Miller v. United States

550 F. Supp. 669, 1 Cl. Ct. 1, 1982 U.S. Claims LEXIS 2314
United States Court of Claims·Decided October 19, 1982·No. 66-75·Published·Cited by 13 cases

Opinion

OPINION

COLAIANNI, Judge:

Plaintiff in this case has alleged a “taking” by the Government of a flowage and underflowage easement on farm property riparian to the Arkansas River in Perry County, Arkansas. Plaintiff’s complaint is that his land suffers increased flooding and duration of flooding as a result of the operation of the McClellan-Kerr Arkansas River Navigation System. He further maintains that the project has raised the ground water table under his land and that he is consequently unable to machine farm parts of the land.

A trial was held on the issue of liability and I concluded that defendant’s actions resulted in a compensable “taking” under the fifth amendment. On June 14, 1978, a recommended decision and findings of fact were submitted to the court to that effect. *671 In response to exceptions by defendant, the court, by order of November 21, 1979, remanded the case back to the trial division for additional findings of fact on specific questions which the court deemed necessary for a determination of the case.

Following the remand and pursuant to order, a pretrial conference was held to determine if a trial would be necessary to answer the court’s questions. As a result of the conference, the parties stipulated responses to questions 1^4 of the November 21st order. These stipulations were contained in a “Memorandum Re Pretrial Conference,” dated April 7, 1981. Thereafter, in a further effort to respond to additional questions, the parties stipulated answers to the court’s questions (a), (b) and (c). The stipulation regarding the latter questions was accepted on August 19, 1981, in open court.

One question of fact remained to which the parties were unable to stipulate an answer. Thus, on August 19,1981, a trial was held in Little Rock, Arkansas, to hear testimony and receive exhibits on this final issue.

When this case was remanded, it was deemed to have been remanded for a resolution of only those specific factual questions detailed in the court’s order of November 21, 1979. Accordingly, no additional recommended opinion was to have been proposed to the court by the trial judge. However, with the implementation of the Federal Courts Improvement Act of 1982 and the resulting dissolution of the Court of Claims and the creation of the new Claims Court, this has changed.

As of October 1,1982, the trial division of the Court of Claims became the United States Claims Court. With this change, the new Claims Court judges were charged with the responsibility of reaching final decisions in cases brought before the court. The former Court of Claims judges have become appellate judges of the new Court of Appeals for the Federal Circuit, and their duties include hearing appeals from final judgments rendered by the Claims Court. Because of these changes, it is incumbent upon me to do more than simply refer the findings of fact and conclusions of law to the new appellate court in answer to the particular questions included in the remand order from the former Court of Claims judges; I must now reach a decision as to the issues not already resolved and render a final judgment in this case.

Therefore, based on a review of the entire record, including the conclusions of law contained in the remand order, the stipulations of the parties, and the additional evidence received at trial, I have concluded that there has been no taking in this case, and that plaintiff is thus not entitled to compensation for the flooding of his property-

Background

A portion of the facts contained in the June 14, 1978, opinion, useful to the understanding of the decision on remand, are set forth here again as background.

Plaintiff, in 1936, became the owner of a 1,834-acre tract of land in Perry County, Arkansas. This tract (hereinafter, the “property”) was at one time located within a northward loop of the Arkansas River. The Arkansas River was highly unstable in its natural state. Because of its heavy sediment load, it presented serious impediments to navigation. The river could overnight change from a mere trickle of water to a rushing torrent, change its course, and destroy improvements along its banks.

During the late forties, erosion transformed plaintiff’s property into a peninsula delimited by a “horseshoe” bend of the Arkansas, and reduced his acreage to between one-third and one-half of its original size. The Corps of Engineers (hereinafter the “Corps”) became concerned, as they expected that the river would soon cut itself a new channel across the neck of the peninsula. Such a natural “avulsive change” would have been a serious setback to river navigation, as the new channel would probably contain sharp, difficult-to-navigate bends. The United States therefore acquired 248 acres from plaintiff for $34,000 and planned the construction on this acreage of a new, easily navigable channel for the river (hereinafter the “Morrilton Cutoff” or “Cutoff”).

