Miller v. Edison Electric Illuminating Co.

186 N.E. 581, 283 Mass. 517, 1933 Mass. LEXIS 1009
CourtMassachusetts Supreme Judicial Court
DecidedJune 29, 1933
StatusPublished
Cited by5 cases

This text of 186 N.E. 581 (Miller v. Edison Electric Illuminating Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Edison Electric Illuminating Co., 186 N.E. 581, 283 Mass. 517, 1933 Mass. LEXIS 1009 (Mass. 1933).

Opinion

Pierce, J.

This is an action of tort to recover damages for personal injuries, sustained by the plaintiff by reason of a defective manhole cover in the sidewalk which the defendant, as alleged, was bound to keep in repair.

At the close of the evidence the judge on the defendant’s motion directed a verdict for the defendant, and the plain[519]*519tiff excepted. The judge “reserved the case for report to the Supreme Judicial Court at the request of both parties upon the stipulation that if, disregarding any evidence improperly admitted after objection and exception, the direction is error judgment shall be entered for the plaintiff in the sum of $9,000, unless by reason of the provision of G. L. c. 84 the maximum amount that the plaintiff can recover is $4,000, in which event if the direction is error, judgment is to be entered for the plaintiff for $4,000.” The report contains all the material evidence.

At the trial it was agreed by counsel that “the street in question was a public way and that the manhole was constructed by a contractor employed by the Edison company in 1923”; that “A permit was issued May 23, 1923, on its application for the construction of a conduit running the length of Quincy Street, and that the permit included building of a manhole on which' the plaintiff fell”; that “In the summer of 1927 the Edison company was ordered to make certain manholes conform to a certain grade set by the city engineer and that the manholes were constructed and set to that grade, including the manhole on which the plaintiff fell”; that “the work was passed upon and inspected and that the Edison company had no right to do anything at that time other than what the city engineer and the city inspector ordered to be done”; and that “when the Edison company left there the sidewalk had not been laid, but that the manhole was constructed at the grade given by the city engineer and left in that condition and passed by the city inspector on the job.”

A bond was admitted in evidence over the defendant’s objection and exception for the purpose of showing control and for the purpose of showing an agreement for indemnification which would entitle the plaintiff to bring action against the Edison company. No technical objection was raised to the execution of the bond. The bond was as follows: “Know- all men by these presents that we, the Edison Electric Illuminating Company of Boston, Massachusetts, as principal, and Fred G. Haven of Somerville, Mass., as surety, are holden and stand firmly bound unto [520]*520the City of Boston in the sum of twenty thousand dollars, to the payment of which to the said City of Boston we hereby jointly and severally bind ourselves, our successors and assigns, heirs, executors and administrators. This obligation is upon the condition that if the Edison Electric Illuminating Company of Boston has received or shall hereafter receive any permit from the Superintendent of Streets to occupy or make an opening in any public way and shall hereafter receive or has received any permit from the Superintendent of Streets to occupy or make an opening in any public way and shall faithfully discharge and perform every duty and requirement imposed by statute, ordinance or regulation upon persons occupying or making openings in public ways, conform to all directions of the Superintendent of Streets relating to the work done under such permit and pay all expenses and damages incurred by the city or recovered from it by reason of such occupation, opening or work, the obligation shall become of no effect; otherwise it shall continue in full force. Signed, sealed and delivered this ninth day of September 1909.”

For the purpose of showing control of the manhole evidence was admitted that on March 4, 1929, the defendant made an opening on Quincy Street at the Phillips Brooks School for the purpose of repairing a manhole. It further appeared that following the thirtieth day of January, the day of the accident, two squares of granolithic pavement were relaid around the manhole in question by the contractor who built the paving; and that a permit in the form of an order issued to the contractor, which read: “Henry F. Malley” “You are hereby authorized and directed to repair two blocks of artificial stone sidewalk at the expense of the Edison Electric Illuminating Company. This order is not good unless approved by the Edison Electric Illuminating Company.” This order referred to the location of the manhole in question and was approved by the Edison Electric Illuminating Company. “It was agreed that there was no application to repair the two blocks of concrete in the application to repair the manhole cover on March 4, 1929, but there was an order given to repair them and the re[521]*521pair was done and charged to the Edison company, and they paid for it to the contractor Malley.” From 1927, when the manholes were constructed to conform to certain grades set by the engineer, until the moment of the accident on January 30, 1929, the defendant did nothing and had no right to do anything to change the level or grade of the sidewalk in which the manhole was placed. It appeared in evidence that the sidewalk was laid by a city contractor and that when the job was finished in October or early November, 1927, the casting was “level with the sidewalk and agreed with its slope.”

The report describes the accident to the plaintiff in substance as follows: The plaintiff lived, and had a place of business, on Quincy Street, Hoxbury. January 30, 1929, “was a dull day” and “there was no snow on the sidewalk.” At 7:50 a.m. he left his house to go to his place of employment. As he was walking on the sidewalk his attention to his footing was momentarily diverted therefrom by a salutation coming from a man riding in an automobile. He turned his head to see who was calling and coincidently he stepped on the top of a manhole cover; “his foot twisted ... his ankle turned over and he fell down” and sustained injuries for which he seeks damages in this action.

The manhole itself is of brick set on a solid foundation. It is five feet deep by three and one half feet wide and five feet long, and is built on a concrete floor. The entrance to the manhole is a circular opening twenty-nine inches across, rimmed with an iron casting which rests on iron rails and encloses the top of the manhole chamber. The only part of the manhole visible from the sidewalk is the edge of the casting and the solid iron cover. The sidewalk at the place where the accident occurred was of concrete construction and about eight feet wide, the back of the sidewalk being three inches higher than the curbing. When the sidewalk was laid and finished in October or early November, 1927, the casting “was level with the sidewalk and agreed with its slope.” There was evidence to warrant a finding by the jury that at the time of the accident, and before for about six months, the sidewalk was one and one half inches [522]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer v. Veolia Energy North America
121 N.E.3d 1221 (Massachusetts Supreme Judicial Court, 2019)
Regan v. John J. Amara & Sons Co.
205 N.E.2d 705 (Massachusetts Supreme Judicial Court, 1965)
City of Boston v. A. W. Perry, Inc.
22 N.E.2d 627 (Massachusetts Supreme Judicial Court, 1939)
Berlandi v. Union Freight Railroad
16 N.E.2d 17 (Massachusetts Supreme Judicial Court, 1938)
Sloper v. City of Quincy
16 N.E.2d 14 (Massachusetts Supreme Judicial Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
186 N.E. 581, 283 Mass. 517, 1933 Mass. LEXIS 1009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-edison-electric-illuminating-co-mass-1933.