Midtown Edge, L.P. and Midtown Condominiums, L.L.C. v. the City of Houston

Court of Appeals of Texas·Decided February 13, 2014·No. 01-12-00730-CV·Published

Opinion

Opinion issued February 13, 2014

In The

Court of Appeals

For The

First District of Texas

Edge’s suit against the City for breach of contract, inverse condemnation, declaratory judgment, and promissory estoppel. In four issues, Edge contends that the trial court erred in granting the City’s plea.

We affirm.

Background

In its petition, Edge alleges that in July 2005, it began construction of a condominium development project (the “Project”), consisting of ninety-three residential units, located in the Midtown area of Houston. After Edge applied to the City for use of its wastewater line, the City responded by letter, dated August 5, 2005, stating that a new wastewater line would need to be constructed because the existing eight-inch wastewater line in the vicinity of the Project was inadequate to accommodate the Project’s needs. In its letter, the City listed various “methods” of financing the new line, noting that it could pay for all or some of the costs of design and construction, or Edge could choose to pay the costs on its own. If the City paid any portion of the costs, a contract between the City and Edge, approved by City Council and executed by the Mayor, would be required. The City noted that other financing methods could be used, including one in which Edge could “ask” the City to establish a connection charge for any other property owner subsequently connecting to the new line. To share the cost of constructing the line, such an owner would be required to pay a pro rata charge, which would then be

forwarded to Edge. The City explained that upon “completion of the construction of the line and acceptance of the project by the City, the line will be dedicated to the City of Houston for ownership and maintenance.”

In its October 31, 2005 letter responding to the City’s letter, Edge stated that it was “not requesting City of Houston cost sharing participation,” it “underst[ood] that all cost sharing participation require[d] an approved contract by city council prior to the construction of the utility,” and it understood that “requesting such participation may result in the delay of a building permit being issued.”

Subsequently, the City issued a construction permit, and Edge constructed the new line at a cost of $224,991.02. Upon completion, Edge dedicated the new line to the City for its ownership and maintenance.

At some point, Pierce Street Flats (the “Flats”), a new apartment complex constructed in the vicinity of the Project, connected to the new line. In 2007, Edge applied to the City for reimbursement of $48,664, which it alleges was the Flats’s pro rata share of Edge’s cost to construct the new line. And Edge notified the Flats that it was responsible for a share of the construction costs of the new line. The City denied reimbursement, and the Flats disconnected from the new line and connected to the older eight-inch wastewater line.

Edge further alleges in its petition that the City’s letter concerning financing of the new line constituted “a letter agreement,” a “valid, enforceable agreement”

between the City and Edge. It asserts that the City breached its obligations “under this contract” by denying Edge’s request for reimbursement after the Flats connected to the new line. And it further alleges that the Texas Legislature has waived the City’s governmental immunity for purposes of such a breach–of– contract claim. 2 Edge argues that the City, by denying reimbursement, committed an unconstitutional “taking” because it intentionally took the new line for the benefit of the public without compensating Edge and without Edge’s consent. Edge seeks a judgment declaring that (1) it constructed the line “pursuant to a valid and enforceable contract and municipal ordinance,” not only for its own benefit, but for the benefit of the City and the public; (2) the City breached the contract by denying reimbursement; and (3) the City violated Edge’s rights under the Texas Constitution by taking Edge’s property without adequate compensation. Alternatively, Edge asserts a claim for promissory estoppel, alleging that the City made a promise, upon which Edge relied to its detriment, to reimburse Edge. Finally, Edge claims that the Flats has been unjustly enriched. 3 In its answer, the City generally denies Edge’s allegations, and it asserts that

it is immune from suit. In its second amended plea to the jurisdiction, the City 2 See TEX. LOC. GOV’T CODE ANN. § 271.152 (Vernon 2005).

3 The Flats is a named defendant in the proceedings below. However, it is not subject to the order sustaining the City’s plea to the jurisdiction, and it is not a party to this appeal.

argues that Edge’s “breach of contract claim is barred by governmental immunity from suit” because the City’s letter, “which Edge claims is the agreement upon which its breach of contract claim is based” is not a contract. The City asserts that Edge’s inverse condemnation claim is barred by immunity, and it argues that there has not been an unconstitutional “taking” because Edge consented to the City’s ownership of the new line by dedicating it to the City without objection. Further, the City asserts that Edge’s claims for declaratory relief and promissory estoppel are barred by governmental immunity.

