Miller v. Fort Hill Development Associates, Inc.

11 Mass. L. Rptr. 432
CourtMassachusetts Superior Court
DecidedJanuary 6, 2000
DocketNo. 9701777
StatusPublished

This text of 11 Mass. L. Rptr. 432 (Miller v. Fort Hill Development Associates, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Fort Hill Development Associates, Inc., 11 Mass. L. Rptr. 432 (Mass. Ct. App. 2000).

Opinion

Fecteau, J.

This is an action brought by the plaintiffs in connection with the defendants’ construction of a duplex residential structure. The complaint is in seven counts, five against the corporate defendant, alleging breach of contract, in falling to complete the construction on time and in failing to build as agreed in the specifications, breach of warranty, misrepresentation and a violation of G.L.c. 93A; the remaining two counts against the individual defendant allege misrepresentation and a c. 93A violation. The defendants deny wrongdoing of any kind and say that if there were defects present when their work on the project was stopped, the plaintiffs prevented them from correcting any such defects or completion, that the house was substantially completed on time, that the plaintiffs were permitted by the defendants to begin occupancy one month prior to the expected completion date and that the plaintiffs’ complaints are unreasonable, or relate to items over which they had no legal responsibility and to items that the plaintiffs had previously accepted as satisfactory.

This matter came on before me on October 27, and November 10, 1999. This matter was tried to the court without jury. On August 27, 1999, another justice of this court allowed a motion in limine brought by the plaintiffs that the defendants, being aggrieved by a decision in the District Court, failed to re-insist upon a jury trial in this court, having removed the case from the District Court following entry of judgment there. At trial, the defendants contended that their action in bringing the case to the Superior Court was not a removal after judgment in the District Court but rather an appeal of that judgment, pursuant to G.L.c. 231, Sec. 97.1 ruled that, notwithstanding the styling of the defendants’ pleading by which they sought a transfer of the matter from the District Court to this court as an “appeal,” presumably under the provisions of G.L.c. 231, Sec. 97, since this case could have originated in this court, the provisions of said statute do not apply; rather, the provisions of G.L.c. 231, Sec. 104 and 102C apply. Thus, since the defendants failed to comply with said latter statutes by re-insistence, in this court, on their demand for a jury trial, they have waived their right to a jury trial.

Upon consideration of the evidence, I make the following findings of fact and rulings of law.

[433]*433FINDINGS OF FACT

1. In August 1994, the plaintiffs contracted with the defendants for the construction of a two-story, “side-by-side” duplex at 729 Franklin Street, Worcester, for a total construction price of $145,500.00. Although the contract specified that time was of the essence in the performance by both parties, it also called for construction to be completed within five months following the signing of the written contract, presumably by mid-January 1995, subject to reasonable delays due, for example, to weather, the permit and inspection process and other conditions over which the defendants had no control.

2. The contract called for the house to be built according to written plans, specifications and a bill of materials. The contract promised that the work would be done' in a good, substantial and workmanlike manner. Also referenced and attached to the contract was an express warranty that essentially promised that all structural elements be free of any defects for one year.

3. Construction began in September 1994, with the excavation of the site and the pouring of a footing and foundation. The plaintiffs requested and were allowed to occupy the premises as of the week prior to the Christmas holidays 1994, the structural elements being substantially complete at that time but with finish-work still in progress. This is some evidence that the plaintiffs were satisfied, in general, with the state of completion of the project, as they were moving into occupancy before the projected completion date and without an occupancy permit.

This also likely served to complicate and lengthen the time for completion of the work since the tradesmen had to then work around the plaintiffs and their personal property.

4. Beginning approximately in November 1994, until April or May 1995, the plaintiffs presented the defendants with several “punch lists” of items that needed repair, replacement or completion. These lists included many groups of items, such as carpentry, plastering, painting, plumbing and electrical. In addition, there were complaints about unfinished landscaping, curb cuts and failure to include window openings in the front cellar wall. The punch lists were admitted as exhibits, not for the truth of the matters asserted in the punch lists, but rather as evidence of knowledge or notice to the defendants of complaints of the plaintiffs. Obviously, landscaping work, consisting of the delivery and spreading of loam, grading and seeding of a lawn cannot be done in winter. Moreover, asphalt rendering plants are customarily shut down during winter months although a small inventory of asphalt may be kept on hand for emergency road repairs.

5. Upon receipt of complaints by the plaintiffs, Colecchi called back the subcontractors involved in the trade at issue. Primarily, the only complaints accepted by the defendant were those concerning the finish of interior wall surfaces. These complaints were then remedied, such as touching up the plastering around light switch plates, repair of cracks in walls and repainting walls to cover scratches or to make the wall uniform in appearance. Additionally, there were some minor rewiring tasks needed to be done, such as a doorbell and some smoke detectors, and which were done. She did not verify or agree with some items of complaint, however, such as inadequate flashing around the chimney or leaking around the chimney, leaking oil tanks and rusting oil filler pipes. In addition to the testimony of the defendant Judith Colecchi, the defendants offered evidence from various sub-contractors, including carpenter, electrician, designer and plasterer. They testified that with each item of complaint on the punch lists that concerned their section of the work, remedial work was done in satisfaction of the contract requirements. As to the testimony of each, I found them to be credible.

6. One item of complaint was caused by a change requested by the plaintiffs, namely a lack of soundproofing in the common wall between the two units. I find that the explanation given by the defendants’ designer with respect to the complaint of decreased sound proofing in the common wall being due to the plaintiffs’ decision to have the kitchen cabinets moved off the common wall to a side wall is credible. There is evidence that ten-inch, batt-type insulation is within the common wall and that the specifications do not call for any additional sound barrier.

7. With respect to the plaintiffs’ complaint that cellar windows were not allowed for in the foundation in front of the house was a mistake made by the defendants, but cellar windows were placed in the foundation on the side and rear of each unit. There was no evidence as to the particular damage caused to the plaintiffs on account of the lack of a cellar window in the front of each unit of the house.

8. The case was first tried in the District Court and a decision was entered in favor of the plaintiffs in the amount of $10,145.00, together with interest and costs. (See ex. 1.) The plaintiffs called no witnesses, neither during their case-in-chief nor in rebuttal to the defendants’ evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lubell v. First National Stores, Inc.
172 N.E.2d 689 (Massachusetts Supreme Judicial Court, 1961)
Cincotta v. DuPuy
1 N.E.2d 182 (Massachusetts Supreme Judicial Court, 1936)
Cook v. Farm Service Stores, Inc.
17 N.E.2d 890 (Massachusetts Supreme Judicial Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
11 Mass. L. Rptr. 432, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-fort-hill-development-associates-inc-masssuperct-2000.