Miller v. Calumet Lumber & Manufacturing Co.

121 Ill. App. 56, 1905 Ill. App. LEXIS 345
CourtAppellate Court of Illinois
DecidedMay 29, 1905
DocketGen. No. 11.968
StatusPublished
Cited by4 cases

This text of 121 Ill. App. 56 (Miller v. Calumet Lumber & Manufacturing Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Calumet Lumber & Manufacturing Co., 121 Ill. App. 56, 1905 Ill. App. LEXIS 345 (Ill. Ct. App. 1905).

Opinion

Mr. Justioe

Brown delivered the opinion of the court.

A motion to dismiss the appeal or to affirm the decree of the Circuit Court with statutory damages was made by the appellants in this cause soon after it was entered in this court. The motion was reserved to the hearing in due course. It is now denied. We have considered the appeal on the merits. The objections made to this course because of the alleged informalities in the transcript of the record, we do not think are well taken. By the filing of an additional record by appellants on their suggestion of diminution, and by their also filing under leave of this court the transcript on the former appeal, anything in these objections which might otherwise be material has been met.

The first of the alleged errors of the Circuit Court which is insisted on and argued by the appellants’ counsel in this appeal, is that the complainant by its amended bill and the intervening petitioner by its amended petition have each made an entirely new case, distinct and different from the cases set up by the original bill and original intervening petition, and that since the amended bill and amended petition were not filed within four months after the dates fixed for final payment under the contracts set up therein, respectively, the complainant and intervening petitioner are barred from maintaining this suit. We do not so view the matter. We think the Circuit Court was right in holding that no new or different causes of action were stated in the amended petitions. They asked for a mechanic’s lien, under the statute of Illinois, against the property of certain defendants; the original petitions had asked for the same lien against the same premises. The original and amended petitions were based on the same contracts between the owners and the original contractor, and the same contracts between that original contractor and the petitioners, and described those contracts and the work and materials they respectively called for in the same way. The amended petitions made no new or different parties. We do not see how it can be successfully contended that the later petitions are anything more than the less defective and more artificial method of stating their claim, which is always allowed by way of amendment to parties plaintiff, without rendering them liable to the consequences of having stated a new cause of action.

The gist of the reasons given by the Branch Appellate Court when it reversed the former decree in this cause, was that the amount due from the owner to the original contractor must be ascertained and found before there could be a decree in favor of the claimants. “In this case,” the court says, “the amount due from the owner to the contractor is not found or declared in the decree, nor is there any evidence upon which such a decree can be based.” It is true that the court also says, “Neither the petition nor the intervening petition' comply with the requirements of section 32,” but that the court did not think that their amendment would be made futile and ineffective by the four months’ limitation is shown by its action in, of its own motion, granting leave for such amendment. It may be conceded that the Circuit Court was bound by this action only to allow the amendments, and had power to have afterward declared them useless, but in so doing it would certainly have disagreed with the Branch Appellate Court. We agree with the view of that court and of the Circuit Court. The underlying purpose of statutory limitations is to prevent the unexpected enforcement of stale claims, concerning which persons interested have been thrown off their guard by want of prosecution. This is especially true of the short limitations in lien laws. Nothing could be more different from such a situation than the one in this case.

The next contention of the appellants to be noticed is that the contract between Frink and the Calumet Lumber and Manufacturing Company shows on its-face that it was not in pursuance of the purposes of the original contract between the Millers and Frink, and therefore does not fall within the Lien statute. The ground for this argument is that the Calumet Company contract (which was oral) included (by reference) the terms of an endorsement upon the estimate on which it was based, to the effect that the delivery of the material furnished was to be completed by the Calumet Company within four months from June 2d, 1901, while the contract .between the owners and Frink provided that the entire building should be completed on or before September 1, 1901. Hence' it is urged the first could not be “in pursuance of the purposes” of the second.

• We do not think this conclusion follows. The same estimate which contains “the time memorandum” shows on its face that the materials were contracted for to be delivered to the appellants at the premises involved in this suit, and were so delivered there. The larger part of them had been delivered before September 1, and that part -of them delivered after September 1 was so delivered in compliance with the direct request of the appellants after Frink had abandoned the job—a request made in a complete recognition of the character of the Lumber Company’s contract—as “in pursuance of the purposes” of Frink’s contract with appellants.

The contract between Frink and the Calumet Lumber Company was not inconsistent with the contract between appellants and Frink. There was nothing in it to prevent the Calumet Lumber Company from delivering all the material before September 1, 1901. It simply provided a date before which it must be delivered, or the contract would be broken. The material was presumably to be furnished as called for, and a time limit might be as much for the protection of Frink as for the vendor’s, in order that he might not be overrun with material before he was ready. He may have known that there was no doubt of his being able to get the material as rapidly as he could possibly need it. At all events, as it has been decided in Von Platen v. Winterbotham, 208 Ill., 205, that a subcontract in which there is no time limit whatever may be held to be in pursuance of the purposes of an original contract in which a time for completion is specified; it certainly is not the law that a subcontract in which such a time limit is provided, although the time allowed runs a little beyond that allowed by the original contract, cannot be so held. This objection does not seem to be urged against the intervening petitioner, the Chicago Heights Lumber Company, although by its contract, as alleged, it was to complete the delivery before September 24, 1901. Perhaps this is because the proof shows that its material was in fact all' delivered before August 26. In any event we do not regard the position of appellants in this regard tenable as to either of the appellees’ contracts, and it is not necessary for us to consider whether or not it is still open to them to take it in this second appeal.

The third objection of the appellants to the decree is that the -notice on which the Chicago Heights Lumber Company’s right to a lien depends is not in compliance with the statute. We see no merit in this point. Counsel say that the notice does not state “when the material was to be. delivered,” nor that there was “any fixed time when it was to be delivered,” nor “when payments were to be made.” The statute does not require that the notice should contain this information. It does provide that it shall state when" the amount claimed to be due became due, and the Appellate Court of the Second District in Hurtt v. Sanders Bros. Mfg. Co., 99 Ill. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lametta v. Connecticut Light & Power Co.
92 A.2d 731 (Supreme Court of Connecticut, 1952)
Anderson v. City of Bridgeport
56 A.2d 650 (Supreme Court of Connecticut, 1947)
Garrett Biblical Institute v. National Fire Insurance
257 Ill. App. 117 (Appellate Court of Illinois, 1930)
Kleinschnittger v. Dorsey
152 Ill. App. 598 (Appellate Court of Illinois, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
121 Ill. App. 56, 1905 Ill. App. LEXIS 345, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-calumet-lumber-manufacturing-co-illappct-1905.