Milford Power Co v. Alstom Power, Inc.

822 A.2d 196, 263 Conn. 616, 2003 Conn. LEXIS 195
CourtSupreme Court of Connecticut
DecidedMay 20, 2003
DocketSC 16841
StatusPublished
Cited by45 cases

This text of 822 A.2d 196 (Milford Power Co v. Alstom Power, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milford Power Co v. Alstom Power, Inc., 822 A.2d 196, 263 Conn. 616, 2003 Conn. LEXIS 195 (Colo. 2003).

Opinions

Opinion

KATZ, J.

The dispositive issue in this appeal1 is whether the trial court, in denying a motion to dismiss, properly determined that the untimely notice of a force majeure event, issued pursuant to a provision in the commercial contract (contract) between the plaintiff, Milford Power Company, LLC, and the defendants, Alstom Power, Inc., and Black and Veatch Construction, Inc., gave rise to a justiciable controversy. We conclude that the trial court’s determination was improper and, therefore, that the court did not have jurisdiction over the plaintiffs declaratory judgment action to consider whether the defendants properly had invoked the force majeure clause. Accordingly, we conclude that the trial court’s denial of the defendants’ motion to dismiss was improper.

The record reflects the following facts and procedural history. In February, 1999, the plaintiff and defendants entered into the contract in which, for a sum certain in excess of $230,000,000, the defendants agreed to provide the plaintiff with certain engineering, procurement and construction services related to the construction of an electric power generating plant in Milford. Integral to the project were two forty foot high heat recovery steam generators, one of which collapsed on February 2, 2000, during the course of construction, killing two workers, injuring two others and causing severe property damage. As a result of the accident, the federal [619]*619Occupational Safety and Health Administration (OSHA) commenced an investigation and closed the site, halting construction in the area of one of the generators until March 7,2000, and denying access to a second area until March 2, 2000, when OSHA approved the defendants’ demolition and removal plan. By letter dated March 21, 2000, pursuant to § 9.5 of the contract,2 the defendants provided the plaintiff with notice3 that the incident and [620]*620investigation constituted force majeure events, as defined by § 13.1 of the contract.* **4 The notice did not include a claim under § 9.5 of the contract seeking changes in the time needed to complete the project or in the amount of compensation to be paid to the defendants. The plaintiffs rejected the notice, asserting that it was untimely and that neither the incident, nor the subsequent investigation, constituted a force majeure event under the contract. Thereafter, pursuant to General Statutes § 52-29 and Practice Book § 17-55,5 the plaintiff commenced this declaratory judgment action, seeking, inter alia, a judicial declaration that the notice letter had been untimely and a determination [621]*621that the incident and subsequent investigation had not constituted a force majeure. The plaintiff claimed that a judicial declaration was necessary in order to allow the parties to “ascertain their rights and duties under the Contract with respect to confirming the Contract Price and Substantial Completion Date.”6

The defendants moved to dismiss the action claiming that, because the notice of the force majeure event did not include a claim for additional time or money to construct the project, there was no justiciable controversy between the parties. They argued that the action was premature because it depended on a number of events that had not yet transpired, and that accordingly, no practical relief could be afforded. The plaintiff opposed the motion contending that it was entitled to a declaratory judgment to prevent the defendants in the future from “upset[ting] the parties’ contractual liquidated damages regime . . . .” Essentially, the plaintiff contended that the action was ripe because it anticipated that the defendants would claim entitlement to an equitable extension of time and, therefore, would object to the plaintiffs assessment of liquidated damages.

The trial court denied the motion to dismiss, concluding that the action was justiciable. Specifically, the court concluded that, because the notice letter could lead to a future dispute between the parties regarding the plaintiffs entitlement to liquidated damages for delays arising out of the incident and subsequent investigation, the action was ripe for adjudication.

Thereafter, the plaintiff moved for partial summary judgment on its claim that the notice was untimely [622]*622under § 9.5 of the contract. Specifically, the plaintiff claimed that, because timely notice was a strict condition precedent to the defendants’ right subsequently to assert a claim for additional compensation for the project or time to complete the project, their untimely notice precluded any such future claim. The defendants opposed the motion on the grounds that: (1) timely notice was not a strict condition precedent to any such future claim and that the issue of prejudice resulting from its noncompliance with the notice provision presented an issue of material fact; (2) even if compliance had been a condition precedent to the right to submit a claim for additional time or money, the existence of the issue of whether the doctrine against inequitable forfeiture applied in this case; see Aetna Casualty & Surety Co. v. Murphy, 206 Conn. 409, 412-15, 538 A.2d 219 (1988); precluded the entry of summary judgment.

