Midship Pipeline v. FERC

45 F.4th 867
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 18, 2022
Docket22-60225
StatusPublished
Cited by2 cases

This text of 45 F.4th 867 (Midship Pipeline v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midship Pipeline v. FERC, 45 F.4th 867 (5th Cir. 2022).

Opinion

Case: 22-60225 Document: 00516438866 Page: 1 Date Filed: 08/18/2022

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

FILED August 18, 2022 No. 22-60225 Lyle W. Cayce Clerk

Midship Pipeline Company, L.L.C.,

Petitioner,

versus

Federal Energy Regulatory Commission,

Respondent.

Petition for Review of an Order of the Federal Energy Regulatory Comm. Agency No. 177 FERC 61,186 Agency No. 178 FERC 62,100 Agency No. 178 FERC 61,202

Before Higginbotham, Haynes, and Wilson, Circuit Judges. Cory T. Wilson, Circuit Judge: Midship Pipeline Company, L.L.C. challenges part of a Federal Energy Regulatory Commission (FERC) order directing an administrative law judge to determine the “reasonable cost” for Midship to complete remediation activities at Sandy Creek Farms in Oklahoma. The FERC, like all administrative agencies, must ground its actions “in a valid grant of authority from Congress,” Food & Drug Admin. v. Brown & Williamson Tobacco Corp., 529 U.S. 120, 161 (2000), and Midship contends that the Case: 22-60225 Document: 00516438866 Page: 2 Date Filed: 08/18/2022

No. 22-60225

FERC’s governing statutes do not grant the agency authority to determine “reasonable cost” of remediation. Thus, Midship asserts the FERC’s order is ultra vires. The FERC counters that this issue is not ripe for appeal, and, in any event, its order is entitled to deference. We conclude this dispute is ripe for our review and vacate the provision of the FERC’s order requiring a determination of “reasonable cost.” We otherwise remand for further proceedings. I. On August 13, 2018, the FERC issued a certificate order under the Natural Gas Act (NGA) allowing Midship to construct and operate a 200- mile natural gas pipeline crossing privately held land in Oklahoma. 164 F.E.R.C. ¶ 61,103. Midship’s certificate, like most issued under the NGA, contained requirements related to rates, environmental analyses, and restoration of affected land. Id. Midship completed the pipeline in March 2020. 174 F.E.R.C. ¶ 61,220, 62,111. It then put the pipeline in operation and proceeded to restore land impacted by the construction. Id. A year later, the FERC directed Midship “to take immediate action to remedy unresolved restoration issues on certain landowner tracts.” Id. at 62,110. This included “[c]orrect[ing] ponding, restor[ing] preconstruction contours,” and “[r]emov[ing] known construction debris” on property held by Sandy Creek. Id. at 62,113. The FERC noted that it had previously directed Midship to address these issues, id. at 62,113 n.1, and recommended that Midship and the landowners negotiate a settlement through the FERC’s Dispute Resolution Service, id. at 62,112. The FERC caveated this suggestion by

2 Case: 22-60225 Document: 00516438866 Page: 3 Date Filed: 08/18/2022

acknowledging that if negotiations failed it lacked the authority to require Midship to compensate the landowners, id. at 62,112 n.13. 1 After several months, Sandy Creek and Midship were unable to reach a settlement. 177 F.E.R.C. ¶ 61,186. Sandy Creek filed a statement before the FERC indicating that, although its land still needed to be restored, it did not want Midship to remediate the land because Midship’s continued presence would lead to “irreparable impacts.” Id. Instead, Sandy Creek preferred a settlement that would compensate Sandy Creek for restoring its land itself. Id. In response, the FERC entered another order recognizing that Midship and Sandy Creek remained at an impasse. Id. It found that “despite general agreement as to the proper scope of the restoration work needed . . . , Midship and Sandy Creek Farms have not been able to agree on a specific plan or cost thereof.” Id. at *4. The FERC then appointed an administrative law judge (ALJ) to resolve two questions: “(1) the methods and scope of work activities remaining in order to restore the Sandy Creek Farms property in accordance with the Certificate Order . . . and (2) the reasonable cost to complete such activities.” Id. The FERC again acknowledged that it could not award damages but stated that “developing a record as to the necessary measures and their cost will assist [the FERC] in evaluating what further remediation is required and what further steps to take to resolve the issues here.” Id.

1 The landowners filed a motion for rehearing and asked the FERC to retract its statement about ordering compensation. But the FERC reiterated that it had “no authority to direct payment of compensation for damages . . . . Should Landowners seek compensation from Midship, Landowners may pursue these claims in the appropriate state court.” 175 F.E.R.C. ¶ 61,145, 61,932.

3 Case: 22-60225 Document: 00516438866 Page: 4 Date Filed: 08/18/2022

Midship filed a petition for rehearing, asserting that the FERC lacked authority to determine the “reasonable cost” of remediation. 178 F.E.R.C. ¶ 61,202, *2. The FERC denied Midship’s petition and reiterated the rationale from its prior order. Id. at *3. Roughly three weeks later, Midship filed a request for a stay with the FERC and a petition for review before this court challenging the directive that the ALJ determine the reasonable cost of remediation. Shortly thereafter, while its stay motion before the FERC remained pending, Midship requested a stay from this court pending appeal. The FERC denied Midship’s stay motion, but shortly after, we granted Midship a stay of the challenged portion of the FERC’s order. Midship Pipeline Co., L.L.C. v. Fed. Energy Regul. Comm’n, No. 22-60225, slip. op. at 1 (5th Cir. May 25, 2022) (per curiam order). We also expedited the appeal. Id. at 5. Meanwhile, the remainder of the order is in effect, and proceedings before the ALJ are ongoing. II. The NGA states that: [a]ny party to a proceeding under this chapter aggrieved by an order issued by [the FERC] in such proceeding may obtain a review of such order in the court of appeals of the United States for any circuit wherein the natural-gas company to which the order relates is located or has its principal place of business.

15 U.S.C. § 717r(b). In reviewing FERC orders pursuant to § 717r(b), we also apply the overarching appellate framework of the Administrative Procedure Act (APA), 5 U.S.C. § 701. El Paso Elec. Co. v. Fed. Energy Regul. Comm’n, 832 F.3d 495, 503 (5th Cir. 2016) (citing La. Pub. Serv. Comm’n v. Fed. Energy Regul. Comm’n, 771 F.3d 903, 909 (5th Cir. 2014)).

4 Case: 22-60225 Document: 00516438866 Page: 5 Date Filed: 08/18/2022

A. As threshold matters, the FERC first argues that this dispute is not ripe for review. Next, if it is, the FERC contends its interpretation of the NGA ought to be accorded deference under Chevron, U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837 (1984). 1. Whether an issue is ripe for appeal turns on “(1) the fitness of the issues for judicial decision; and (2) the hardship to the parties of withholding court consideration.” Gulfport Energy Corp. v. Fed. Energy Regul. Comm’n, 41 F.4th 667, 679 (5th Cir. 2022) (quoting Cochran v. Sec. & Exch. Comm’n, 20 F.4th 194, 212 (5th Cir. 2021)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayfield v. LABR
117 F.4th 611 (Fifth Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
45 F.4th 867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midship-pipeline-v-ferc-ca5-2022.