*672 In May 1950 the Corps constructed a pilot channel across the neck of the ox bow. The abrasive action of the river soon widened the channel to the desired extent, and its northern bank was stabilized by the Corps in 1952 by the construction of a suitable revetment. The new channel captured most of the flows of the Arkansas. As a result of water flowing through the old channel at lesser velocities, sediment was deposited. The silting-up of the ox bow was accelerated by the Corps’ construction of two dikes at the upstream end of the old channel in 1952 to divert flows away from the old riverbed. The old channel became an ox bow lake, a nonnavigable tributary of the Arkansas. Eventually the plaintiff sought and obtained title to the emerged lands, and began to farm them. Of the 1,719 acres currently comprising the Miller farm or property, approximately 800 acres lie on the pre-cutoff bed of the Arkansas River.

In 1956 the Corps began the construction of the McClellan-Kerr Arkansas River Navigation Project, authorized by Congress back in 1946. 1 Seven tributary lakes were to be converted into multiple-purpose reservoirs for low-flow regulation, sediment control, flood control, domestic and industrial water supply, and hydroelectric power. In addition, the main stem of the river was to be “canalized” by 17 navigation locks and dams. (When completed, the project was to provide a 448-mile long navigational channel from around Tulsa, Oklahoma, to the Mississippi River.) By 1964 the last of the upstream flood control reservoirs had been readied for flood control operation, the primary object of the authorizing legislation. The canalization plan was changed many times as the Corps found ways of simplifying the system. In 1960 or shortly thereafter, it was decided that the Toad Suck Ferry Lock and Dam No. 8 would be located 9% miles downstream from plaintiff’s property, and that the elevation of its upstream navigation pool would be fixed at 265 ft. The property is riparian to this pool. In 1965 wing dikes were constructed downstream of the property, and in 1969 the downstream Dam No. 8 was closed.

Plaintiff alleged in his complaint that the closing of the dam resulted in greater flooding to his land and that the operation of flood control reservoirs caused increased duration of flooding on the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Miller v. United States, 550 F. Supp. 669, 1 Cl. Ct. 1, 1982 U.S. Claims LEXIS 2314 (cc 1982).

550 F. Supp. 669 (Miller v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Edward M. Crough, Inc. v. Department of General Services
572 A.2d 457 (District of Columbia Court of Appeals, 1990)
Pearson (Gary L.) v. u.s.pearson v. United States
727 F.2d 1118 (Federal Circuit, 1983)
Lewis (Randall R.) v. u.s.lewis v. United States
727 F.2d 1118 (Federal Circuit, 1983)
Hargrett v. United States
3 Cl. Ct. 655 (Court of Claims, 1983)
Mariner (John Wayne) v. u.s.mariner v. United States
727 F.2d 1118 (Federal Circuit, 1983)
Bussa (John J.) v. u.s.bussa v. United States
727 F.2d 1117 (Federal Circuit, 1983)
Allen (Walter) v. u.s.allen v. United States
723 F.2d 69 (Federal Circuit, 1983)
Sladic (Michael J.) v. u.s.sladic v. United States
723 F.2d 69 (Federal Circuit, 1983)
Shanbaum (Theodore) v. u.s.shanbaum v. United States
723 F.2d 69 (Federal Circuit, 1983)
Staskus (John) v. u.s.staskus v. United States
723 F.2d 68 (Federal Circuit, 1983)
Berenholz (Gustav) v. u.s.berenholz v. United States
723 F.2d 68 (Federal Circuit, 1983)
Bounds (Enver H.) v. u.s.bounds v. United States
723 F.2d 68 (Federal Circuit, 1983)