Midwest Payment Systems, Inc. v. Citibank Federal Savings Bank

801 F. Supp. 9, 1992 U.S. Dist. LEXIS 14350, 1992 WL 236182
CourtDistrict Court, S.D. Ohio
DecidedAugust 31, 1992
DocketC-1-91-581
StatusPublished
Cited by7 cases

This text of 801 F. Supp. 9 (Midwest Payment Systems, Inc. v. Citibank Federal Savings Bank) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midwest Payment Systems, Inc. v. Citibank Federal Savings Bank, 801 F. Supp. 9, 1992 U.S. Dist. LEXIS 14350, 1992 WL 236182 (S.D. Ohio 1992).

Opinion

ORDER GRANTING PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT

SPIEGEL, District Judge.

This matter is before the Court on the Plaintiff Midwest Payment Systems, Inc.’s (“Midwest”) Motion for Summary Judgment (doc. 6), the Defendant Citibank Federal Savings Bank’s (“Citibank”) Motion for Partial Summary Judgment (doc. 11), Citibank’s Response (doc. 12), Midwest’s *11 Reply (doc. 14), and Citibank’s Reply (doc. 16).

BACKGROUND

On October 7, 1987, Midwest and Brook-field Federal Bank for Savings (“Brook-field”) entered into a contract. About eight months later, Midwest and Brookfield agreed to an addendum to the contract. As a result of a merger, Citibank assumed all of Brookfield’s rights and obligations under the contract and the addendum.

Pursuant to the Midwest-Citibank contract, Midwest was required to provide a data processing service known as Electronic Funds Transfer (“EFT”) for five years commencing on November 1, 1987. Under the addendum, Midwest was also required to provide data processing services known as CIRRUS Gateway Services for three years beginning on May 31, 1988. If neither party objected, the provisions in the addendum were to be automatically extended for an additional three years.

Under the contract, Midwest and Brook-field agreed that Midwest would be the exclusive provider of Midwest’s EFT requirements. Plaintiff’s Motion for Summary Judgment, doc. 6, ex. A. 1 Following Brookfield’s merger with Citibank, representatives from Citibank and Midwest discussed a possible “buy out” of Citibank’s obligations under the contract and the addendum. The talks between the two corporations were not successful, however. As a result, on July 14, 1991, Citibank began using other providers for the services which Midwest had the exclusive right to provide to Citibank under the Midwest-Citibank contract. Four days later, a Midwest Vice President wrote to Citibank that Citibank had breached the Midwest-Citibank contract, and appropriate remedies would be taken through litigation. Midwest brought suit eight days after this letter, seeking to enforce the liquidated damages remedy set forth in the contract. Plaintiff Midwest claims that under the liquidated damages provision, its damages total $290,980.08.

Citibank contends that Midwest is not entitled to damages. Citibank points to section 8 of its contract with Midwest:

(a) Default by Customer. Customer shall be in default under this Agreement upon the occurrence of any of the following events (“Events of Default”):
... (iii) In the event that customer is in default is in default of any terms or conditions of this Agreement ... whether by reason of its own action or inaction or that of another, and such default continues for 30 days after receipt of a notice from MPS [Midwest] describing such default or violation, unless within such 30 day period Customer either corrects the default or, in the opinion of MPS, initiates appropriate action to correct such default and thereafter diligently pursues to cure such default.
(b) Termination. Upon the occurrence of an Event for Default, MPS may at any time thereafter terminate this Agreement effective 60 days after notice of such termination is given by MPS to Customer. Termination of Customer for any reason shall not relieve Customer from any liability or obligation to MPS arising prior to such termination. In the event this Agreement is terminated by MPS other than at the end of the initial Term or any renewal period, Customer shall pay to MPS an amount equal to the average sum of the monthly billings payable by customer for the three calendar months immediately prior to the date of termination, multiplied by the number of months remaining during the then current term of this Agreement.

Citibank argues that Midwest did not properly notify Citibank of its default under the contract, after Citibank transferred its EFT requirements to another source.

STANDARD OF REVIEW

The narrow question that we must decide on a motion for summary judgment *12 is whether there exists a “... genuine issue as to any material fact and [whether] the moving party is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(c). The Court cannot try issues of fact on a Rule 56 motion, but is empowered to determine only whether issues exist that should be tried. In re Atlas Concrete Pipe, Inc., 668 F.2d 905, 908 (6th Cir.1982).

The moving party “has the burden of showing conclusively that there exists no genuine issues as to a material fact and the evidence together with all inferences to be drawn therefrom must be read in the light most favorable to the party opposing the motion.” Smith v. Hudson, 600 F.2d 60, 63 (6th Cir.) (emphasis in original), cert. denied, 444 U.S. 986, 100 S.Ct. 495, 62 L.Ed.2d 415 (1979). Moreover, “while the movant’s papers are to be closely scrutinized, those of the opponent are to be viewed indulgently.” Id. at 63. “[T]he District Court [is] obligated to consider not only the materials specifically offered in support of the motion, but also all ‘pleadings, depositions, answers to interrogatories, and admissions’ properly on file and thus properly before [the] court.” Id. (quoting Rule 56(c), Fed.R.Civ.P.).

Summary judgment “must be used only with extreme caution for it operates to deny a litigant his day in court.” Id. The Supreme Court elaborated upon this standard, in Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986), as follows:

[T]he plain language of Rule 56(c)' mandates the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case and on which that party will bear the burden of proof at trial....

Id. at 322, 106 S.Ct. at 2552. Summary judgment is not appropriate if a dispute about a material fact is “genuine,” that is, if the evidence is such that a reasonable jury could return a verdict for the non-moving party. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Nevertheless, conelusory allegations are not sufficient to defeat a motion for summary judgment. McDonald v. Union Camp Corp., 898 F.2d 1155, 1162 (6th Cir.1990).

DISCUSSION

In resolving the pending motion, this Court must consider a number of issues. We shall examine these in turn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Nationwide Mut. Ins. Co.
2018 Ohio 3758 (Ohio Court of Appeals, 2018)
Marlon Jackson v. State Farm Fire & Casualty Co
461 F. App'x 422 (Sixth Circuit, 2012)
Stonehenge Land Co. v. Beazer Homes Investments, L.L.C.
893 N.E.2d 855 (Ohio Court of Appeals, 2008)
Waste Management, Inc. v. Rice Danis Industries Corp.
257 F. Supp. 2d 1076 (S.D. Ohio, 2003)
Fifth Third Bank v. Cooker Restaurant Corp.
738 N.E.2d 817 (Ohio Court of Appeals, 2000)
GOVERNMENT GUAR. FUND OF FINLAND v. Hyatt Corp.
960 F. Supp. 931 (Virgin Islands, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
801 F. Supp. 9, 1992 U.S. Dist. LEXIS 14350, 1992 WL 236182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midwest-payment-systems-inc-v-citibank-federal-savings-bank-ohsd-1992.