Miller v. William A. Smith Constructing Co.

603 P.2d 602, 226 Kan. 172, 1979 Kan. LEXIS 306
CourtSupreme Court of Kansas
DecidedJuly 14, 1979
Docket49,588
StatusPublished
Cited by11 cases

This text of 603 P.2d 602 (Miller v. William A. Smith Constructing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. William A. Smith Constructing Co., 603 P.2d 602, 226 Kan. 172, 1979 Kan. LEXIS 306 (kan 1979).

Opinion

The opinion of the court was delivered by

Fromme, J.:

The Court of Appeals in an unpublished opinion affirmed the district court’s judgment in this case holding all claims were barred by the three-year statute of limitations, K.S.A. 60-512(1). This statute covers actions brought upon obligations not in writing. We granted review to consider whether the five-year statute of limitations, K.S.A. 60-511(1), should govern. K.S.A. 60-511(1) provides:

“The following actions shall be brought within five (5) years: (1) An action upon any agreement, contract or promise in writing.”

The defendant, William A. Smith Constructing Company, Inc., by its employees, R. H. Miller and D. E. Huncke, after certain *173 oral negotiations, submitted the following purchase order to Harold E. Miller d/b/a H. E. Miller & Sons Construction Company. It should be noted that the R. H. Miller who signed the purchase order had no connection with the latter company. The purchase order was as follows:

“To H. E. Miller & Sons Constr Co.
5801 Outlook
Shawnee Mission, Kansas
Date 10 August, 1971
Terms Net 30 Days
F.O.B. Job Site
Ship Via Your Truck
Rental of Equipment listed below, for work at Mission Lumber Co. 119th St. & 1-35, as called for by our Mr. Hayes, starting about August 18, 1971
1 ea Case Backhoe - Loader 19.00/hr
1 ea 6Y2 cy tandem dump truck 15.00/hr
Thurs Morning 8:00 a.m.
371-8184
8-25-71
WM. A. SMITH CONTRACTING CO., INC. Charge Job # 468
1401 Fairfax Twy
Kansas City, Kas. 66115
Signed R.H. Miller Title
Approved D. E. Huncke Project Manager.”

Under this agreement the equipment was furnished to the defendant on six separate days and on completion of the work the plaintiff submitted an itemized statement indicating a total of $1,496.00 was due under the agreement. More than three but less than five years passed before the present action was filed.

The plaintiff asserts that the writing is sufficient to constitute a promise in writing as required by K.S.A. 60-511(1) which limits such actions to a period of five years. Plaintiff argues that the purchase order and billing statement contain all essential terms of the contract between the parties. Nothing more is needed for the court to arrive at the terms and conditions of the agreement.

Defendant asserts that parol evidence is necessary to determine the contractual terms and that the writings do not contain all essential elements of the contract. Although defendant does not specifically state which contractual terms are not in writing, his reliance on Fairbanks v. Koelling, 167 Kan. 361, 205 P.2d 930 (1949), infers that he contends a written promise to pay is missing. In Fairbanks the writing relied on was as follows:

*174 “ ‘Emmett, Kansas
“ ‘January 21, 1944
“ ‘Bought of Lloyd Fairbanks 4 stacks alfalfa, 2 first 2 second cuttings about 35 tons at $19.50 per ton in stack — 2 stacks brown alfalfa about 15 ton at $13.00 per ton in. stack. $25.00 check as down payment.
“ ‘C.H. Koelling
“ ‘707 West 17
“ ‘2-8145
“ ‘Topeka’ ”

Syllabus.

It is noted in Fairbanks the date of the agreement was given, the parties were named, the alfalfa purchased was specified, the prices were set forth, and the receipt of a check as down payment was acknowledged. The court in Fairbanks held, however, that the instrument was insufficient to be entitled to the protection of the five-year statute. The writing omitted any promise to pay on a day certain. It would not be possible to determine when the statute of limitations would begin to run. The court pointed out, that in order to prove a claim under the writing, evidence would have to be introduced to establish an oral understanding by the parties as to the time and manner of payment.

The general rule is that a written agreement, contract or promise in writing which falls within the five-year statute of limitations, K.S.A. 60-511(1), must contain all its material terms in writing. A contract which is partly in writing and partly oral is in legal effect an oral contract so far as the statute of limitations may be concerned. The writing necessary to have the additional protection of the five-year statute must be full and complete in itself so as not to require proof of extrinsic facts to establish all essential contractual terms. Fey v. Loose-Wiles Biscuit Co., 147 Kan. 31, 75 P.2d 810 (1938); Annot., 3 A.L.R.2d 809, 813 (1949); 51 Am. Jur. 2d, Limitation of Actions § 94, p. 668; 53 C.J.S., Limitations of Actions § 60, p. 1018.

The writing need not, however, be signed by all parties, and where a writing containing all the essential terms of a contract is executed by the party to be charged and the contract is accepted and acted on by the other party the contract is one in writing for purposes of determining which statute of limitations applies. See Fey v. Loose-Wiles Biscuit Co., 147 Kan. at 34-36; 51 Am. Jur. 2d, Limitation of Actions § 94, p. 669.

*175 In the present case the purchase order was made up after oral discussions were completed between the parties. The writing identified the two parties to the agreement, the date of the writing, the nature of the equipment to be furnished, the prices to be paid, who was to transport the equipment to the job site, where it was to be delivered, and when payment was to be made (“Terms Net 30 Days”). In addition the writing was signed by and on behalf of the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zenda Grain & Supply Co. v. Farmland Industries, Inc.
894 P.2d 881 (Court of Appeals of Kansas, 1995)
Rupe v. Triton Oil & Gas Corp.
806 F. Supp. 1495 (D. Kansas, 1992)
Dow Chemical Corp. v. Weevil-Cide Co., Inc.
630 F. Supp. 125 (D. Kansas, 1986)
Chilson v. Capital Bank of Miami
701 P.2d 903 (Supreme Court of Kansas, 1985)
Chilson v. Capital Bank of Miami
692 P.2d 406 (Court of Appeals of Kansas, 1984)
Matherly v. Hanson
359 N.W.2d 450 (Supreme Court of Iowa, 1984)
Fingeret v. Retirement Board
475 A.2d 889 (Commonwealth Court of Pennsylvania, 1984)
Harvester, Inc. v. Goodyear Tire & Rubber Co.
606 P.2d 498 (Court of Appeals of Kansas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
603 P.2d 602, 226 Kan. 172, 1979 Kan. LEXIS 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-william-a-smith-constructing-co-kan-1979.