Milan Gala v. Mark Harris

Louisiana Court of Appeal·Decided November 2, 2011·No. CA-0011-0654·Unknown

Opinion

STATE OF LOUISIANA

COURT OF APPEAL, THIRD CIRCUIT

11-654

MILAN GALA VERSUS MARK HARRIS

**********

APPEAL FROM THE

FIFTEENTH JUDICIAL DISTRICT COURT PARISH OF LAFAYETTE, NO. C-20085062 HONORABLE JULES DAVIS EDWARDS, DISTRICT JUDGE

**********

SHANNON J. GREMILLION

JUDGE

**********

Court composed of Oswald A. Decuir, Elizabeth A. Pickett, and Shannon J. Gremillion, Judges.

REVERSED IN PART AND RENDERED; AFFIRMED IN PART.

John H. Weinstein Thomas E. St. Germain Weinstein & St. Germain, L.L.C. 1414 N.E. Evangeline Thruway Lafayette, LA 70501 (337) 235-4001 Counsel for Defendant/Appellee: Mark Harris

Luke Edwards 1313 Lafayette St. P. O. Box 3483 Lafayette, LA 70502 (337) 233-9995 Counsel for Plaintiff/Appellant: Milan Gala

GREMILLION, Judge.

The plaintiff, Milan Gala, d/b/a Acadiana A-1 Fence Company, appeals the judgment in favor of the defendant, Mark Harris. For the following reasons, we reverse in part and render and affirm in part.

FACTUAL AND PROCEDURAL BACKGROUND In September 2008, Gala filed a petition for sums due on an open account against Harris. Gala alleged that Harris owed him $20,000.00 for a fence he partially built for Harris and his wife at their Youngsville, Louisiana home. A contract dated August 12, 2005 obligated Gala to construct a fence around the Harris home for $43,432.86. Harris paid Gala $27,650.00 as a down payment with the balance to be paid upon completion. Work on the fence began in August 2005 but was interrupted by Hurricanes Katrina and Rita. The Harrises claim that Gala never returned to finish the job, while Gala claims that he was prevented from finishing the job.

Following a one-day trial in November 2010, the trial court found a contract existed between the parties, but that the $15,782.86 balance was not due since Gala failed to complete the fence, and the contract was for the sale of a future thing that never came into existence. The trial court further found that there was never a meeting of the minds regarding certain modifications of the fence. Thus, the trial court found the contract was not modified. The trial court further found that Gala only partially performed and failed to prove that the Harrises prevented him from completing performance.

Gala filed a Motion for New Trial and to Hold in Contempt and/or Annul Judgment. The trial court denied the motions for new trial, to hold the Harrises in contempt for perjury, and to annul the judgment. Gala now appeals.1

1 Gala filed a supervisory writ with this court which was denied because the judgment on the merits was a final, appealable judgment.

ASSIGNMENTS OF ERROR

Gala assigns as error:

1. The trial court’s failure to award damages to him pursuant to substantial performance or quantum meruit.

2. The trial court’s denial of his Motion for New Trial and To Hold In Contempt and/or To Annul Judgment.

SUBSTANTIAL PERFORMANCE/QUANTUM MERUIT Gala does not dispute the trial court’s finding that the instant matter was not an open account, but instead arose in contract. The trial court based its ruling on La.Civ. Code art. 2450, which states:

A future thing may be the object of a contract of sale. In such a case the coming into existence of the thing is a condition that suspends the effects of the sale. A party who, through his fault, prevents the coming into existence of the thing is liable for damages.

The trial court stated:

The contract was for the sale of [sic] future thing. The future thing was the fabrication and installation of a fence. The plaintiff provided partial performance; but, the performance was not competed. Final payment for the future thing was due upon completion. Since the future thing was never completed the $15,782.86 has not come due. Plaintiff has failed to prove that the defendants prevented the plaintiff’s performance during the period August through December 2005.

We find the trial court legally erred in finding that the contract was for the sale of a future thing. A future thing is a thing that has yet to come into existence, such as a sale of a future crop or an unborn animal. See Frey v. Amoco Prod. Co., 603 So.2d 166 (La.1992). A nearly 90% completed fence is not a future thing. We perform a de novo review of the record and render a judgment on the merits when the trial court legally errs by applying the wrong legal standard. Lasha v. Olin, 625 So.2d 1002 (La. 1993). Substantial Performance

Gala argues that of an approximately 1300 foot fence, the portion that he did not complete was roughly a 120 foot section that included a metal frame gate. Gala claims that he made repeated attempts to complete the project, but was prevented from doing so by the Harrises. Thus, he argues that he was entitled to recover the contract price because the job was substantially completed. Gala argues that even if the contract had not been substantially completed, the trial court was required to make an award based on quantum meruit. We agree.

In disputes involving construction contracts, whether the contractor has substantially performed determines whether he will recover the full contract price. Ortego v. Dupont, 611 So.2d 792 (La.App. 3 Cir. 1992). Whether a contractor has substantially performed under the contract is a question of fact. Id. Factors to consider in determining whether substantial performance exists are “the utility to the owner of the work performed, the extent of the defect or non-performance, the degree to which the purpose of the contract is defeated, and the ease of correction.” Walter Lafargue Real Estate, Inc., v. Raines, 420 So.2d 1309, 1311 (La.App. 3 Cir. 1982). If the contractor has not substantially performed under the contract, i.e. there is unfinished work, the contractor is limited to recovery in quantum meruit, and his recovery will be reduced by the amounts the owner must expend to complete the project. Id. “The burden of proof of unfinished work or defects and the cost of completion or correction is upon the owner.” Boydstun v. Johnston, 401 So.2d 629, 631 (La.App. 3 Cir.), writ denied, 404 So.2d 1262 (La.1981).

At the conclusion of the trial, the trial court rendered oral reasons for judgment and stated:

Completion has not yet occurred, and the plaintiff has not proven one way or the – I’m not able to determine one way or the other whether the defendants prevented the plaintiff from performing during the period of August and December, or whether or not the defendant simply chose – I’m sorry, plaintiffs simply chose to not perform during that time period.

But ultimately, on the 13th of December, plaintiff notified defendant that he was dissolving the contract as a result of failing to perform, and four months of non performance is sufficient to allow the plaintiff to conclude that performance would not occur within a reasonable period of time.

....

MR. EDWARDS: Your Honor, are you making any specific finding regarding substantial completion?

THE COURT: No, I did not.

Free access — add to your briefcase to read the full text and ask questions with AI

Milan Gala v. Mark Harris, (La. Ct. App. 2011).

Milan Gala v. Mark Harris (Milan Gala v. Mark Harris) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lasha v. Olin Corp.
625 So. 2d 1002 (Supreme Court of Louisiana, 1993)
Walter Lafargue Real Estate, Inc. v. Raines
420 So. 2d 1309 (Louisiana Court of Appeal, 1982)
Frey v. Amoco Production Co.
603 So. 2d 166 (Supreme Court of Louisiana, 1992)
Ortego v. Dupont
611 So. 2d 792 (Louisiana Court of Appeal, 1992)
Boydstun v. Johnson
401 So. 2d 629 (Louisiana Court of Appeal, 1981)