Miller v. Safford

CourtUnited States Bankruptcy Court, E.D. Michigan
DecidedNovember 23, 2021
Docket19-03023
StatusUnknown

This text of Miller v. Safford (Miller v. Safford) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Safford, (Mich. 2021).

Opinion

UNITED STATES BANKRUPTCY COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION – FLINT

IN RE:

JAMES SAFFORD AND Case No. 19-30059 KRISTINE SAFFORD, Chapter 13 Proceeding Debtors. Hon. Daniel S. Opperman _______________________________________/ DOUGLAS MILLER and JULIE MILLER,

Plaintiffs,

v. Adv. Proc. No. 19-3023

JAMES SAFFORD,

Defendant. _______________________________________/

OPINION GRANTING PLAINTIFFS’ MOTION FOR SUMMARY JUDGMENT

Introduction Before the Court is Plaintiff Douglas and Julie Miller’s Motion for Summary Judgment against James Safford. Plaintiff filed this action under 11 U.S.C. §§ 523(a)(2), (a)(4) and 523(a)(6) objecting to the dischargeability of debt. The instant Motion for Summary Judgment is brought pursuant to Section 523(a)(4) only. For the reasons stated in this Opinion, the Court grants Plaintiffs’ Motion. Facts Defendant was an owner, officer, and authorized agent of Safford, Inc., d/b/a Integrity Construction & Contracting (“Integrity”) at all relevant times. Plaintiffs engaged Defendant and Integrity to build a home for them after their previous home was destroyed by fire and entered into a contract with Integrity on August 16, 2017. Plaintiffs assert that the residential building licenses of Integrity and Defendant had expired prior to entering into this contract or on May 31, 2018. The contract price agreed to was $275,000, with 5 draws of $55,000 conditioned upon the completion of certain stages in the construction process. Disputes arose regarding the timing and completion of certain stages and Integrity ultimately abandoned the project after receiving funds under the contract. Prior to and after abandoning the project, Defendant and Integrity failed to

pay subcontractors and suppliers, ultimately resulting in Plaintiffs being left to make the majority of the payments. These amounts total $44,033.65, and for excavation subcontractors, and additional $22,026.99 was not paid. Plaintiffs filed an action in state court asserting violations of the Michigan Building Contract Fund Act (“MBCFA” or “Act”), as well as violations of the Michigan Occupational Code. During discovery in the state court case, Defendant confirmed that Integrity failed to pay its laborers and subcontractors at least $23,088.06. There are disputes concerning the final amounts not accounted for, but the state court proceeding discovery process revealed that “at the very least, Defendant had failed to account for $44,781.98 of Plaintiff’s funds.” During the state

court proceeding, Defendant failed to produce a complete accounting of funds received from Plaintiffs or provide evidence of any payment provided to its subcontractors on this project. Defendant filed his petition seeking Chapter 7 relief with this Court before Plaintiffs could file their motion for default judgment in state court. Accordingly, they filed an adversary proceeding in this Court and submitted discovery requests to Defendant, which Defendant did not fully answer. After Plaintiffs filed a motion to compel discovery responses, this Court allowed Defendant additional time to respond, which he did in part. Given this partial response after ample opportunity to supply discovery responses, this Court entered an Order on April 28, 2020 sanctioning Defendant for failing to comply with discovery. This Order “prohibited” Defendant “from introducing evidence regarding the discovery responses, records, documents, issues, categories or information referenced in the Court’s February 18, 2020 Order Compelling Discovery Responses.” This Order also precluded Defendant from “introducing evidence, relating to the use of, or accounting for the construction trust funds paid by Plaintiffs to Defendant and/or the Company.”

Plaintiffs originally assert that the current amount owed by Integrity and Defendant to Plaintiffs is $319,878.98, which is $134,345.94 (three times the $44,781.98, as treble damages for conversion of trust funds is claimed), plus $185,533.04, representing Plaintiffs’ delay damages, cost to complete, amounts paid directly by Plaintiffs to Defendant’s subcontractors, and amounts still owing to these subcontractors. Plaintiffs assert summary judgment is appropriate because these facts are undisputed, attaching the relevant documents to support such along with the Affidavit of Plaintiff Douglas Miller, and that under applicable Michigan law, this debt is nondischargeable under Section 523(a)(4). Defendant denies that his actions amount to defalcation and violations of the MBCFA,

and that the delays were due to flooding that occurred during the construction process that were not the fault of Defendant or Integrity. Defendant does not attach any further accounting to support his position (and the April 28, 2020 Sanctions Order would preclude them from doing so). The Court heard oral arguments on July 22, 2021 and questioned Plaintiffs’ calculation of damages. To clarify these calculations, the Court allowed the parties an opportunity to supplement their briefs. Each party did so, and the Court has reviewed these helpful pleadings. Plaintiffs’ supplements clarify Plaintiffs’ damages under the MBCFA by detailing the $55,000 deposited by Plaintiffs with Defendant and Integrity and the accounting of $10,218.02 by Defendant, leaving $44,781.98 as unaccounted funds. This amount, when trebled, is $134,345.94. Next, Plaintiffs detailed each cost and unpaid invoice caused by Defendant’s defalcation, which Plaintiffs argue is also included as a separate item of damages. In particular, Plaintiffs report the following damages:

1. Unpaid Invoices to be Paid by Plaintiffs $ 22,026.99 2. Invoices Paid by Plaintiffs 44,033.65 3. Delay Costs 30,938.40 4. Net Cost to Complete Work 88,534.00 Total $185,533.04

All of these damage items are supported by affidavits and exhibits and are carefully catalogued in Plaintiffs’ original brief and well summarized in Plaintiffs’ supplemental pleadings. Plaintiffs also explain and account for the proper calculation of damages in regard to treble damages as allowed by the MBCFA and Cohen v. De La Cruz, 523 U.S. 213 (1998). Their table of calculations is: MBCFA and Conversion Damages $134,345.94 Damages Incurred as a Result of Defalcations 185,533.04 Less Amount Defalcated (44,781.98) Total Damage Request $275,097.00

In his supplement, Defendant argues that numerous man hours were incurred by Defendant as detailed in Defendant’s affidavit, filed with his response to Plaintiffs’ Motion and well after the deadline set by the Court. Also, Defendant claims Plaintiffs are “double dipping” on their damage calculations, that certain damage calculations are wrong, and that the $275,097 requested by Plaintiffs is more than the original contract between the parties. After careful review of the pleadings, the Court finds that the record is complete for purposes of this Opinion. Jurisdiction This Court has jurisdiction over this matter pursuant to 28 U.S.C. §§ 1334 and 157(a). This is a core proceeding under 28 U.S.C. § 157(b)(2)(I) (determinations as to the dischargeability of certain debts). Summary Judgment Standard

Federal Rule of Civil Procedure 56 is made applicable in its entirety to bankruptcy adversary proceedings by

Related

Cohen v. De La Cruz
523 U.S. 213 (Supreme Court, 1998)
Bullock v. BankChampaign, N. A.
133 S. Ct. 1754 (Supreme Court, 2013)
In Re Patel
565 F.3d 963 (Sixth Circuit, 2009)
Cappella v. Little (In Re Little)
163 B.R. 497 (E.D. Michigan, 1994)
Janda v. Riley-Meggs Industries, Inc.
764 F. Supp. 1223 (E.D. Michigan, 1991)
Shears v. Vestal (In re Vestal)
521 B.R. 604 (W.D. Michigan, 2014)
Hale v. Campbell
46 F. Supp. 772 (N.D. Iowa, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
Miller v. Safford, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-safford-mieb-2021.