Milaeger Well Drilling Co. v. Muskego Rendering Co.

85 N.W.2d 331, 1 Wis. 2d 573, 66 A.L.R. 2d 563, 1957 Wisc. LEXIS 378
CourtWisconsin Supreme Court
DecidedOctober 8, 1957
StatusPublished
Cited by2 cases

This text of 85 N.W.2d 331 (Milaeger Well Drilling Co. v. Muskego Rendering Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milaeger Well Drilling Co. v. Muskego Rendering Co., 85 N.W.2d 331, 1 Wis. 2d 573, 66 A.L.R. 2d 563, 1957 Wisc. LEXIS 378 (Wis. 1957).

Opinion

CuRRiE, J.

The brief of the defendant states the questions to be determined on this appeal to be:

(1) Did the plaintiff fulfil its contract ?

(2) If the plaintiff did not fulfil the contract, did the defendant so conduct itself so as to waive such fulfilment?

With respect to the first question, it is defendant’s contention that the contract required the plaintiff to continue drilling operations until “sufficient water” was obtained, and the plaintiff has breached the contract by not doing so. Genni v. Hahn (1892), 82 Wis. 90, 51 N. W. 1096, is cited as authority holding that plaintiff cannot recover if it committed such breach.

It is defendant’s further position that the term “sufficient water” appearing in the contract is ambiguous and subject to explanation by parol testimony. Defendant’s counsel attempted to have Wauer, president of the defendant, testify as to a conversation had between him and Milaeger, president of the plaintiff, at the time the parties were' negotiating the contract of October 1, 1951. The defendant sought thereby to establish that the parties had verbally agreed upon a definition of what was intended by use of the words “sufficient water.” The trial court sustained an objection to the question inquiring as to such conversation between the parties on the ground that to admit such testimony would violate the parol-evidence rule. The defendant then made an offer of proof to the effect that Wauer would have testified that the parties before the contract was entered into agreed that the term “sufficient water” in the contract meant a minimum of 50 gallons per minute of usable water.

We are satisfied that the trial court committed error in excluding such offered testimony. If a contract is ambigú[578]*578ous, the declarations of parties constituting the negotiations for the contract may be resorted to in aid of construction without violating the parol-evidence rule. Wheelwright v. Pure Milk Asso. (1932), 208 Wis. 40, 44, 240 N. W. 769, 242 N. W. 486. Such error, in view of the precedent of Genni v. Hahn, supra, would be prejudicial and require a new trial unless the appeal can be decided in plaintiffs favor on the second issue of waiver.

In passing on the question of whether or not the defendant by its acts effectively waived any defective performance on the part of the plaintiff, it is necessary to review the pertinent evidence bearing on this issue.

Drilling operations were commenced by the plaintiff on November 8, 1951, and, on January 8, 1952, the same were discontinued after a depth of 202 feet had been reached. The next day a bailer test was run. This disclosed that the water present was “cloudy and a bit muddy.” This is usually the condition of the water at the start of opening up a new well. Milaeger then telephoned to Wauer and informed him “It looks like we got a well,” and Wauer requested that the test by pump be run.

It was agreed between the parties that a screen should be put into the bottom of the well. This consisted of pipe six inches in diameter and 28 feet eight inches in length having holes perforated in it. Such screen was an “extra” not covered by the contract, and the $67.50 and $17.60 items in plaintiffs first statement rendered in the sum of $2,205.10 covered the same. Such screen was placed in the well on January 11, 1952, and on the same day the plaintiff attached its pump and ran the test. Such test disclosed that the well had a capacity of from 20 to 30 gallons per minute. Milaeger then offered to “develop” the well so as to get the cloudiness and sand out of the water at a cost of $10 per hour. Wauer [579]*579refused such offer and stated that he would grout the well and “develop” it with his own pump.

Milaeger, however, admitted on his adverse deposition taken before trial that Wauer was not then satisfied with the capacity of water produced by the well as disclosed by the test. The plaintiff removed its equipment from defendant’s premises on January 14, 1952, and on the same day mailed to the defendant its statement in the sum of $2,205.10, a copy of which appears in the statement of facts preceding this opinion.

The defendant possessed a turbine pump having a pumping capacity of 90 gallons per minute. The defendant had its maintenance man, one Willms, drop 120 feet of pipe, with a 10-foot “tailpiece” attached, into the well and connect the same to this turbine pump. Willms gave contradictory testimony as to how he operated such pump. While an adverse witness called by the plaintiff, he testified that he “opened” the pump up to capacity. Later, when called as defendant’s witness, he stated that he operated the pump very slowly. Willms operated the pump until it broke suction as a result of there being no more water in the well at the depth reached by the pipe attached to the pump. Then the pump was primed again and the pump operated very slowly so as not to exceed the capacity of the water present. The capacity of the well was found to be no more than 20 to 30 gallons per minute.

These pumping operations were performed by Willms in January, 1952. Nevertheless, in spite of both the pump tests made by plaintiff and Willms disclosing a well capacity of 20 to 30 gallons per minute, the defendant made its $1,000 remittance on account on February 1, 1952, by mailing a check for that amount to the plaintiff. Such check was not accompanied by any letter stating any reservation of rights [580]*580against the plaintiff. Neither did the detachable voucher attached to such check contain any reservation whatsoever.

We consider that the instant appeal is clearly ruled by our decision in Guschl v. Schmidt (1954), 266 Wis. 410, 417, 63 N. W. (2d) 759, wherein it was stated:

“While a partial or total payment on a building contract does not constitute an acceptance of the work in so far as latent defects are concerned, such a payment by the owner with knowledge of a particular defect does constitute a waiver of such defect in the absence of any other circumstances mitigating against such a waiver.”

The brief of the defendant concedes that the foregoing is a correct statement of the applicable principle of law. However, it argues that there are mitigating circumstances here present which prevent the $1,000 payment on account from constituting a waiver by the defendant of its right to claim that plaintiff had breached its contract by not drilling the well to a depth where “sufficient water” had been obtained. Such mitigating circumstances are alleged to consist of “frequent” statements by Milaeger that the well could be “developed” to produce sufficient silt-free water.

The evidence does not bear out such contention. Milaeger testified that the reason why Wauer insisted in the summer of 1952 that the well be drilled deeper was not because Wauer was dissatisfied with the capacity of the well, but rather due to the fact that the well had become clogged by sand as a result of Willms operating the turbine pump at too high a speed contrary to Milaeger’s instructions. Milaeger further testified that Wauer’s refusal to make further payments on account because of insufficient water was “long” after the defendant had “messed it up” with its turbine pump.

On the other hand, Wauer testified that, after the turbine pump became clogged with sand while Willms was operating it, Wauer called Milaeger and complained, and Milaeger [581]*581came out to defendant’s plant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Merchandising Corporation v. McAlpin
440 S.W.2d 489 (Missouri Court of Appeals, 1969)
Markman v. Hoefer
106 N.W.2d 59 (Supreme Court of Iowa, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
85 N.W.2d 331, 1 Wis. 2d 573, 66 A.L.R. 2d 563, 1957 Wisc. LEXIS 378, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milaeger-well-drilling-co-v-muskego-rendering-co-wis-1957.