Miller v. Long Oil & Gas Exploration, Ltd.

542 So. 2d 75, 104 Oil & Gas Rep. 8, 1989 La. App. LEXIS 574, 1989 WL 31834
CourtLouisiana Court of Appeal
DecidedApril 5, 1989
DocketNo. 87-1344
StatusPublished
Cited by3 cases

This text of 542 So. 2d 75 (Miller v. Long Oil & Gas Exploration, Ltd.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Long Oil & Gas Exploration, Ltd., 542 So. 2d 75, 104 Oil & Gas Rep. 8, 1989 La. App. LEXIS 574, 1989 WL 31834 (La. Ct. App. 1989).

Opinion

KNOLL, Judge.

Dr. Garland D. Miller appeals an adverse judgment dismissing his claim against Long Oil & Gas Exploration, Ltd. (hereafter Long) for damages for Long’s failure to comply with the terms of a written contract which granted Long a servitude of passage to and from an oil well in Sabine Parish.

The trial court ruled that: (1) even though the servitude did not specify the location of the road, the parties agreed on its location; (2) since Miller failed to prove the parish requirements for the construction or maintenance of a rural, non-subdivision road, he is not entitled to damages because he failed to show a breach of the contract; and (3) it is more believable than not that subsequent to the confection of the written contract, Miller and Long verbally agreed to a location for the placement of the pipeline different from that stipulated in the servitude.

Miller contends that the trial court was manifestly erroneous in: (1) its interpretation of the contract; (2) its determination that Miller failéd to carry his burden of proof regarding the location and construction requirements of the road; and (3) its conclusion that Miller and Long verbally amended the written contract to provide for another pipeline location. We affirm.

FACTS

On March 1, 1985, Miller purchased approximately 37 acres in rural Sabine Parish which border Toledo Bend. At the time of this purchase, the property was already burdened by an oil, gas, and mineral reservation) and a mineral lease existed in favor of Long. However, the mineral lease did not have an ingress and egress clause, and no drilling activity existed on the property either prior to or at the time of Miller’s purchase.

[77]*77On April 15, 1985, Long, represented by its president, Palmer R. Long, entered into a written contract with Miller in which Miller granted Long the rights of ingress and egress to two well sites for the drilling and production of minerals. In consideration for this right Long gave Miller a ½6 working ownership interest in the wells, together with other stipulations not pertinent to this litigation, and particularly contracted as follows:

“(2) The drilling of wells on the property causes the need for there to be a good road on the property for heavy oil trucks and production trucks. Long Oil will build this road. There will be an agreed upon entry for such to be done and where. Said road shall be built and maintained to parish size and specifications.
* * * * * *
(8) It is agreed and understood that at no time will any compressor units be used on the premises. Further that the tank batteries shall be located on adjacent property commonly referred to as the Martinez tract. The pipeline shall run south from the well site to a fence line, then from the fence line to the Martinez tract in as near a straight line as possible.”

Approximately 37 days after signing this agreement, Long drilled a well on the subject property. Although the well was initially productive, its performance diminished. Its productivity at the time of trial was not established.

Almost one year later, on March 14, 1986, Miller advised Long by letter that their contract was in default for five specific reasons, two of which were failure to build a road to the wells which met parish specifications, and failure to lay the pipeline in the location designated by the contract. On or about May Í4, 1986, Miller and Long’s well operator met with attorneys for Miller and Long to amicably address these questions, and as a result of this discussion Miller hired a surveyor to mark a specific road site on the property. Although the record shows that Miller presented a copy of the survey to Long’s attorney, the road depicted on Miller’s survey was not acceptable to Long and was never built. Miller then filed this action against Long on August 29, 1986.

ROAD LOCATION AND DESIGN SPECIFICATIONS

Miller contends that he intended to subdivide his rural acreage. He argues that the trial court erred in its determination that the parties to the servitude agreement did not envision a road built to subdivision specifications, and in further finding that Miller failed to prove the requirements of a rural, non-subdivision road by a preponderance of the evidence. Miller further argues that the trial court was erroneous when it determined that he verbally agreed to locate the road over an existing logging road through the property.

We will first address the location of the road.

LSA-C.C. Art. 750 provides that, “If the title does not specify the location of the servitude, the owner of the servient estate shall designate the location.”

Unlike the location of the pipeline, discussed more fully infra, which was specified, the servitude of passage for the road simply provided that, “There will be an agreed upon entry for such to be done and where.” For the reasons which follow, we find no error in the trial court’s determination that Miller and Long agreed that the road would be located along an existing logging road.

In Patout v. Lewis, 51 La.Ann. 210, 25 So. 134 (1899), the Supreme Court determined that a dumping ground, not specifically designated in a predial servitude, was improperly located. In Patout, the court applying Art. 779 (1870), now LSA-C.C. Art. 750, stated, 25 So. at page 138:

“[W]e must assume the location was the proper one. A fixed status or condition of things, reaching over a number of years, the consent to which is evidenced not only by the silence and acquiescence of defendant, but by affirmative acts on his part, cannot be ignored and collateral[78]*78ly drawn in question as has been attempted to be done by defendant.”

Although the facts of the case sub judice are not as forcefully present as they were in Patout, we nonetheless find the Patout rationale applicable. Palmer Long testified that he and Miller discussed the issue of the road placement prior to the signing of the servitude, and that they agreed that it was most expeditious if they followed the logging road to the well site. Miller disagrees. It is axiomatic that credibility determinations and the resolution of factual differences are within the purview of the trier of fact. In the present case, the record establishes that Miller lives on the property in question and he was at the well site almost daily during development of the well. It also shows that Miller, as a working interest owner of minerals, had a vested interest in the speedy completion of the well. The record further shows that it was not until almost a year later that Miller formally objected to Long about various contractual breaches that occurred, failing even at that time to make any mention that the road was not properly located along a route designated by him. Moreover, it was not until June of 1986, more than a year after the servitude was signed, that a surveyor staked out a proposed road at Miller’s behest.

After carefully reviewing the record in light of the principles outlined in Patout, we cannot say that the trial court was manifestly erroneous in its determination that Long’s placement of the road was not at a location designated by Miller.

We now turn to Miller’s argument that Long failed to construct a road and maintain it to parish size and specifications as outlined in the servitude of passage.

Under the terms of LSA-C.C. Art.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lafourche Realty Co. v. Entergy La., Inc.
255 So. 3d 1086 (Louisiana Court of Appeal, 2018)
Phipps v. Schupp
163 So. 3d 212 (Louisiana Court of Appeal, 2015)
Miller v. Long Oil & Gas Exploration, Ltd.
544 So. 2d 403 (Supreme Court of Louisiana, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
542 So. 2d 75, 104 Oil & Gas Rep. 8, 1989 La. App. LEXIS 574, 1989 WL 31834, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-long-oil-gas-exploration-ltd-lactapp-1989.