Miller v. People's Lumber Co.

98 Ill. App. 468, 1900 Ill. App. LEXIS 562
CourtAppellate Court of Illinois
DecidedNovember 26, 1901
StatusPublished

This text of 98 Ill. App. 468 (Miller v. People's Lumber Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. People's Lumber Co., 98 Ill. App. 468, 1900 Ill. App. LEXIS 562 (Ill. Ct. App. 1901).

Opinion

Mr. Justice Waterman

delivered the opinion of the court:

The exceptions to the master’s report were neither sustained nor disallowed, the decree of the court reciting that the cause came on to be heard upon the amended bill of complaint taken as confessed by certain parties, named, answered by others, named, replication to such answers and the report of the master made in pursuance of an order of reference, and “ on the objection and exception to the report of said master, and the court being fully advised in the premises, it is ordered that said report be altered as herein in this decree set forth.”

The court had no power to alter the master’s report. It might reject or confirm it, overrule, or disallow exceptions thereto, but it could not change it. Such as it is, it is the master’s work, for which he alone is responsible.

•The court in this decree found that at the filing of the bill, September 19, 1898, there was due the contractor, Achenbach, from Peter Miller, $865, and that on August 26, 1898, there xvas due from Achenbach to the People’s Lumber Company $430.87, and that it had a lien as a subcontractor therefor from August 26 th.

The court further found that on the 23d day of August, 1898, Achenbach, being in arrears in his payments for materials furnished by the True & True Company, it refused to furnish any further material to said Achenbach, and thereupon Miller, the petitioner, verbally agreed with said True & True Company, that in consideration that it would furnish the material yet to be delivered under the agreement made xvith it by Achenbach, he, said Miller, would pay for material so to be delivered and also the balance then remaining due for material already furnished.

The court further found that said True & True Company furnished the balance of said material and that there became due to said True & True Company the sum of $190, xvith interest from the 10th day of September, 1898, and “that it is entitled to an original contractor’s lien for $190, with interest from September 10,1898, at five per cent per annum, and also $1 for filing a statement of lien and $5 for solicitor’s fees for filing the same and $19 for solicitor’s fees in this case.”

The court also found that Enoch Rydberg, Herman Johnson, Axel Johnson, Frank Reburg, John Schade and August Johnson, were carpenters employed on said building, and that about September 1, 1898, Achenbach, being in arrears in his payments to them, petitioner Miller agreed with them that if they would continue to work, he would pay them the amount so due from Achenbach and also pay them for the work thereafter to be done. Thereupon the court finds that each of said carpenters is entitled to a lien as an original contractor, namely: Enoch Rydberg, §38.40, with interest from the 12th day of September, 1898, and §3.84 for solicitor’s fees; Henry Johnson, §62.70, and interest from the 12th day of September, 1898, and $8.27 as solicitor’s fees; Axel Johnson, §45.30, with interest from the 12th day of 'September, 1898, and §4.63 as solicitor’s fees; Frank Reburg, §47.70, with interest from September 12,1898, and §4.77 as solicitor’s fees; John Schade, §71.85, with interest from September 12, 1898, and §7.18 as solicitor’s fees; and that August Johnson is entitled to §55.13 and a lien therefor as a sub-contractor, with interest thereon from September 12, 1898, and §5.51 as solicitor’s fees in accordance with the master’s report, which is in all things, as to him, approved and confirmed.

The master’s report finds that August Johnson is entitled, as a sub-contractor, to $85.95, together with interest amounting to §4.40, and solicitor’s fees amounting to §9.03, making in all the sum of §99.38. This report was made the 27th day of September, 1898. The discrepancy between the master’s report and the decree of the court which confirms the same as to August Johnson is not explained.

The decree further finds that Hodge & Homer Company is entitled to a lien on the premises for §100.95, but that Miller, the petitioner, is only obliged to pay said Hodge & Homer Company seventy per cent of the amount due, with interest from the 15th day of September, 1898, at the rate of five per cent per annum, together with §7.03 as its solicit- or’s fees.

The decree was entered June 8, 1900, and gives first and prior mechanic’s liens, up to and including the day of the decree, on the premises as follows:

People’s Lumber Company, $466.70, with solicitor’s fee of $43.

True & True Company, $205.39, with solicitor’s fee of $19, also $1 costs for filing suit and $5 for solicitor’s fee for filing same.

Enoch Bydberg, $41.42, and $3.84 solicitor’s fee.

Herman Johnson, $38.71, and $8.27 solicitor’s fee.

Axel Johnson, $48.97, and $4.33 solicitor’s fee.

Frank Beburg, $51.57, and $5.51 solicitor’s fee.

John Schade, $76.68, and $7.18 solicitor’s fee.

Hodge & Homer Co., $76.02, and $7.03 solicitor’s fee.

August Johnson, $55.59, and $5.51 solicitor’s fee.

And the decree provides that one-half the cost of the proceedings shall be paid by the petitioner Miller, and one-half by the respective lienors, to be divided pro rata among them, and directs that unless the petitioner or some of the defendants pay the aforesaid contractors the amount allowed, together with interest thereon from the day of the decree, and also pay the solicitor’s fees as found, then the premises be sold.

The decree makes no mention of the payment by the petitioner of $156.80, in satisfaction of liens amounting, as found by the master to $196, on account of which payment the master, allowed the owner, Miller, $137.20, being seventy per cent of the amount of liens satisfied by said payment.

The total amount of liens allowed by the decree is $1,137.97, whereas the decree finds that at the filing of the petition there was only $865 unpaid on the contract price, an overplus of $262.97; or, if we add to this the $137.20 allowed by the master to the owner for the discharge of liens amounting to $196, the amount which must be paid by the owner to free the premises from liens amounts to $417.17 more than the $865 which the decree finds was unpaid at the time of the filing of the petition.

All of the statements rendered by the contractor, Achenbach, to the owner, Miller, of names and amounts due for work done upon and materials furnished for said building, mention the People’s Lumber Company as entitled to $580.

Thereafter and before any notice had been filed by any contractor or given to the owner, he paid the People’s Lumber Company $300, thus, as he understood, reducing its claim, to $280. Upon the hearing before the master, it appeared that the contractor, Achenbach, had made false representations and statements to the owner, and that in reality instead of there being only $580 due the People’s Lumber Company, there was really owing to it $730.87.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
98 Ill. App. 468, 1900 Ill. App. LEXIS 562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-peoples-lumber-co-illappct-1901.