Miller v. Lykens Borough Authority

712 A.2d 800, 1998 Pa. Commw. LEXIS 347
CourtCommonwealth Court of Pennsylvania
DecidedMay 19, 1998
StatusPublished
Cited by3 cases

This text of 712 A.2d 800 (Miller v. Lykens Borough Authority) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Lykens Borough Authority, 712 A.2d 800, 1998 Pa. Commw. LEXIS 347 (Pa. Ct. App. 1998).

Opinion

PELLEGRINI, Judge.

Edwin and Donna Miller (Millers) appeal from an order of the Court of Common Pleas of Dauphin County (trial court) denying their post-trial motions seeking a new trial solely on the issue of damages against Lykens Borough Authority (Authority).

On December 18,1989, the Authority excavated part of Pottsville Street in Wieonisco Township (Township) in order to repair a damaged water line. After finishing its repairs to the water line, the Authority filled in the area of the roadway that it had excavated using material that contained frozen particles and placed the material in eight to twelve inch layers using a regular tamper.1 This measure was to be a temporary solution until the repairs could be completed by paving the roadway. On December 30,1989, while driving down Pottsville Street, Mr. Miller’s vehicle struck the utility cut which, since the time of the last inspection, was down eight to twelve inches below the roadway. Up until two days before the accident, the Authority had sent employees to the site to check the excavation for subsidence but none had occurred. The Millers filed suit against the Authority alleging that the Authority was negligent in the restoration of the roadway because it improperly backfilled the trench it had excavated and such negligence caused Mr. Miller’s injuries.2

When the case was first tried the jury was unable to reach a verdict. The Authority then moved for a directed verdict because it contended that the evidence did not establish that it had notice of a dangerous condition of the roadway. The trial court granted the motion and entered a directed verdict in favor of the Authority and the Millers appealed to this Court. In Miller v. Department of Transportation, 690 A.2d 818 (Pa. Cmwlth.1997) (Miller I), we reversed and ordered a new trial reasoning that there was sufficient evidence presented in which the jury could conclude that the Authority had notice that the roadway was a dangerous condition and the trial judge erred in taking that issue away from the jury.

At the close of the second trial, the trial court submitted a special verdict form to the jury containing three questions.3 Because the utility exception to governmental immunity in 42 Pa.C.S. § 8542(b)(5) requires actual or constructive notice to the agency before a plaintiff can recover, the trial court submitted this third question to the jury:

Do you find that the Defendant, Lykens Borough Authority, had actual notice or could reasonably be charged with notice of the depression/ditch on Pottsville Street, under all the circumstances in this ease, in sufficient time prior to the accident on the evening of December 30, 1989, to have taken measures to protect against the dangerous condition?

Millers’ counsel objected to submitting this question to the jury. He contended that the Authority was presumed, as a mater of law, to have the requisite notice because it created the allegedly dangerous condition if the jury were to find that the Authority had improperly filled the utility cut. When the jury returned its verdict, it found that the Authority was negligent in backfilling the utility cut and that its negligence caused Mr. Miller’s injuries, but because the Authority did not have actual or constructive notice of the dangerous condition in sufficient time before Mr. Miller’s accident to allow it to make repairs, the Authority was not liable to Mr. Miller for his injuries. The Millers filed post-trial motions contending that the trial judge erred in submitting the factual issue of notice to the jury and because the jury found the Authority negligent backfilling the utility cut a new trial should be held solely on the issue of damages. Relying on our decision in Kennedy v. City of Philadelphia, 160 Pa. Cmwlth. 558, 635 A.2d 1105 (1993) affirmed, [802]*802540 Pa. 527, 658 A.2d 788 (1995), the trial court denied the motion because notice under the exceptions to governmental immunity was not to be inferred merely because the Authority created the dangerous condition. This appeal followed.4

As they did below, the Millers do not allege here that the jury’s finding that the Authority lacked notice was against the weight of the evidence, but only that because the Authority created the dangerous condition causing Miller’s injuries, the trial court erred in submitting the issue of notice to the jury because notice that the cut could have subsided should have been imputed to the Authority as a matter of law. They contend that the notice required by 42 Pa.C.S. § 8542(b)(5) is nothing more than normal constructive notice and that where the defendant’s own antecedent conduct causes the dangerous condition, the plaintiff need not establish either actual or constructive notice. Penn v. Isaly Dairy Co., 413 Pa. 548, 198 A.2d 322 (1964); Finney v. G.C. Murphy, 406 Pa. 555, 178 A.2d 719 (1962). Because its negligence created the dangerous condition that caused Mr. Miller’s injury, the Millers argue that the Authority should be deemed to have had notice of the dangerous condition, just as a private landowner would have under the same circumstances.

The trial court based it decision to submit the factual question of notice to the jury on the exception contained in 42 Pa.C.S. § 8542(b)(5) that deals with local utilities. The utility exception provides that liability shall be imposed if the injuries complained of were caused by:

A dangerous condition of the facilities of a steam, sewer, water, gas or electric systems owned by the local agency and located within rights-of-way, except that the claimant to recover must establish that the dangerous condition created a reasonably foreseeable risk of the kind of injury which was incurred and that the local agency had actual notice or could reasonably be charged with notice under the circumstances of the dangerous condition at a sufficient time prior to the event to have taken measures to protect against the dangerous condition.5

As a prerequisite for recovering under this exception, a plaintiff is required to establish that the agency had actual or constructive notice under all of the circumstances. What the Millers contend is that when an agency creates a dangerous condition, negligence and notice are intertwined. While this may be true where the dangerous condition is obvious, e.g., if the Authority did not fill in the cut at all, the more precise issue, and the one involved in this case is whether the agency is charged with notice of a latent defect caused by its antecedent conduct.

We dealt with the issue of whether a governmental agency had notice of a latent defect in Kennedy, albeit under the traffic control exception that contains the same language on notice as the utility exception.6 In Kennedy, plaintiffs decedent was killed after she was struck by a car while walking along a roadway in which plaintiff alleged was improperly marked by PennDOT. The roadway contained only a single dotted white line that separated the west bound lanes. At trial it was shown that PennDOT [803]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. Lamberson v. SEPTA
Commonwealth Court of Pennsylvania, 2025

Cite This Page — Counsel Stack

Bluebook (online)
712 A.2d 800, 1998 Pa. Commw. LEXIS 347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-lykens-borough-authority-pacommwct-1998.