To its plea, the City attached its letter to Edge, Edge’s letter to the City, and the affidavit of R. Moreno, the City’s Division Manager of the Department of Public Works and Engineering (the “Department”), Utilities Analysis Section. In his affidavit, Moreno testified that he reviewed the City’s records and they reveal that “since September 10, 2008, the date that Houston’s City Council . . . approv[ed] the pro-rata reimbursement, no permit has ever been issued by [the City] to any person located within the service area . . . to connect to the [new line] and no money has been collected for the benefit of [Edge] from any third party.” He noted that the City issued a permit to Black Finn Restaurant in August 2011 to connect to a terminating manhole on the new line, but the City did not collect a connection fee because the restaurant is “not located within the service area.”

The City also attached to its plea the affidavit of R. Mendez, an inspector for the Department. Mendez testified that the Flats’s contractor had inadvertently tapped into the new line, the City had not granted the Flats permission to tap into the new line, the City instructed the Flats to disconnect from the line, and the Flats complied.

Further, the City attached to its plea the affidavit of A. Sheridan, a Department Supervising Engineer, who testified that Edge did not file the documents necessary to complete its application for establishment of a pro-rata reimbursement (rate) until July 2008.4 He noted that on September 10, 2008, the City Council established a rate for connections to the New Line.

After a hearing, the trial court granted the City’s plea to the jurisdiction and dismissed Edge’s claims.

Plea to the Jurisdiction

A plea to the jurisdiction is a dilatory plea that seeks dismissal of a case for lack of subject matter jurisdiction. Harris Cnty. v. Sykes, 136 S.W.3d 635, 638 (Tex. 2004); Villarreal v. Harris Cnty., 226 S.W.3d 537, 541 (Tex. App.— Houston [1st Dist.] 2006, no pet.). We review de novo a trial court’s ruling on a jurisdictional plea. See Ben Bolt-Palito Blanco Consol. Indep. Sch. Dist. v. Texas Political Subdivisions Prop./Cas. Joint Self-Ins. Fund, 212 S.W.3d 320, 323 (Tex.

4 Edge sought reimbursement in 2007 for the connection pertaining to the Flats.

2006); City of Houston v. Vallejo, 371 S.W.3d 499, 501 (Tex. App.—Houston [1st Dist.] 2012, pet. denied).

Free access — add to your briefcase to read the full text and ask questions with AI

Midtown Edge, L.P. and Midtown Condominiums, L.L.C. v. the City of Houston, (Tex. Ct. App. 2014).

Midtown Edge, L.P. and Midtown Condominiums, L.L.C. v. the City of Houston (Midtown Edge, L.P. and Midtown Condominiums, L.L.C. v. the City of Houston) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
Town of Flower Mound v. Stafford Estates Ltd. Partnership
135 S.W.3d 620 (Texas Supreme Court, 2004)
Harris County v. Sykes
136 S.W.3d 635 (Texas Supreme Court, 2004)
City of White Settlement v. Super Wash, Inc.
198 S.W.3d 770 (Texas Supreme Court, 2006)
Mission Consolidated Independent School District v. Garcia
253 S.W.3d 653 (Texas Supreme Court, 2008)
The City of Houston v. Steve Williams
353 S.W.3d 128 (Texas Supreme Court, 2011)
Waco Independent School District v. Gibson
22 S.W.3d 849 (Texas Supreme Court, 2000)
Texas Natural Resource Conservation Commission v. IT-Davy
74 S.W.3d 849 (Texas Supreme Court, 2002)
Tooke v. City of Mexia
197 S.W.3d 325 (Texas Supreme Court, 2006)
Sefzik v. City of McKinney
198 S.W.3d 884 (Court of Appeals of Texas, 2006)
Potcinske v. McDonald Property Investments, Ltd.
245 S.W.3d 526 (Court of Appeals of Texas, 2007)
Town of Flower Mound v. Stafford Estates Ltd. Partnership
71 S.W.3d 18 (Court of Appeals of Texas, 2002)
Paciwest, Inc. v. Warner Alan Properties, LLC
266 S.W.3d 559 (Court of Appeals of Texas, 2008)
Freedman v. University of Houston
110 S.W.3d 504 (Court of Appeals of Texas, 2003)
General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)
Villarreal v. Harris County
226 S.W.3d 537 (Court of Appeals of Texas, 2006)
Prime Products, Inc. v. S.S.I. Plastics, Inc.
97 S.W.3d 631 (Court of Appeals of Texas, 2002)
Maguire Oil Co. v. City of Houston
69 S.W.3d 350 (Court of Appeals of Texas, 2002)