The trial court granted the plaintiffs motion and entered partial summary judgment against the defendants, concluding that compliance with the notice provision was a condition precedent to the defendants’ right to later assert a claim for additional time or money due to the adverse impact of the incident and resulting investigation, and that the doctrine against equitable forfeiture did not pertain under the facts of this case. Thereafter, litigation continued with respect to a second count of the complaint; see footnote 6 of this opinion; which is not the subject of this appeal, until May 17, 2002, when the parties stipulated to the entry of a final judgment for the plaintiff with respect to the first count and to the dismissal without prejudice of the second count. This appeal followed.

The defendants claim that the trial court improperly determined that: (1) there was a justiciable controversy; (2) compliance with the notice provision was a condition precedent; and (3) the doctrine of inequitable forfeiture did not apply. We agree with the first claim and, [623]*623accordingly, do not address the remaining claims. See Crone v. Gill, 250 Conn. 476, 479 n.5, 736 A.2d 131 (1999).

We begin by setting forth the fundamental principles that guide our resolution of this appeal. Justiciability and ripeness have been referred to by our Appellate Court as related doctrines. See American Premier Underwriters, Inc. v. National R. Passenger Corp., 47 Conn. App. 384, 390 n.12, 704 A.2d 243 (1997), cert. denied, 244 Conn. 901, 710 A.2d 174 (1998); Cumberland Farms, Inc. v. Groton, 46 Conn. App. 514, 517-18, 699 A.2d 310 (1997), rev’d on other grounds, 247 Conn. 196, 719 A.2d 465 (1998); Mayer v. Biafore, Florek & O’Neill, 45 Conn. App. 554, 556-57, 696 A.2d 1282 (1997), rev’d on other grounds, 245 Conn. 88, 713 A.2d 1267 (1998); ASL Associates v. Zoning Commission, 18 Conn. App. 542, 548-49,559 A.2d 236 (1989).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larobina v. Altice Media Solutions, LLC
229 Conn. App. 791 (Connecticut Appellate Court, 2024)
Duso v. Groton
228 Conn. App. 390 (Connecticut Appellate Court, 2024)
Townsend v. Commissioner of Correction
226 Conn. App. 313 (Connecticut Appellate Court, 2024)
Markatos v. Zoning Board of Appeals
346 Conn. 277 (Supreme Court of Connecticut, 2023)
U.S. Bank National Assn. v. Rothermel.
339 Conn. 366 (Supreme Court of Connecticut, 2021)
Viking Construction, Inc. v. TMP Construction Group, LLC
338 Conn. 361 (Supreme Court of Connecticut, 2021)
Francis v. Board of Pardons & Paroles
338 Conn. 347 (Supreme Court of Connecticut, 2021)
State Marshal Assn. of Connecticut, Inc. v. Johnson
198 Conn. App. 392 (Connecticut Appellate Court, 2020)
Mendillo v. Tinley, Renehan & Dost, LLP
187 A.3d 1154 (Supreme Court of Connecticut, 2018)
Mikucka v. St. Lucian's Residence, Inc.
191 A.3d 1083 (Connecticut Appellate Court, 2018)
Mangiafico v. Town of Farmington
163 A.3d 631 (Connecticut Appellate Court, 2017)
Bruno v. The Travelers Companies
161 A.3d 630 (Connecticut Appellate Court, 2017)
State v. Montanez
88 A.3d 575 (Connecticut Appellate Court, 2014)
Fernandez v. Mohegan Tribal Gaming Authority
12 Am. Tribal Law 392 (Mohegan Gaming Disputes Trial Court, 2012)
Roger Sherman Liberty Center, Inc. v. Williams
28 A.3d 1026 (Connecticut Superior Court, 2011)
Shenkman-Tyler v. Central Mut. Ins. Co.
12 A.3d 613 (Connecticut Appellate Court, 2011)
TOWN OF TRUMBULL v. Palmer
1 A.3d 1121 (Connecticut Appellate Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
822 A.2d 196, 263 Conn. 616, 2003 Conn. LEXIS 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milford-power-co-v-alstom-power-inc-conn-2003.