Miller v. Guy H. James Construction Co.

653 P.2d 221
CourtCourt of Civil Appeals of Oklahoma
DecidedOctober 29, 1982
Docket53856
StatusPublished
Cited by4 cases

This text of 653 P.2d 221 (Miller v. Guy H. James Construction Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Guy H. James Construction Co., 653 P.2d 221 (Okla. Ct. App. 1982).

Opinion

BOYDSTON, Presiding Judge.

Plaintiff Roger Miller, d/b/a R. Miller & Sons Co., (Subcontractor) sued to recover the cost of repair work to a concrete channel liner that washed out twice while it was being constructed for Guy H. James Construction Co. (Prime Contractor) and Santa Fe Land Improvement Co. (Owner). Subcontractor also sued to enforce a lien against the property of Santa Fe. The case was tried to the court and resulted in a $37,231.87 judgment, attorney fees, interest, and costs in favor of Subcontractor. In addition, foreclosure of the lien was ordered.

*223 Owner, Prime Contractor, and its bond company, Federal Insurance Company, appeal and allege the judgment is contrary to law and is not supported by the evidence. We reviewed the record and found it supported by law and competent evidence. We affirm.

Prime Contractor and Owner contracted for the construction of a concrete lined surface water drainage ditch on a 300 acre industrial site. Prime Contractor subcontracted the grading and dirt work to Sewell Brothers, Inc. (Sewell). The subcontract for construction of the concrete ditch liner went to Subcontractor.

The construction plans, including engineering and specifications for the dirt and grade work, were contracted by Owner to Cobb Engineering Company and were furnished to Prime Contractor. The engineering plans were defective according to the evidence presented at trial.

After Subcontractor had partially completed the ditch liner, runoff from a heavy rainstorm washed it out. The liner was repaired and 97 percent completed by Subcontractor when another rainstorm washed it out. Again Subcontractor reconstructed the damaged ditch. Reasonableness of the repair cost is not disputed, and the contract between Prime Contractor and Subcontractor is silent as to which of the parties should bear the risk of such a loss.

Subcontractor filed suit after Prime Contractor and Owner refused to reimburse him for the repair work. The suit against Prime Contractor alleged the plans were defective. Suit against Owner was to foreclose a materialman’s lien against the property.

Prime Contractor then filed an “action over” against Owner alleging that should the court enter judgment in favor of Subcontractor, Prime Contractor should be entitled to judgment against Owner because the wash-outs of the liner were caused by defective plans and specifications furnished by Owner. Prime Contractor also filed a third party action against Sewell asserting the “hold harmless” clause in its contract with' Sewell and alleging Sewell had compacted the dirt and graded the area negligently thus contributing to the damage. Sewell, however, was never properly served.

The court, after five days of testimony, rendered judgment in favor of Subcontractor against Prime Contractor, Owner, and Federal Insurance Company on the repair cost and the lien and denied Prime Contractor’s right to recover against Owner. The trial court made general findings because no request was made for special findings of fact and conclusions of law. Prime Contractor, Owner, and Federal Insurance appeal. Prime Contractor does not appeal the court’s ruling that Owner need not reimburse it for the repair cost.

The sole issue presented on appeal is whether the evidence is sufficient to support the judgment and whether the judgment is contrary to law. Stated another way: who must bear the loss from destruction of or damage to the project during performance of a building contract?

I

We are required to affirm the judgment of the court sitting in matters of law without a jury if its judgment'is supported by competent evidence and is not contrary to law. Pracht v. Oklahoma St. Bank, Okl., 592 P.2d 976 (1979). Moreover, the judgment must stand if it is warranted under any proper legal theory. Diem v. Diem, Okl., 372 P.2d 19 (1962).

The evidence is almost undisputed that: (1) the plans were defective; (2) they were furnished by Owner’s engineer; (3) they were a part of Subcontractor’s contractual obligation; and (4) Subcontractor fully complied with the terms of the contract.

Experts testified there are two ways to design a surface water drainage system. The first, not employed here, is called “point loading” design. This system deliberately channels water to “load” into the concrete ditch at one or more single points of entry. The other system is called “sheet loading,” the system applicable to this case. This system is designed to cause water to *224 flow into a channel evenly across the entire length of the ditch in a “sheet.” To prevent “point loading” and erosion of the silty loam soil involved here, an expert testified the slope grade should have been such as to allow water to travel no more than two feet per second. The existing slope grade of 1-2 percent (1-2 feet per 100 feet) allowed an excessive water velocity of 6-7 feet per second; consequently, the surface water quickly eroded the soil near unintended single entry points and washed out the ditch liner.

There is evidence from which the court could conclude the plans were defective in two ways: (1) they permitted “point loading” instead of “sheet loading”; and (2) the steep grade permitted the water to flow at. an excessive velocity. Consequently, the combination of erosion and unintended “point loading” quickly undermined the concrete liner, causing it to “float out” and be damaged.

Some evidence indicates Sewell’s equipment and work was substandard; however, Sewell was not a party to the suit, and this issue was not seriously contested. For the record, it appears the work done by Sewell contributed to the extent of damage, but not to the fact.

Based on these facts there is ample evidence from which the court could properly find Subcontractor free from negligence and the major contributing cause of the damage to be the defective plans.

II

Prime Contractor argues the judgment is contrary to law for several reasons. First, Prime Contractor claims no responsibility for the torts of his independent contractor, Sewell, under Oklahoma City v. Caple, 187 Okl. 600, 105 P.2d 209 (1940). This argument fails because Subcontractor did not allege or rely on proof of either the negligence of Prime Contractor or Sewell. He did prove his work was performed according to faulty plans and specifications furnished by Prime Contractor and that he should not have to bear the loss caused by their deficiency. The issue of Sewell’s negligence was first seriously raised specifically by Prime Contractor in his third party action. The proof of Sewell’s negligence that seeped into the record was peripheral at best, compared to the proof directed toward the defective design.

Rather, the thrust of Subcontractor’s action sounds in contract. Absent open and obvious design defects which should be apparent to a prudent contractor and called to a prime contractor’s attention, the party who furnishes plans and specifications impliedly warrants them to be fit for their intended use. Both parties cite Woods v. Amulco Products, 205 Okl. 34, 235 P.2d 273 (1951), in which the Oklahoma Supreme Court held:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Tulsa v. Air Tulsa, Inc.
1992 OK 146 (Supreme Court of Oklahoma, 1992)
Musco v. Cynda Corporation, No. Cv 91 0387749 (Aug. 28, 1992)
1992 Conn. Super. Ct. 8164 (Connecticut Superior Court, 1992)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
653 P.2d 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-guy-h-james-construction-co-oklacivapp-1982.