comptroller of the city of New York to discharge the liens of the appellants Jackson, Koebling Construction Com-, pany and Baker, Smith & Co., and this action was commenced on the 20th day of December, 1906.

The court thus refused to give to these lienors any portion of the money on deposit with the comptroller, but gave to each of the appellants a personal judgment against the Murphy Company for the amount due under their contracts with the Murphy Company; and the appellants appeál from the judgment refusing to enforce their liens on the moneys on deposit with the comptroller. These liens were filed under section 12 of the Lien Law (Gen. Laws, chap. 49 [Laws of 1897, chap. 418], as amd. by Laws of 1902, chap, 37; since amd. by Laws of 1908, chap. 85, and re-enacted in Consol. Laws, chap. 33; Laws of 1909, chap. 38), which provides that “ at any time before the construction of a public' improvement is completed and accepted by the State, or by the. municipal corporation, and within thirty days after such completion and.acceptance, a person performing work for, or furnishing materials to, a contractor, his sub-contractor, assignee or legal representative, may file a notice of lien.” The Lien Law provides for two classes of liens, one a lien in favor of one who performs labor or furnishes materials for the improvement of real property with the consent or at the request of the' owner thereof, [603]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milliken Bros. v. City of New York
156 A.D. 930 (Appellate Division of the Supreme Court of New York, 1913)
Berger Manufacturing Co. v. City of New York
67 Misc. 636 (New York Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
135 A.D. 598, 120 N.Y.S. 841, 1909 N.Y. App. Div. LEXIS 4024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milliken-bros-v-city-of-new-york-nyappdiv-1909.