Miller v. Walsh County Water Resource District

2012 ND 152, 819 N.W.2d 526, 2012 WL 3031369, 2012 N.D. LEXIS 158
North Dakota Supreme Court·Decided July 26, 2012·No. No. 20120018·Published·Cited by 6 cases

Opinions

KAPSNER, Justice.

[¶ 1] John Miller and J.D. Miller Farming Association (collectively “Miller”) appeal from an order affirming the Walsh County Water Resource District’s decision requiring Miller to remove unpermitted dikes from his property located in Forest River Township. We affirm, concluding Miller has failed to establish that the District acted arbitrarily, capriciously or unreasonably, that there is not substantial evidence to support its decision, or that the District is estopped from requiring removal of the dikes.

I

[¶ 2] In 1955, approximately two years before the creation of a water resource district in Walsh County and the existence of permit requirements for dike construction, Miller’s father built dikes along the Forest River to protect his farmland from flooding. In early to mid 1996, Miller repaired and revised the dike system on the property. Miller’s work on the dikes prompted a complaint from an area resident which was sent to, among others, the State Water Commission, the District and Miller. The complainant requested in his July 14, 1996, letter that the dike system “be torn down in its entirety ... because if this dike system is allowed to stand for even one spring, the Forest River Community will forever be impacted.” On July 18, 1996, a state water resource engineer wrote to the District’s chairman referencing the complaint and stating “[w]e do not have a record of a dike construction permit issued in section 21, Forest River Township. It appears that a construction permit is required and should have been applied for before construction began.” At the time, a permit was required if a dike was capable of retaining, obstructing or diverting more than 12⅜ acre-feet of water. See N.D.C.C. § 61-16.1-38; 1985 N.D. Sess. Laws ch. 669, § 3. The engineer urged the District to investigate the complaint and informed it that “[a]n engineering analysis is necessary to determine the impact of the unpermitted dike on the city.” On July 18, 1996, the District’s chairman wrote to Miller advising him to “seize [sic] all work on the dike along the Forest River.”

[¶ 3] Randy Gjestvang, the Red River Water Resource Engineer, met with Miller and surveyed the property to obtain elevations of the dikes. In an October 16, 1996, letter to the District’s chairman, Gjestvang [529] revealed the results of his survey and said he found a “new dike.”

Aerial photos and on-site investigations were also used to attempt to determine the extent of any old dikes. Unfortunately, the old dike was apparently completely removed in some areas. For those areas, the soil was used for fill for the new dike that was realigned further from the river. In other areas, soil was placed along the same alignment as the old dike. The old dike was apparently very narrow, and partially falling into the river in some areas. According to the landowner, he was mainly attempting to strengthen the dike. He felt that he had matched the elevation of the old dike. He also said that the contractor had knocked down the top of the narrow dike, when widening the top of it. The contractor had also told us that they had made efforts to construct the new dike to the same elevation as the old one.

Gjestvang made several suggestions regarding appropriate dike elevations. The minutes of the District’s October 17, 1996 meeting state:

The Board met with Randy Gjestvang, SWC, and John Miller concerning the dike built around the city of Forest River. The W.C.W.R.D. and SWC requested Mr. Miller to make some changes to the dike. Mr. Miller was agreeable and will comply with all proposals. He said the work should be completed within a week. Randy Gjestvang will inspect then.

[¶ 4] In a February 11, 1997, letter to the District’s chairman, Gjestvang reported that he had inspected the additional work done to the dikes by Miller and found the work “was completed according to the guidelines provided.” He further noted “[t]he levees in Section 21 are not considered to be permitted. They remain with the same status as the majority of the dikes that exist along the Forest River in this area.” Also on February 11,1997, the complainant wrote to the District’s chairman stating he had spoken with Gjestvang and “I hereby withdraw my complaint.” The District took no further action on the matter.

[¶ 5] During the summer of 2010, Miller repaired part of the dike system that had been breached. In August 2010, another area landowner filed a dike complaint against Miller with the District. The landowner claimed Miller’s “unpermit-ted illegal dike system” was causing excessive river bank erosion and landscape damage to her property during high water events. After receiving the complaint, Miller had the dikes surveyed to make sure the elevations were the same as the elevations set by Gjestvang in 1996. In a letter dated November 9, 2010, the District informed Miller:

Upon investigation of the area and consulting with the ND State Water Commission the Walsh County Water Resource District has determined that the dike system has been constructed without obtaining a dike permit from the State. In 1990’s a State construction permit was required for projects capable of retaining, obstructing or diverting 12½ acre-feet of water. Therefore, the Walsh County Water Resource District Board is ordering that the dike system be removed in its entirety on or before November 30, 2010. If the dike system is not removed in its entirety by November 30, 2010, the Walsh County Water Resource District will cause the removal of the dike system and assess the cost thereof, or such portion as the Board shall determine, against your property.

[¶ 6] Miller requested a hearing and presented evidence that the current elevations of the dikes were at the same elevations set by Gjestvang in 1996. Following [530] the hearing, the District convened in a closed executive session with its attorney. The District ultimately determined Miller’s dike system did not have a permit as required by N.D.C.C. § 61-16.1-38, it was “capable of retaining, obstructing or diverting more than 50 acre-feet of water,” and ordered its removal under N.D.C.C. § 61-16.1-53 no later than September 1, 2011. The district court affirmed the District’s decision.

II

[¶ 7] Miller argues the District’s decision requiring him to remove the dikes is arbitrary, capricious and unreasonable.

[¶ 8] This Court has outlined the limited standard of review applicable to this type of case:

In an appeal from the decision of a local governing body under N.D.C.C. § 28-34-01, our scope of review is the same as the district court’s and is very limited. Our function is to independently determine the propriety of the decision, without according any special deference to the district court’s decision, and unless the Board acted arbitrarily, capriciously or unreasonably, or there is not substantial evidence to support the decision, it must be affirmed. A decision is not arbitrary, capricious or unreasonable if the exercise of discretion is the product of a rational mental process by which the facts and the law relied upon are considered together for the purpose of achieving a reasoned and reasonable interpretation.

Free access — add to your briefcase to read the full text and ask questions with AI

Miller v. Walsh County Water Resource District, 2012 ND 152, 819 N.W.2d 526, 2012 WL 3031369, 2012 N.D. LEXIS 158 (N.D. 2012).

2012 ND 152 (Miller v. Walsh County Water Resource District) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hoff v. City of Burlington
2025 ND 62 (North Dakota Supreme Court, 2025)
Mosler v. Gerace
Supreme Court of The Virgin Islands, 2024
Blume Construction, Inc. v. State ex rel. Job Service North Dakota
2015 ND 285 (North Dakota Supreme Court, 2015)
Estate of Hogen
2015 ND 125 (North Dakota Supreme Court, 2015)
Stenehjem, ex rel. v. National Audubon Society, Inc.
2014 ND 71 (North Dakota Supreme Court, 2014)